26-118368-TE · 26-118407-TJIssued / Issued
Long steel-beam haul & PSE gas relocation
Applied Aug 13 · issued Aug 26 and Sep 3, 2026
Steel-haul permit 26-118368-TE was issued August 26 and describes deliveries of 64- to 96-foot steel beams to the 606 site, without establishing a delivery date, installation date or intended use. PSE/Infrasource gas permit 26-118407-TJ was issued September 3; its fuller filed scope describes a main relocation through the Onni parcel to tie an existing commercial service at neighboring 601 108th Avenue NE. These are logistics and adjacent-service records. The public scope does not establish either one as an Onni critical-path requirement, and neither substitutes for the separate grading or building permits.
Record ↗26-117887-BGIssued
Excavation-pit conveyor systems
Applied Aug 4 · status checked Oct 14, 2026
The pit-conveyor electrical permit remains Issued in the October 14 city record. Its scope describes two 600-amp, 480-volt, three-phase systems for NW Construction; Prime Electric provides feeders and connections while Ault Electric Services connects, tests and verifies motor rotation. The Revision 1 electrical review closed Approved August 24. Issuance does not establish when the conveyors were installed or began operating, and it does not authorize the separate full-grading, podium or tower packages.
Record ↗26-116729-FR · 26-114882-TJReady to Issue / Issued
Heavy-equipment fuel & telecom relocation
Filed Jun 29–Jul 13 · Comcast field work Sep 8–9, 2026
Two small mobilization records remain on the consolidated parcel. Fuel permit 26-116729-FR covers a fuel cube for heavy equipment and names Northwest Construction Inc. as contractor; it remains Ready to Issue and the filing does not state its capacity. Bellevue's July 29 fire approval carries grounding, labeling, setback, extinguisher and empty-before-movement conditions. Comcast right-of-way permit 26-114882-TJ lets crews access two vaults and relocate one splice case. After a July 22 attempt was tabled, a September 2 preconstruction call set overnight work for 9 p.m.–5 a.m.; inspections document Cannon crews and traffic control on both sides of 106th Avenue September 8, followed by a September 9 note that the splicing work was performed and the crew moved on. The record does not say Onni requested the move or identify it as an excavation prerequisite, so it remains adjacent utility coordination.
Record ↗24-104273-UEPending
Project utility extension
Filed Feb 2024 · status checked Oct 14, 2026
The utility-extension permit serving the development remains Pending. Bellevue approved its Revision 3 fire review July 29 after a June 29 meeting about protecting connections and the hydrant/fire-department-connection layout. The approval requires a fire jobsite preconstruction inspection before work begins, a separate underground-private-fire-line permit and a future operational permit for private hydrants, whose maintenance and reporting remain the property owner's responsibility. The Revision 3 utility review ended August 19 with another revision request and comments uploaded to MyBuildingPermit, so the package has not yet cleared its core utility review.
Record ↗26-106943-LJPending
Comprehensive reconfiguration
Filed Apr 1 · reviews Sep 17–18 · status checked Oct 14, 2026
This pending application would move the hotel from Tower 1 to Tower 3. Separate April reporting describes more than 400 hotel rooms and less office space, but the permit summary has no reconciled replacement schedule; the approved 257-room Tower 1 plan remains the baseline. Bellevue marked the Revision 3 transportation review Approved September 17 and land-use review Approved September 18. The transportation note requires a signed concurrency certificate on the same day as permit issuance, and the land-use note says it is waiting for concurrency. A reviewer expected issuance September 21, but the October 14 parcel record still shows both this application and linked concurrency record 26-108760-DC as Pending. Review approval and a forecast are not land-use permit issuance.
Record ↗26-108760-DCPending
Concurrency gate on the reconfiguration
Applied Apr 16 · status checked Oct 14, 2026
A predevelopment-services record tied to the reconfiguration above. Its city note requires a new transportation-concurrency determination before 26-106943-LJ can be approved. Transportation requested a June 30 revision grouping the proposed retail, restaurant and fitness uses under the Shopping Plaza 40k–150k-square-foot trip-generation category; its second review closed July 14. September 17–18 notes on the redesign still call for a signed concurrency certificate at issuance. This linked record remained Pending October 14; a closed discipline review is not an approved determination.
Record ↗25-126179-BEIssued Jan 12, 2026
Demolition
Applied Oct 30, 2025 · issued Jan 12, 2026
The demolition permit (expiring Jan 11, 2029); its scope notes it "replaces expired permit 21 133862 BE," the original 2021 demolition filing that had lapsed. Dickson Demolition completed removal of the former John Danz Theatre and the former Belle Lanes / Barnes & Noble building in spring 2026.
Record ↗26-114797-BG · 26-114355-BF · 26-111760-TJIssued / closed / closed
Temporary power & site utilities
Status checked Oct 14, 2026
The larger temporary construction-power permit 26-114797-BG is now Issued. Its scope covers a 2,500-amp and a 4,000-amp 480-volt three-phase service plus a power skid for lights, tools and a portable office. The smaller temporary-service permit 26-114355-BF was issued June 17 and finaled June 25; the wireless-cabinet relocation 26-111760-TJ was finaled August 3. Both read Closed in the reviewed record. Electrical issuance alone does not establish that the new service has been energized.
Record ↗25-105052-BB · 25-105181-BB · 25-105109-BB · 25-105295-BBPending
Superstructure: podium + three towers
Filed Feb–Mar 2025 · status checked Oct 14, 2026
Onni filed the superstructure as four separate building permits, each still Pending: the podium (25-105052-BB), Tower 1 residential + hotel (25-105181-BB), Tower 2 residential (25-105109-BB), and Tower 3 office shell-and-core (25-105295-BB). The podium's Revision 3 structural review requested another revision September 17 while a separate Revision 5 structural line closed that day; these are different review cycles. Earlier fire and nonstructural correction lines also remain part of the record. The project's multi-tower Total Building Performance energy documentation is coordinated through the podium package, with Tower 2 and Tower 3 mechanical revisions requested September 9. Tower 3's utility review closed Approved September 4 but bars connection until the pending 24-104273-UE extension is built and accepted; a Tower 3 fire review requested another revision September 17. The pending 2026 hotel relocation still affects Tower 1 and Tower 3. None of these discipline entries issues a podium or tower permit.
Record ↗21-134212-BVIssued
Mass excavation & shoring
Issued Sep 3 · pile inspections Sep 28–Oct 14, 2026
Bellevue issued mass-excavation and shoring permit 21-134212-BV September 3. Its September 18 building preconstruction inspection is marked Partial with Corrections, but the inspector expressly wrote that shoring may start. The note requires city approval on the east side when shoring reaches the elevation needing soil nails where no easement has been granted. The people record names ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis as contractor-of-record under registration ONNI11A780MN, without identifying a specialist shoring subcontractor. Eight pile inspections dated September 28 and 29 and October 2, 5, 6, 7, 12 and 14 are marked Ongoing, with no notes. They document shoring inspection activity, without confirming a completed wall, satisfaction of the east-side condition or construction of permanent tower foundations. Full clear-and-grade permit 24-104334-GD remains Pending.
Record ↗24-104334-GDPending
Full-site clear & grade
Applied Feb 29, 2024 · status checked Oct 14, 2026
The separate clear-and-grade application for the full three-tower, podium and below-grade development remains Pending. It is distinct from issued early-works permit 21-133872-GD and the now-issued shoring permit 21-134212-BV. Bellevue's parcel record describes 24-104334-GD as the clear-and-grade permit for the complete development. Its land-use and transportation review lines remain tied to the pending 2026 reconfiguration, and its June Revision 2 clearing-and-grading review requested another revision. The September 18 shoring preconstruction note does not change the status of this separate grading application.
Record ↗21-133872-GD · 22-104918-UEIssued Dec 23, 2025
Early-works package
Issued Dec 2025 · latest job conference Sep 24, 2026
The authority now supporting visible earth removal is early-works clear-and-grade permit 21-133872-GD, issued December 23, 2025 with the city description "Early works clear and grade permit for mass excavation." Its public people record names Gary Merlino Construction Co. as contractor; that does not award Merlino the separate perimeter-shoring package. After preconstruction conferences April 1 and June 17, crews progressed from slab removal into broad shallow earthwork. Bellevue recorded a July 14 erosion-control inspection as Partial with Corrections, directing catch-basin inserts along 106th Avenue NE, and a July 20 follow-up as Ongoing. At a third job conference July 28, the inspector wrote: "Maintain mechanical street sweeper while exporting soils." That confirms soil export and a street-tracking control, but not the material's destination or contamination classification. A September 24 erosion-control job conference is marked Completed with no note; it does not record a change to the permitted scope. A transportation review note still limits this permit to "early grading only" and says full on-site grading was not approved under it. The package also includes fire-hydrant-relocation permit 22-104918-UE, issued December 2, 2025.
Record ↗24-104362-BBIssued
Below-grade structure (P2–P5)
Filed Feb 29, 2024 · issued Sep 9, 2026
Bellevue issued the parking-level P2-through-P5 building permit on September 9, with a permit expiration of September 8, 2029. Its scope covers the shared below-grade structure for the three towers and podium. The current people record names ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis as contractor-of-record under registration ONNI11A780MN; it does not name a concrete or other specialist subcontractor. No inspection was posted under this permit at the October 14 check. Issuance is the legal milestone that supersedes the August Pending and September 1 Ready to Issue statuses, but it does not establish that permanent garage work has begun or authorize the separate podium and tower packages.
Record ↗24-113252-LJClosed — finaled Feb 11, 2026
Plan refinement
Applied Jun 2024 · finaled Feb 11, 2026
A 2025 update — now closed and issued — that cut below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to about 532, and relocated the central energy plant to Tower 1.
Record ↗19-104024-LP · 19-104023-LDApproved 2022
Master Development Plan, SEPA & Design Review
Approved Jun 23, 2022
The combined Master Development Plan / SEPA review (19-104024-LP) and Design Review (19-104023-LD) for the three-tower scheme, filed in early 2019 and approved with conditions on June 23, 2022. The environmental review ended in a Determination of Non-Significance (DNS). The block is zoned DNTN-O1 (Downtown Office 1).
Record ↗18-108805-DB · 18-111104-DCClosed
Pre-application records
Filed spring 2018
The block's modern entitlement trail begins here: a pre-application record to "construct mixed use development" (18-108805-DB, applied Mar 21, 2018) and a design-conference record (18-111104-DC, applied Apr 16, 2018), both preceding the January 2019 land-use filings.
Record ↗