Permits & records

The paper trail.

Every figure on this site traces back to a public record. Here is the actual permit ledger — file numbers, dates and status — how the program has shifted across three rounds of city filings, and the hard numbers buried in the project's environmental review.


City permit record

Checking the city ledger…

Permit approval and visible work are separate milestones. “Ready to Issue” is not an issued permit.

Critical path · as of October 14, 2026

What has to clear before the towers can rise.

The live site can look busy while the legal path remains narrow. This map follows the records that change what work may proceed, from issued early works and shoring through the garage, podium and tower permits.

  1. 01Current authorityIssued

    Limited early grading and soil export

    • 21-133872-GD

    This issued permit authorized the limited grading and documented soil export that began before the shoring preconstruction inspection. A transportation review note limits it to early grading; the separately issued shoring permit is addressed below.

    Why this gate matters

    Visible hauling and equipment alone do not establish which permit governs an operation or that the full-site grading permit is issued.

    Public record ↗
  2. 02Program gatePending

    Resolve the pending land-use reconfiguration

    • 26-106943-LJ
    • 26-108760-DC

    The proposal to move the hotel from Tower 1 to Tower 3 received approved transportation and land-use review lines September 17–18. The reviewers still require a signed concurrency certificate at permit issuance, and both the redesign and linked concurrency records remain Pending.

    Why this gate matters

    The city ties the full-site clear-and-grade record and the Tower 1 and Tower 3 building reviews to this decision. Tower 2 is less directly affected, not approved.

    Public record ↗
  3. 03Ground gateMixed — issued / pending

    Shoring issued; full-site grading remains pending

    • 24-104334-GD
    • 21-134212-BV

    Bellevue issued the shoring permit September 3. A September 18 preconstruction inspection says shoring may start, with later city approval required on the east side at the soil-nail elevation where no easement has been granted. Eight subsequent pile inspections through October 14 are marked Ongoing without notes resolving that condition or confirming completion. Full-site clear-and-grade remains Pending October 14.

    Why this gate matters

    Track the east-side approval condition and separate full-grading permit alongside dated evidence of perimeter support.

    Public record ↗
  4. 04Structure gateIssued

    Below-grade building permit issued

    • 24-104362-BB

    Bellevue issued the P2-through-P5 building permit September 9. The permit covers the shared garage structure, but no inspection was posted under it at the October 14 check and the podium and tower packages remain Pending.

    Why this gate matters

    Confirm applicable preconstruction requirements and dated field evidence before describing permanent garage work as started; permit issuance alone is not a field milestone.

    Public record ↗
  5. 05Shared-base gatePending

    Build the podium before independent tower runs

    • 25-105052-BB

    The shared-base permit contains retail, amenity, food-and-beverage, gym, daycare, event and office uses. A structural review requested another revision September 17 while a separate structural revision line closed; the multi-tower energy analysis is coordinated through this package. The overall building permit remains Pending and distinct from every tower permit.

    Why this gate matters

    The common base is structurally upstream of the three tower superstructures, although design reviews for those packages continue in parallel.

    Public record ↗
  6. 06Vertical gatesPending

    Each tower needs its own issued building permit

    • 25-105181-BB
    • 25-105109-BB
    • 25-105295-BB

    Tower 1, Tower 2 and Tower 3 are separate building-permit packages. All three remain Pending; Tower 1 and Tower 3 are tied to the reconfiguration, while September 9 mechanical entries for Towers 2 and 3 track the shared Total Building Performance energy review through the podium package. Tower 2 also retains unresolved structural comments.

    Why this gate matters

    The first tower to rise cannot be established from an old sequencing concept. The clearest public signal will be an issued permit for that tower, not review activity alone.

    Public record ↗

Permit statuses and shoring/below-grade inspections checked October 14, 2026; review details retain their stated September dates. It is an editorial reading of stated permit relationships, not a city schedule or a forecast of field-start or issuance dates.

How to read a review · 24-104362-BB · as of August 22, 2026

A review approval is not a building permit.

Bellevue's review ledger can show meaningful technical progress without changing the legal status of the permit. This dated August example shows the distinction: several disciplines advanced while the application itself remained Pending at the cutoff.

  1. 01

    Conceptual smoke control

    Approved Aug 10

    What it means
    The named discipline review closed approved. That is evidence that this concept-level review no longer carried an open correction at that moment.
    What it does not mean
    It is not final acceptance or commissioning of an installed smoke-control system, and it does not issue the building permit.
  2. 02

    Other nonstructural reviews

    Advanced Aug 19–21

    What it means
    Utilities, transportation, land use and clearing-and-grading approved their latest reviews; the latest nonstructural building review recorded no concern.
    What it does not mean
    Those results apply to their review lines. They do not override an unresolved discipline elsewhere in the same application.
  3. 03

    Structural review

    Revision requested Aug 20

    What it means
    The structural reviewer requested another revision, and a newer structural review line remained open at the cutoff date.
    What it does not mean
    The decisive structural gate had therefore not closed even as other reviewers completed their work.
  4. 04

    Overall permit

    Pending

    What it means
    The public permit summary still listed 24-104362-BB as pending for the P2-through-P5 structure.
    What it does not mean
    No individual approval above should be described as authorization to construct the garage levels.

Status language in the steps mirrors the dated August review ledger, not today's overall status. The permit advanced to Ready to Issue on September 1 and Issued on September 9. Review activity can change independently of the permit summary, so both records must be checked before describing a legal phase change.

Review activity ↗

The ledger

Every filing, by the file number.

16 of 16
  1. 26-118368-TE · 26-118407-TJIssued / Issued

    Long steel-beam haul & PSE gas relocation

    Applied Aug 13 · issued Aug 26 and Sep 3, 2026

    Steel-haul permit 26-118368-TE was issued August 26 and describes deliveries of 64- to 96-foot steel beams to the 606 site, without establishing a delivery date, installation date or intended use. PSE/Infrasource gas permit 26-118407-TJ was issued September 3; its fuller filed scope describes a main relocation through the Onni parcel to tie an existing commercial service at neighboring 601 108th Avenue NE. These are logistics and adjacent-service records. The public scope does not establish either one as an Onni critical-path requirement, and neither substitutes for the separate grading or building permits.

    Record ↗
  2. 26-117887-BGIssued

    Excavation-pit conveyor systems

    Applied Aug 4 · status checked Oct 14, 2026

    The pit-conveyor electrical permit remains Issued in the October 14 city record. Its scope describes two 600-amp, 480-volt, three-phase systems for NW Construction; Prime Electric provides feeders and connections while Ault Electric Services connects, tests and verifies motor rotation. The Revision 1 electrical review closed Approved August 24. Issuance does not establish when the conveyors were installed or began operating, and it does not authorize the separate full-grading, podium or tower packages.

    Record ↗
  3. 26-116729-FR · 26-114882-TJReady to Issue / Issued

    Heavy-equipment fuel & telecom relocation

    Filed Jun 29–Jul 13 · Comcast field work Sep 8–9, 2026

    Two small mobilization records remain on the consolidated parcel. Fuel permit 26-116729-FR covers a fuel cube for heavy equipment and names Northwest Construction Inc. as contractor; it remains Ready to Issue and the filing does not state its capacity. Bellevue's July 29 fire approval carries grounding, labeling, setback, extinguisher and empty-before-movement conditions. Comcast right-of-way permit 26-114882-TJ lets crews access two vaults and relocate one splice case. After a July 22 attempt was tabled, a September 2 preconstruction call set overnight work for 9 p.m.–5 a.m.; inspections document Cannon crews and traffic control on both sides of 106th Avenue September 8, followed by a September 9 note that the splicing work was performed and the crew moved on. The record does not say Onni requested the move or identify it as an excavation prerequisite, so it remains adjacent utility coordination.

    Record ↗
  4. 24-104273-UEPending

    Project utility extension

    Filed Feb 2024 · status checked Oct 14, 2026

    The utility-extension permit serving the development remains Pending. Bellevue approved its Revision 3 fire review July 29 after a June 29 meeting about protecting connections and the hydrant/fire-department-connection layout. The approval requires a fire jobsite preconstruction inspection before work begins, a separate underground-private-fire-line permit and a future operational permit for private hydrants, whose maintenance and reporting remain the property owner's responsibility. The Revision 3 utility review ended August 19 with another revision request and comments uploaded to MyBuildingPermit, so the package has not yet cleared its core utility review.

    Record ↗
  5. 26-106943-LJPending

    Comprehensive reconfiguration

    Filed Apr 1 · reviews Sep 17–18 · status checked Oct 14, 2026

    This pending application would move the hotel from Tower 1 to Tower 3. Separate April reporting describes more than 400 hotel rooms and less office space, but the permit summary has no reconciled replacement schedule; the approved 257-room Tower 1 plan remains the baseline. Bellevue marked the Revision 3 transportation review Approved September 17 and land-use review Approved September 18. The transportation note requires a signed concurrency certificate on the same day as permit issuance, and the land-use note says it is waiting for concurrency. A reviewer expected issuance September 21, but the October 14 parcel record still shows both this application and linked concurrency record 26-108760-DC as Pending. Review approval and a forecast are not land-use permit issuance.

    Record ↗
  6. 26-108760-DCPending

    Concurrency gate on the reconfiguration

    Applied Apr 16 · status checked Oct 14, 2026

    A predevelopment-services record tied to the reconfiguration above. Its city note requires a new transportation-concurrency determination before 26-106943-LJ can be approved. Transportation requested a June 30 revision grouping the proposed retail, restaurant and fitness uses under the Shopping Plaza 40k–150k-square-foot trip-generation category; its second review closed July 14. September 17–18 notes on the redesign still call for a signed concurrency certificate at issuance. This linked record remained Pending October 14; a closed discipline review is not an approved determination.

    Record ↗
  7. 25-126179-BEIssued Jan 12, 2026

    Demolition

    Applied Oct 30, 2025 · issued Jan 12, 2026

    The demolition permit (expiring Jan 11, 2029); its scope notes it "replaces expired permit 21 133862 BE," the original 2021 demolition filing that had lapsed. Dickson Demolition completed removal of the former John Danz Theatre and the former Belle Lanes / Barnes & Noble building in spring 2026.

    Record ↗
  8. 26-114797-BG · 26-114355-BF · 26-111760-TJIssued / closed / closed

    Temporary power & site utilities

    Status checked Oct 14, 2026

    The larger temporary construction-power permit 26-114797-BG is now Issued. Its scope covers a 2,500-amp and a 4,000-amp 480-volt three-phase service plus a power skid for lights, tools and a portable office. The smaller temporary-service permit 26-114355-BF was issued June 17 and finaled June 25; the wireless-cabinet relocation 26-111760-TJ was finaled August 3. Both read Closed in the reviewed record. Electrical issuance alone does not establish that the new service has been energized.

    Record ↗
  9. 25-105052-BB · 25-105181-BB · 25-105109-BB · 25-105295-BBPending

    Superstructure: podium + three towers

    Filed Feb–Mar 2025 · status checked Oct 14, 2026

    Onni filed the superstructure as four separate building permits, each still Pending: the podium (25-105052-BB), Tower 1 residential + hotel (25-105181-BB), Tower 2 residential (25-105109-BB), and Tower 3 office shell-and-core (25-105295-BB). The podium's Revision 3 structural review requested another revision September 17 while a separate Revision 5 structural line closed that day; these are different review cycles. Earlier fire and nonstructural correction lines also remain part of the record. The project's multi-tower Total Building Performance energy documentation is coordinated through the podium package, with Tower 2 and Tower 3 mechanical revisions requested September 9. Tower 3's utility review closed Approved September 4 but bars connection until the pending 24-104273-UE extension is built and accepted; a Tower 3 fire review requested another revision September 17. The pending 2026 hotel relocation still affects Tower 1 and Tower 3. None of these discipline entries issues a podium or tower permit.

    Record ↗
  10. 21-134212-BVIssued

    Mass excavation & shoring

    Issued Sep 3 · pile inspections Sep 28–Oct 14, 2026

    Bellevue issued mass-excavation and shoring permit 21-134212-BV September 3. Its September 18 building preconstruction inspection is marked Partial with Corrections, but the inspector expressly wrote that shoring may start. The note requires city approval on the east side when shoring reaches the elevation needing soil nails where no easement has been granted. The people record names ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis as contractor-of-record under registration ONNI11A780MN, without identifying a specialist shoring subcontractor. Eight pile inspections dated September 28 and 29 and October 2, 5, 6, 7, 12 and 14 are marked Ongoing, with no notes. They document shoring inspection activity, without confirming a completed wall, satisfaction of the east-side condition or construction of permanent tower foundations. Full clear-and-grade permit 24-104334-GD remains Pending.

    Record ↗
  11. 24-104334-GDPending

    Full-site clear & grade

    Applied Feb 29, 2024 · status checked Oct 14, 2026

    The separate clear-and-grade application for the full three-tower, podium and below-grade development remains Pending. It is distinct from issued early-works permit 21-133872-GD and the now-issued shoring permit 21-134212-BV. Bellevue's parcel record describes 24-104334-GD as the clear-and-grade permit for the complete development. Its land-use and transportation review lines remain tied to the pending 2026 reconfiguration, and its June Revision 2 clearing-and-grading review requested another revision. The September 18 shoring preconstruction note does not change the status of this separate grading application.

    Record ↗
  12. 21-133872-GD · 22-104918-UEIssued Dec 23, 2025

    Early-works package

    Issued Dec 2025 · latest job conference Sep 24, 2026

    The authority now supporting visible earth removal is early-works clear-and-grade permit 21-133872-GD, issued December 23, 2025 with the city description "Early works clear and grade permit for mass excavation." Its public people record names Gary Merlino Construction Co. as contractor; that does not award Merlino the separate perimeter-shoring package. After preconstruction conferences April 1 and June 17, crews progressed from slab removal into broad shallow earthwork. Bellevue recorded a July 14 erosion-control inspection as Partial with Corrections, directing catch-basin inserts along 106th Avenue NE, and a July 20 follow-up as Ongoing. At a third job conference July 28, the inspector wrote: "Maintain mechanical street sweeper while exporting soils." That confirms soil export and a street-tracking control, but not the material's destination or contamination classification. A September 24 erosion-control job conference is marked Completed with no note; it does not record a change to the permitted scope. A transportation review note still limits this permit to "early grading only" and says full on-site grading was not approved under it. The package also includes fire-hydrant-relocation permit 22-104918-UE, issued December 2, 2025.

    Record ↗
  13. 24-104362-BBIssued

    Below-grade structure (P2–P5)

    Filed Feb 29, 2024 · issued Sep 9, 2026

    Bellevue issued the parking-level P2-through-P5 building permit on September 9, with a permit expiration of September 8, 2029. Its scope covers the shared below-grade structure for the three towers and podium. The current people record names ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis as contractor-of-record under registration ONNI11A780MN; it does not name a concrete or other specialist subcontractor. No inspection was posted under this permit at the October 14 check. Issuance is the legal milestone that supersedes the August Pending and September 1 Ready to Issue statuses, but it does not establish that permanent garage work has begun or authorize the separate podium and tower packages.

    Record ↗
  14. 24-113252-LJClosed — finaled Feb 11, 2026

    Plan refinement

    Applied Jun 2024 · finaled Feb 11, 2026

    A 2025 update — now closed and issued — that cut below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to about 532, and relocated the central energy plant to Tower 1.

    Record ↗
  15. 19-104024-LP · 19-104023-LDApproved 2022

    Master Development Plan, SEPA & Design Review

    Approved Jun 23, 2022

    The combined Master Development Plan / SEPA review (19-104024-LP) and Design Review (19-104023-LD) for the three-tower scheme, filed in early 2019 and approved with conditions on June 23, 2022. The environmental review ended in a Determination of Non-Significance (DNS). The block is zoned DNTN-O1 (Downtown Office 1).

    Record ↗
  16. 18-108805-DB · 18-111104-DCClosed

    Pre-application records

    Filed spring 2018

    The block's modern entitlement trail begins here: a pre-application record to "construct mixed use development" (18-108805-DB, applied Mar 21, 2018) and a design-conference record (18-111104-DC, applied Apr 16, 2018), both preceding the January 2019 land-use filings.

    Record ↗

Reporting on a spring 2026 Bellevue Downtown Association briefing itemized the then-current early-works status: three permits described as issued — a hydrant relocation, the demolition permit, and an early-works clearing-and-grubbing permit — with the shoring permit still in revisions. That account is a dated, single-source snapshot. Bellevue subsequently issued shoring permit 21-134212-BV on September 3 and below-grade permit 24-104362-BB on September 9; full-site clear-and-grade remains Pending. Source ↗

Change-log

How the program has shifted.

Element2022 approved2025 refinement2026 proposed
Tower heights53 / 54 / 45 stories——
Hotel257 rooms, Tower 1refinement does not restate countpending move to Tower 3; no city-approved count published
Residences425 + 634 = 1,059refinement does not restate countreporting says >1,300; not an amended approval
Office871,818 sf, Tower 3refinement does not restate areareporting says ~896,000 sf; pending proposal would reduce it
Daycare9,532 sf9,532 sf9,532 sf
Parking2,479 / 7 levels1,712 / 5 levels—
Bike storage—~532 stalls—
Energy plant—→ Tower 1—

The 2019 SEPA checklist, 2022 approval, 2025 refinement, 2026 reporting and pending reconfiguration are different evidence versions. The 2025 public permit description does not publish replacement unit, room or office totals, and the pending application has no reconciled city-approved floor schedule in the records reviewed here.

By the primary record

The numbers in the environmental file.

Gross floor area
3,507,371 sf
2019 program, three towers on a podium
Site area
174,914 sf
4.01 acres; the pre-demolition block was over half surface parking
Excavation
≈356,853 cu yd
soil removed for the below-grade garage
Demolished
≈68,100 sf
≈27,900 sf retail + 40,245 sf “church” — the Belle Lanes/Barnes & Noble building and former John Danz Theatre
Impervious surface
≈98% → ≈95%
≈171,311 → ≈166,662 sf; plazas and landscaping replace surface parking
PM peak trips
1,741 net new
619 in / 1,122 out (Transpo Group, 2019)
Groundwater
65–87 ft
below grade, in on-site monitoring wells
Projected workers
≈3,010–4,013
office, hotel & retail
Projected residents
≈3,132
in the residential portion
Lifecycle GHG footprint
≈2,992,382 MTCO₂e
gross 2019 estimate — embodied + energy + transport, before sustainability measures

Heating-oil tank under Belle Lanes

A 2017 Phase I assessment flagged a possible abandoned heating-oil underground storage tank: tax-assessor records show the Belle Lanes bowling alley ran an oil-burning furnace, with no record of the tank being decommissioned.

A dry-cleaning solvent plume

A known release of the dry-cleaning solvent PCE from the former “Thinker Toys” site at NE 8th & 106th has migrated down-gradient into soil and groundwater beneath part of the block.

SEPA record · Stormwater

Where the runoff goes: west to Meydenbauer Bay.

The 2019 SEPA checklist describes a project that keeps the block's existing drainage pattern rather than rerouting it: site and building runoff is gathered in area drains and catch basins and discharged into the public storm system in 106th Ave NE. From there it follows the path it already takes — west through 106th Ave NE storm laterals (generally 12-inch, with one 24-inch) into the 54-inch Meydenbauer storm-drain trunk main, which the applicant calls “non-capacity constrained,” running along NE 2nd Street, Bellevue Way NE and Main Street before discharging directly to Meydenbauer Bay, an arm of Lake Washington about 0.8 mile west.

On water quality, the checklist commits to managing stormwater from the new impervious surfaces per the 2017 City of Bellevue Storm and Surface Water Engineering Standards, and notes that “non-infiltrating bioretention planters” will be used to manage runoff on site. The “non-infiltrating” qualifier is the operative detail: because the block sits over a solvent plume being addressed through an independent cleanup enrolled for Ecology technical review, as well as dense glacial till, the planters are lined so runoff doesn't soak into the ground.

The impervious-cover math is why the filing treats flow control lightly: the site is already about 98% impervious (~171,311 sf, the pre-demolition block being largely surface parking), and the towers-on-a-podium scheme actually drops that to about 95% (~166,662 sf) as plazas and landscaping replace asphalt. Two regulatory backstops still apply: City stormwater review under Bellevue's NPDES Phase II municipal permit (Meydenbauer Bay drains to Lake Washington), and a state Construction Stormwater General (NPDES) permit from Ecology governing discharges during the deep excavation.

Discharge point
Meydenbauer Bay
via 106th Ave NE laterals → 54-in trunk main; an arm of Lake Washington ~0.8 mi west
Trunk main
54-inch
“non-capacity constrained”; runs NE 2nd St → Bellevue Way NE → Main St
On-site GSI
Non-infiltrating bioretention planters
lined — manage runoff without infiltrating, over the plume and glacial till
Construction permit
NPDES Construction Stormwater General Permit
required from WA Ecology for the excavation phase
Source ↗

Construction haul routes

Hauling the dig: tens of thousands of truckloads.

The single hardest number in the project's environmental record is the dirt: the 2019 SEPA checklist puts overall excavation at roughly 356,853 cubic yards, with only minimal fill brought back. The checklist never tallies the resulting truck trips, so the count is an estimate, not a project figure — but the arithmetic is unavoidable. At roughly 12–15 cubic yards per loaded tandem dump truck, that volume works out to on the order of 24,000–30,000 loaded truckloads over the life of the dig (a wider plausible range is ~20,000–36,000), each a round trip on city streets. Some spoil is not clean fill: the record flags a likely abandoned heating-oil tank under the old Belle Lanes and a migrated dry-cleaning-solvent (PCE) plume, with any contaminated soil removed to permitted off-site disposal under state and local rules.

Where those trucks may drive is constrained by city code. The block fronts 106th Avenue NE between NE 6th and NE 8th Streets, but 106th is not one of Bellevue's designated truck routes: under Bellevue City Code 11.70.060, trucks over eight feet wide, 30 feet long, or 32,000 pounds — plus anything carrying hazardous cargo — are confined to the state highway system or a short list of authorized routes, which on this side of downtown run along 108th and 112th Avenues NE rather than 106th. In practice loaded haul trucks are expected to reach a designated route or I-405 by the most direct path.

Bellevue handles that through right-of-way permitting. Hauling, parking and staging in the public right-of-way require a Commercial Right-of-Way Use permit, and a Traffic Control Plan is a required submittal — the document in which haul routes, lane and sidewalk closures and flagging are spelled out and approved by the city. Standard conditions keep abutting businesses and residents accessible and bar closing the sidewalks on both sides of a block at once. Dust and tracking are addressed on the environmental side: the checklist commits to Puget Sound Clean Air Agency dust rules and sprinklering during demolition and to a Temporary Erosion and Sedimentation Control plan.

Excavation volume
≈356,853 cu yd
2019 SEPA checklist; minimal fill returned
Estimated loaded truckloads
≈20,000–36,000
independent estimate, not a project figure (≈356,853 cu yd ÷ ~10–18 cy/truck)
Frontage street
106th Ave NE (NE 6th–NE 8th)
NOT a designated truck route under BCC 11.70.060
Restricted-truck threshold
>8 ft wide / >30 ft / >32,000 lb
confined to highways or authorized routes (108th/112th Ave NE)
Permit for hauling/staging
Commercial ROW Use permit
Traffic Control Plan is a required submittal
Source ↗

Design review · Conditions of approval

Five departures, and public access locked in forever.

The June 2022 Master Development Plan and Design Review approval (19-104024-LP & 19-104023-LD) came with conditions that shape the project in detail. The city granted five Administrative Departures from the Land Use Code under LUC 20.25A.030.D, all approved: a build-to-line departure, a compact-parking departure, planter strips in lieu of tree pits, a weather-protection departure, and a reduction in required open space. The compact-parking departure let the design use 61% compact stalls (about 1,517) against a 65% code maximum. The open-space departure shaved the on-site public plaza from the code-required 10% of the site (17,491 sf) to 9.75% (17,069 sf) — justified because the project already dedicates a Major Public Open Space and a 30-foot Grand Connection segment; counting all plaza types, the staff report says it provides over 43,177 sf, about 25% of the site.

Several conditions lock in public access in perpetuity: Onni must record legal agreements with King County guaranteeing 24-hour public access within the 30-foot Grand Connection section (condition 40), the Major Public Open Space (condition 41), and the east–west through-block pedestrian connection (condition 39, which also requires directional signage at every access point), plus a public-access easement keeping the outdoor plazas "open to the public at all times" (condition 42).

The reason those agreements are mandatory rather than voluntary lies in Bellevue's Amenity Incentive System: under LUC 20.25A.175, any property within the Grand Connection or a Major Public Open Space must be placed under a recorded agreement granting the public a "nonexclusive right of pedestrian use and access" — an obligation tied to earning bonus floor-area ratio through LUC 20.25A.070, executed before a certificate of occupancy issues. A separate condition (47) grants no signage approvals up front: before any occupancy, tenant-improvement or sign permit, Onni must submit a complete sign package consistent with Bellevue City Code 22B.10, with signs forming "an integral part of the overall architectural design."

Administrative Departures
5 granted
build-to line, compact parking, planter strips, weather protection, open space
Compact parking
61% (~1,517 stalls)
against a 65% code maximum
On-site public plaza
9.75% (17,069 sf)
departure from the 10% / 17,491 sf requirement
Total open space
>43,177 sf (~25%)
all plaza types, incl. Major Public Open Space + Grand Connection
Public access
24-hour, recorded with King County
conditions 39–42; tied to bonus FAR (LUC 20.25A.175)
Source ↗

SEPA record · Transportation

Inside the traffic study: concurrency, six intersections, and a 56-foot frontage.

The project's transportation review runs deeper than the headline trip count. Transpo Group's Traffic Impact Analysis (November 20, 2020) evaluated six intersections — Bellevue Way NE/NE 8th, 106th Ave NE at NE 8th, NE 4th and NE 6th, 108th Ave NE/NE 8th, and Lincoln DW/NE 8th — and the city found all would remain at level of service E or better with the project's improvements in place. For Bellevue's concurrency test under the Traffic Standards Code (BCC 14.10), the project was modeled at roughly 1,356 new PM-peak trips and assigned via the city's EMME-2 model; all 14 Mobility Management Areas met their standards, so it received a Certificate of Concurrency. The 1,356 concurrency figure is lower than the 1,741 gross PM-peak generation total — the record doesn't explain the gap, but it likely reflects pass-by and internal-capture credits.

The underlying trip-generation memo (Transpo Group, January 9, 2019) built the 1,741 figure from Bellevue impact-fee trip rates, by use: office 919 trips, residential 533, retail and food court 137, hotel 107, daycare 93 and restaurant 42, minus credits for the existing retail (68) and church (22) removed. The daycare's 12.34 trips per 1,000 sf is the highest per-square-foot rate of any use. (One wrinkle: the trip memo modeled a rounded "1,300 dwellings," slightly above the 1,289-unit count cited elsewhere in the same filing.) Because the code carries no parking ratio for hotel, daycare or fitness, Transpo prepared dedicated demand studies — the hotel at 0.55 vehicles per occupied room (141 vehicles for 257 rooms), the daycare at 0.24 per student (12 vehicles for 52 students), and the gym via a separate March 2021 Fitness Center Parking Analysis.

As mitigation, the approval requires Onni to widen 106th Ave NE along its frontage to a future 56-foot, five-lane cross-section up to NE 8th St, with a minimum 15-foot sidewalk separated by a 5-foot planter strip and a rebuilt transit stop. The site provides thirteen off-street loading stalls — twelve sized for an SU-30 truck and one for a WB-40 semi — fed from a shared east-side service lane that also serves loading and refuse for the neighboring Symetra and Key Center towers, which hold an access easement across the block. Non-freight access is separate: a daycare drop-off on Level 0 and a 150-foot rideshare/drop-off pullout on Level 1, with plan sheets explicitly labeling "Uber drop-off" zones. Before initial occupancy the owner must record a city-approved Transportation Management Program under BCC 14.60.070, and pays Bellevue transportation impact fees at building-permit issuance.

Intersections studied
6 (all LOS E or better)
Transpo Group TIA, Nov 20, 2020
Concurrency trips
~1,356 PM-peak
EMME-2 model; Certificate of Concurrency issued
Loading stalls
13 (12 SU-30 + 1 WB-40)
shared east service lane w/ Symetra & Key Center
106th Ave NE frontage
widened to 56 ft, 5 lanes
15-ft sidewalk + 5-ft planter; matching Artise widening to the north
TDM
recorded TMP (BCC 14.60.070)
required before initial occupancy
Source ↗

Civic data · Assessed value

King County assesses the cleared block near $140 million — almost all land.

The entire Onni 606 site is carried by the King County Assessor as a single consolidated parcel, 154410-0214, with a situs address of 680 106th Ave NE and a lot size of 174,913 square feet (about 4.02 acres). The Assessor lists the taxpayer of record as ONNI 106TH AVE BELLEVUE LLC, still under the legacy name “Barnes and Noble Bookstore and Doxa John Danz Building.”

For the 2025 valuation (2026 tax year) the Assessor sets the total appraised value at $139,931,400 — $139,930,400 of it land and just $1,000 improvements, so almost the entire assessed value sits in the land. The total has held flat at $139,931,400 across the 2024–2026 tax years, up from $135,558,500 for 2023.

A land base of roughly $140 million implies a sizable annual property-tax obligation — on the order of $1 million at Bellevue's commercial levy rates — though the exact billed amount is published separately by King County Treasury. As the towers rise, expect the improvement value (now $1,000) to climb sharply in future assessment rolls.

The single consolidated parcel was legally created by a City of Bellevue Boundary Line Adjustment: the Assessor's legal description reads "CHERITON FRUIT GARDENS PLAT #1 PCL '1' OF BELLEVUE BLA #19-104027 LW REC #20210315900014" — Parcel 1 of BLA file 19-104027-LW, recorded March 15, 2021, which folded the block's formerly separate lots into one development parcel (the previously separate 620 106th Ave NE parcel, 154410-0217, now returns no Assessor data, consistent with the merger). The 2019 acquisition is recorded as a bargain-and-sale deed under King County excise number 2973252, dated February 12, 2019, transferring title from Sterling Realty Organization Co. for $116,000,000. On financing, the DJC reported in June 2026 that "just over a year ago, Wells Fargo agreed to provide a $53.5 million loan to Onni" — placing it around mid-2025 and framed as money to "help get the job started," so it reads as an early-works or predevelopment facility rather than the full construction loan a build of this scale will ultimately require.

Assessor parcel
154410-0214
situs 680 106th Ave NE, Bellevue
Lot size
174,913 sf (≈4.02 ac)
single consolidated parcel for the assemblage
Parcel created by
BLA 19-104027-LW
recorded #20210315900014, Mar 15, 2021
Appraised value (2026 tax year)
$139,931,400
valued year 2025; flat across 2024–2026
Land vs. improvements
$139,930,400 land / $1,000 improv.
≈100% land — the block is cleared
Recorded financing
$53.5M Wells Fargo loan
~mid-2025; framed as early-works/predevelopment
Taxpayer of record
ONNI 106TH AVE BELLEVUE LLC
listed under the legacy “Barnes and Noble… John Danz” name
Source ↗

Sources

Independent and not affiliated with Onni Group. Figures are drawn from public City of Bellevue and Washington Ecology records and are subject to change as the project is permitted.