26-116729-FR · 26-114882-TJPending / issued
Heavy-equipment fuel & telecom relocation
Filed Jun 29–Jul 13, 2026
Two small July mobilization records on the consolidated parcel. Fuel permit 26-116729-FR, applied July 13 and listed as Pending July 15 after first appearing as Open, covers a fuel cube for heavy equipment; the filing does not state its capacity. The status change is an ordinary move into review, not an issuance. Right-of-way permit 26-114882-TJ, applied June 29 and issued July 13 after a July 9 approval, lets Comcast access two vaults and relocate one splice case. The Comcast record does not say the move is required by Onni, so it is adjacent utility-coordination evidence rather than a confirmed excavation prerequisite.
Record ↗26-106943-LJPending
Comprehensive reconfiguration
Filed Apr 1, 2026
A pending application to comprehensively reconfigure the development; per the city description, the primary change relocates the hotel from Tower 1 to Tower 3. Mid-2026 reporting describes the program as still in flux, with the hotel possibly growing from roughly 257 to about 400 rooms and the office component reduced to make room. Not yet approved — the current approved plan still places the hotel in Tower 1. As of July 14 its second land-use review remained open and its second transportation review was in progress. A linked predevelopment record (26-108760-DC) makes a new transportation concurrency determination a prerequisite, so the reconfiguration can't be signed off until that record clears.
Record ↗26-108760-DCPending
Concurrency gate on the reconfiguration
Applied Apr 16 · reviewed Jul 14, 2026
A predevelopment-services record tied to the reconfiguration above. Its city note is explicit: "A new transportation concurrency determination will be required," and a concurrency application must be submitted "prior to approval of 26 106943 LJ." Transportation requested a June 30 revision grouping the proposed retail, restaurant and fitness uses under the Shopping Plaza 40k–150k-square-foot trip-generation category; the second transportation review closed July 14. The permit itself still reads Pending, so that closed review line is procedural progress rather than an approved concurrency determination.
Record ↗25-126179-BEIssued Jan 12, 2026
Demolition
Applied Oct 30, 2025 · issued Jan 12, 2026
The demolition permit (expiring Jan 11, 2029); its scope notes it "replaces expired permit 21 133862 BE," the original 2021 demolition filing that had lapsed. Dickson Demolition completed removal of the former John Danz Theatre and the former Belle Lanes / Barnes & Noble building in spring 2026.
Record ↗26-114797-BG · 26-114355-BF · 26-111760-TJReady to issue / closed / issued
Temporary power & site utilities
May–Jul 2026
The first field-mobilization permits after demolition. A temporary electrical service (26-114355-BF) was applied for and issued the same day — June 17, 2026 — then finaled June 25 and now reads Closed. The larger temporary construction-power permit (26-114797-BG, applied June 26) installs a 2,500-amp and a 4,000-amp 480-volt three-phase service drawn from the PSE transformers, plus a power skid for site lights, tools and a portable office. Its electrical review was approved July 7 and by July 14 the permit read Ready to Issue — approved, but awaiting contractor-license information and issuance fees rather than issued. Separately, a right-of-way permit (26-111760-TJ, issued May 28) removed a wireless equipment cabinet from a city streetlight pole "to accommodate" the development.
Record ↗25-105052-BB · 25-105181-BB · 25-105109-BB · 25-105295-BBPending
Superstructure: podium + three towers
Filed Feb–Mar 2025
Onni filed the main superstructure as four separate building permits, each still pending in mid-2026 with application expirations in early 2027: the podium (25-105052-BB, applied Feb 27 — its scope lists the shared base uses "including retail, amenity, F&B, gym, daycare, event, office"), Tower 1 residential + hotel (25-105181-BB, applied Mar 3, roof at level 58), Tower 2 residential (25-105109-BB, applied Feb 28, roof at level 59), and Tower 3 office shell-and-core (25-105295-BB, applied Mar 4, roof at level 47). The permits frame the work as starting above the level-5 podium; how the roof-level numbering reconciles with the marketed 53/54/45 story counts isn't spelled out. As of mid-2026 none of the four has been issued — all remain in city review with corrections outstanding, gated on the upstream land-use, clear-and-grade (GD) and shoring (BV) approvals. The review notes are pointed on tower order: Tower 1's and Tower 3's building reviews are held "pending approval" of the 2026 reconfiguration (26-106943-LJ) that shifts the hotel from Tower 1 to Tower 3 — the two towers that redesign reshapes — while Tower 2, the all-residential tower, is gated only on the already-approved 2024 land-use update, leaving it the least-blocked of the three. The podium is built first by necessity (it's the shared base); among the towers, whichever building permit flips from "Pending" to "Issued" first will be the real first tower to rise.
Record ↗21-134212-BVPending
Mass excavation & shoring
Applied Dec 14, 2021
The permit that gates full mass excavation and perimeter shoring, applied December 14, 2021 and still pending July 21, 2026, alongside the below-grade structure permit 24-104362-BB. Its pending status does not prohibit all dirt removal: limited early excavation began in July under issued clear-and-grade permit 21-133872-GD. Land use, utilities and transportation had cleared or raised no concern on the shoring permit's thirteenth revision in June, but the structural and geotechnical reviewers both requested another revision July 10 concerning a geotechnical letter. A condition of approval also bars soil nailing or shoring beneath a street, sidewalk or utility easement without a recorded indemnification agreement protecting the city.
Record ↗21-133872-GD · 22-104918-UEIssued Dec 23, 2025
Early-works package
Issued Dec 2025
The authority now supporting visible earth removal is early-works clear-and-grade permit 21-133872-GD, issued December 23, 2025 with the city description "Early works clear and grade permit for mass excavation." Its second preconstruction conference was completed June 17; crews progressed from slab removal into a broad shallow cut by July 17 and a six-excavator, block-wide early-earthwork operation by July 21. Bellevue recorded an initial erosion-control inspection July 14 as Partial with Corrections, directing installation of catch-basin inserts along 106th Avenue NE, then logged the same inspection type July 20 as Ongoing with no note. That is continued inspection activity, not a final pass. A transportation review note limits the permit to "early grading only" and says full on-site grading was not approved under it, preserving the boundary with the pending shoring permit. The package also includes fire-hydrant-relocation permit 22-104918-UE, issued December 2, 2025.
Record ↗24-104362-BBPending
Below-grade structure (P2–P5)
Filed Feb 29, 2024
The permit for the below-grade structure — parking levels P2 through P5 beneath the three towers and podium. Applied February 29, 2024 and still pending July 21, 2026. Its third structural review remained open and its second fire review was in progress. The latest completed structural note, dated May 28, requested revised structural drawings and calculations plus an interim peer-review letter before approval. July's limited early excavation does not mean this garage permit has been issued.
Record ↗24-113252-LJClosed — finaled Feb 11, 2026
Plan refinement
Applied Jun 2024 · finaled Feb 11, 2026
A 2025 update — now closed and issued — that cut below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to about 532, and relocated the central energy plant to Tower 1.
Record ↗19-104024-LP · 19-104023-LDApproved 2022
Master Development Plan, SEPA & Design Review
Approved Jun 23, 2022
The combined Master Development Plan / SEPA review (19-104024-LP) and Design Review (19-104023-LD) for the three-tower scheme, filed in early 2019 and approved with conditions on June 23, 2022. The environmental review ended in a Determination of Non-Significance (DNS). The block is zoned DNTN-O1 (Downtown Office 1).
Record ↗18-108805-DB · 18-111104-DCClosed
Pre-application records
Filed spring 2018
The block's modern entitlement trail begins here: a pre-application record to "construct mixed use development" (18-108805-DB, applied Mar 21, 2018) and a design-conference record (18-111104-DC, applied Apr 16, 2018), both preceding the January 2019 land-use filings.
Record ↗