26-118368-TE · 26-118407-TJPending / pending
Long steel-beam haul & PSE gas relocation
Applied Aug 13 · steel-haul review approved Aug 21, 2026
Two new right-of-way applications explain part of the street-side mobilization around the block. Street-use permit 26-118368-TE plans deliveries of steel beams measuring 64 to 96 feet to the "606 site"; Bellevue approved its first right-of-way review August 21, but the permit remains Pending and publishes no delivery date, route, beam count or intended use. Utility permit 26-118407-TJ has PSE and contractor Infrasource cutting and capping an existing 1¼-inch main, installing a new 4-inch main for 425 feet in a general-contractor-provided trench on private property, and making a 3-by-5-foot sidewalk cut before tying the existing commercial service at neighboring 601 108th Avenue NE. Its first right-of-way review remains Open. The gas work is therefore an adjacent-service relocation coordinated through the Onni parcel, not evidence of a new tower gas connection; neither filing authorizes the still-pending shoring or below-grade structure.
Record ↗26-117887-BGPending
Excavation-pit conveyor systems
Applied Aug 4 · Revision 1 electrical review approved Aug 24, 2026
An electrical application for two 600-amp, 480-volt, three-phase conveyor-belt systems described as pit conveyors for NW Construction. The filing says Prime Electric will provide the feeders and connections under the temporary-power plan, while permit contractor Ault Electric Services will connect, test and verify rotation of the motors. Bellevue requested a revision August 11 seeking an item-by-item resubmittal and NRTL listing information for the Systems Interface Inc. control panels—or a field evaluation after installation if the panels are not listed. The Revision 1 electrical review closed Approved August 24 without a new public note, but the permit itself remains Pending and publishes no belt dimensions, capacity, layout or installation date. The discipline approval is excavation-logistics progress, not authority for the still-pending perimeter shoring or below-grade structure.
Record ↗26-116729-FR · 26-114882-TJReady to issue / issued
Heavy-equipment fuel & telecom relocation
Filed Jun 29–Jul 13 · fuel ready to issue by Aug 12, 2026
Two small July mobilization records on the consolidated parcel. Fuel permit 26-116729-FR, applied July 13, covers a fuel cube for heavy equipment and names Northwest Construction Inc. as contractor; the filing does not state its capacity. Bellevue approved its first fire review July 29 with conditions including a separate electrical-grounding permit, required grounding and labeling, setbacks, extinguishers and an empty unit before movement. By August 12 the permit had advanced to Ready to Issue—approved but not yet issued. Right-of-way permit 26-114882-TJ, applied June 29 and issued July 13, lets Comcast access two vaults and relocate one splice case. At a July 22 job-start inspection, no work crew had arrived and a Cannon representative said the splice-case audit would be tabled; TCS and flaggers were present to maintain pedestrian access. The Comcast record does not say the move is required by Onni, so it remains adjacent utility-coordination evidence rather than a confirmed excavation prerequisite.
Record ↗24-104273-UEPending
Project utility extension
Filed Feb 2024 · utility revision requested Aug 19, 2026
The utility-extension permit serving the development remains Pending. Bellevue approved its Revision 3 fire review July 29 after a June 29 meeting about protecting connections and the hydrant/fire-department-connection layout. The approval requires a fire jobsite preconstruction inspection before work begins, a separate underground-private-fire-line permit and a future operational permit for private hydrants, whose maintenance and reporting remain the property owner's responsibility. The Revision 3 utility review ended August 19 with another revision request and comments uploaded to MyBuildingPermit, so the package has not yet cleared its core utility review.
Record ↗26-106943-LJPending
Comprehensive reconfiguration
Filed Apr 1, 2026
A pending application to comprehensively reconfigure the development; per the city description, the primary change relocates the hotel from Tower 1 to Tower 3. Separate April 2026 reporting describes more than 400 hotel rooms and a reduced office component, but the pending permit summary does not publish a replacement room count or reconciled program schedule. Not yet approved — the current approved plan still places 257 hotel rooms in Tower 1. Bellevue requested Revision 2 changes from land use August 7. Transportation's August 6 note says the applicant's responses and changes satisfy that reviewer's concerns, but updated plans still must show them; a third land-use and transportation review cycle is now Open. A linked predevelopment record (26-108760-DC) supplied the concurrency determination, but the reconfiguration itself remains Pending.
Record ↗26-108760-DCPending
Concurrency gate on the reconfiguration
Applied Apr 16 · reviewed Jul 14, 2026
A predevelopment-services record tied to the reconfiguration above. Its city note is explicit: "A new transportation concurrency determination will be required," and a concurrency application must be submitted "prior to approval of 26 106943 LJ." Transportation requested a June 30 revision grouping the proposed retail, restaurant and fitness uses under the Shopping Plaza 40k–150k-square-foot trip-generation category; the second transportation review closed July 14. The permit itself still reads Pending, so that closed review line is procedural progress rather than an approved concurrency determination.
Record ↗25-126179-BEIssued Jan 12, 2026
Demolition
Applied Oct 30, 2025 · issued Jan 12, 2026
The demolition permit (expiring Jan 11, 2029); its scope notes it "replaces expired permit 21 133862 BE," the original 2021 demolition filing that had lapsed. Dickson Demolition completed removal of the former John Danz Theatre and the former Belle Lanes / Barnes & Noble building in spring 2026.
Record ↗26-114797-BG · 26-114355-BF · 26-111760-TJReady to issue / closed / closed
Temporary power & site utilities
May–Aug 2026
The first field-mobilization permits after demolition. A temporary electrical service (26-114355-BF) was applied for and issued the same day — June 17, 2026 — then finaled June 25 and now reads Closed. The larger temporary construction-power permit (26-114797-BG, applied June 26) installs a 2,500-amp and a 4,000-amp 480-volt three-phase service drawn from the PSE transformers, plus a power skid for site lights, tools and a portable office. Its electrical review was approved July 7 and the permit remains Ready to Issue—approved but not issued. Separately, right-of-way permit 26-111760-TJ removed a wireless equipment cabinet from a city streetlight pole "to accommodate" the development; Bellevue finaled it August 3 and its status now reads Closed.
Record ↗25-105052-BB · 25-105181-BB · 25-105109-BB · 25-105295-BBPending
Superstructure: podium + three towers
Filed Feb–Mar 2025 · podium utility reviews approved Aug 24, 2026
Onni filed the main superstructure as four separate building permits, each still pending in 2026: the podium (25-105052-BB, applied Feb 27 — its scope lists the shared base uses "including retail, amenity, F&B, gym, daycare, event, office"), Tower 1 residential + hotel (25-105181-BB, applied Mar 3, roof at level 58), Tower 2 residential (25-105109-BB, applied Feb 28, roof at level 59), and Tower 3 office shell-and-core (25-105295-BB, applied Mar 4, roof at level 47). On August 24, the podium's Revision 3 and Revision 4 utility reviews both closed Approved; its Revision 3 transportation review closed with a note that transportation review would be completed under Revision 4. Those are review-path movements, not issuance: the podium and all three tower permits remain Pending. The permits frame tower work as starting above the level-5 podium; how the roof-level numbering reconciles with the marketed 53/54/45 story counts isn't spelled out. Tower 1 and Tower 3 reviews are held "pending approval" of the 2026 reconfiguration (26-106943-LJ), while Tower 2 is tied to the approved 2024 land-use update but still has unresolved structural comments. The podium is built first by necessity; among the towers, the first permit to change from Pending to Issued will be the clearest public signal of which tower can proceed first.
Record ↗21-134212-BVPending
Mass excavation & shoring
Applied Dec 14, 2021 · Revision 15 in review Aug 2026
The permit that gates full mass excavation and perimeter shoring, applied December 14, 2021 and still pending August 22, 2026, alongside the below-grade structure permit 24-104362-BB. Its public people record lists Jon O'Hare as applicant but no contractor, so recurring speculation that Malcolm Drilling has the shoring package is not confirmed by the city file. Limited early excavation can continue under issued early-works permit 21-133872-GD. The shoring application is now on Revision 15: land use and utilities approved their latest reviews August 18, while clearing-and-grading approved and transportation recorded no concern August 19. Structural and geotechnical reviews of Revision 15 remain In Review after both disciplines requested corrections on Revision 14 on August 7. A condition of approval also bars soil nailing or shoring beneath a street, sidewalk or utility easement without a recorded indemnification agreement protecting the city.
Record ↗24-104334-GDPending
Full-site clear & grade
Applied Feb 29, 2024
The separate clear-and-grade application for the full three-tower, podium and below-grade development remains Pending. It is distinct from issued early-works permit 21-133872-GD, which supports the limited grading and soil export now visible on site. Bellevue's parcel record describes 24-104334-GD as the clear-and-grade permit for the complete office-and-residential development. Its land-use and transportation review lines remain pending the 2026 reconfiguration, and its June Revision 2 clearing-and-grading review requested another revision. Until it is issued, the early-works approval should not be read as unrestricted authority for the full excavation.
Record ↗21-133872-GD · 22-104918-UEIssued Dec 23, 2025
Early-works package
Issued Dec 2025 · soil-export conference Jul 28, 2026
The authority now supporting visible earth removal is early-works clear-and-grade permit 21-133872-GD, issued December 23, 2025 with the city description "Early works clear and grade permit for mass excavation." Its public people record names Gary Merlino Construction Co. as contractor; that does not award Merlino the separate, still-pending perimeter-shoring package. After preconstruction conferences April 1 and June 17, crews progressed from slab removal into broad shallow earthwork. Bellevue recorded a July 14 erosion-control inspection as Partial with Corrections, directing catch-basin inserts along 106th Avenue NE, and a July 20 follow-up as Ongoing. At a third job conference July 28, the inspector wrote: "Maintain mechanical street sweeper while exporting soils." That confirms soil export and a street-tracking control, but not the material's destination or contamination classification. A transportation review note still limits this permit to "early grading only" and says full on-site grading was not approved under it. The package also includes fire-hydrant-relocation permit 22-104918-UE, issued December 2, 2025.
Record ↗24-104362-BBPending
Below-grade structure (P2–P5)
Filed Feb 29, 2024 · latest reviews Aug 21, 2026
The permit for parking levels P2 through P5 remains Pending, with Bellevue now listing an August 28 application expiration. Its August review burst cleared substantial nonstructural ground: fire and conceptual smoke control approved August 10; utilities approved August 19; transportation approved August 20 after determining that 5,561 square feet of ancillary residential storage produces no separate impact fee; and land use plus clearing-and-grading approved August 21. The structural gate is still open. A structural review requested another revision August 20 and a newer structural review line remains Open, while the latest nonstructural building review recorded no concern August 21. Early excavation, beam-haul planning and pit-conveyor filings do not mean this garage permit has been issued.
Record ↗24-113252-LJClosed — finaled Feb 11, 2026
Plan refinement
Applied Jun 2024 · finaled Feb 11, 2026
A 2025 update — now closed and issued — that cut below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to about 532, and relocated the central energy plant to Tower 1.
Record ↗19-104024-LP · 19-104023-LDApproved 2022
Master Development Plan, SEPA & Design Review
Approved Jun 23, 2022
The combined Master Development Plan / SEPA review (19-104024-LP) and Design Review (19-104023-LD) for the three-tower scheme, filed in early 2019 and approved with conditions on June 23, 2022. The environmental review ended in a Determination of Non-Significance (DNS). The block is zoned DNTN-O1 (Downtown Office 1).
Record ↗18-108805-DB · 18-111104-DCClosed
Pre-application records
Filed spring 2018
The block's modern entitlement trail begins here: a pre-application record to "construct mixed use development" (18-108805-DB, applied Mar 21, 2018) and a design-conference record (18-111104-DC, applied Apr 16, 2018), both preceding the January 2019 land-use filings.
Record ↗