Breaking, from the record
News
A single entry point for the current phase, permit movement, environmental decisions and human-reviewed visual progress — independently reported and linked to the underlying record.
Verified project status
Early excavation and soil characterization — shoring pending
- On the ground
- The most recent stable, dated visual evidence synthesized here is a July 21 high-resolution photograph. It shows the former buildings and most surface slab gone, with excavators and a tracked dozer across a broad, shallow, graded area.
- In the record
- The pit conveyors' Revision 1 electrical review and two podium utility reviews were approved August 24, but both permits remain Pending. Revision 15 of the shoring permit remains in structural and geotechnical review. Ecology's August 13 soil-disposal decision is not a final cleanup decision.
- Next verified gate
- The next legal phase change requires the applicable shoring, full-grading and below-grade approvals. Beam-haul and pit-conveyor filings are supporting mobilization records, not proof that those gates have cleared.
September 2026
Onni 606 Mass Excavation and Shoring Permit Issued by City of Bellevue
The City of Bellevue has issued the mass excavation and shoring permit for the Onni 606 development, a significant step for the three-tower project.
Onni 606 Below-Grade Structure Permit Moves to 'Ready to Issue' Status
The permit for the below-grade structure (parking levels P2-P5) for the Onni 606 development has advanced to 'Ready to Issue' status, as recorded by the City of Bellevue.
August 2026
Onni 606 Mass Excavation and Shoring Permit Moves to 'Ready to Issue' Status
The permit for mass excavation and shoring at the Onni 606 development site in Downtown Bellevue has advanced to 'Ready to Issue' status, as indicated by city records.
Onni 606 Project Secures Permit for Excavation Conveyor Systems
The Onni 606 development in Downtown Bellevue has received an 'Issued' status for its excavation-pit conveyor system permit, indicating progress toward site preparation.
Onni 606 Project Receives Permit for Steel Beam Haul, Temporary Power
The Onni 606 development in Downtown Bellevue has received an 'Issued' status for a permit to haul large steel beams to the site, alongside an 'Issued' permit for temporary construction power.
- Permit watch
Conveyor and podium reviews advance while both Onni 606 permits remain pending
Bellevue approved the pit conveyors' electrical review and two podium utility reviews August 24; neither action issued a permit or cleared the project's larger excavation gates.
- Environment
Ecology sets disposal conditions for 21,250 tons of PCE-affected Onni 606 soil
The August 13 contained-in determination creates a documented disposal pathway through April 2027; it is not a No Further Action decision or approval of the cleanup plan.
- Permit watch
Long steel-beam haul and gas relocation surface as Onni 606 shoring review advances
Two August 13 street-use filings cover 64- to 96-foot beam deliveries and a 425-foot PSE gas-main relocation; meanwhile, Bellevue is reviewing Revision 15 of the still-pending shoring permit.
- Permit watch
New Onni 606 permit details twin excavation-pit conveyor systems
Bellevue filing 26-117887-BG seeks electrical approval for two 600-amp, 480-volt conveyor systems for NW Construction; an August 11 review requested control-panel listing information, while the fuel-cube permit is now Ready to Issue.
New Conveyor System Permit Filed for Onni 606 Development
A new building permit has been filed for the Onni 606 project in Downtown Bellevue, indicating plans for conveyor systems on the site.
- Monthly progress
July 2026 progress report: Onni 606 moves into early earthwork
A completed-month review pairs the verified July 13–21 visual sequence with permit, inspection and environmental records checked through July 31.
July 2026
- Permit watch
Bellevue records soil export as two Onni 606 fire reviews advance
A July 28 job conference directs crews to keep a mechanical street sweeper running during soil export; fire reviewers approved the fuel-cube and utility-extension reviews July 29, while both permits remain pending.
- Permits
Bellevue requests another structural revision for Onni 606 Tower 2
The city said the Revision 2 submittal repeated Revision 1 and referred the applicant back to June comments; building permit 25-105109-BB remains pending.
- Construction
Six excavators spread across Onni 606 as early earthwork expands
A July 21 photograph shows more equipment, a broader graded work area and the northeast slab broken up; Bellevue logged the early-grading permit's second erosion-control inspection a day earlier.
- Construction
Early excavation is under way at Onni 606 — and Bellevue's record explains the permit boundary
A broad shallow cut, exposed soil and dump-truck activity mark the start of limited excavation under an issued early-grading permit; the shored garage dig remains pending.
- Construction
Slab removal pushes south as crews clear another band of the Onni 606 site
A July 15 photograph shows yesterday's remaining foreground slab gone, rubble consolidated and four excavators spread across the early-works area.
- Permits
Fuel storage, construction power and utility work deepen 606 mobilization
Three small Bellevue records point to a more fully equipped jobsite, while the shoring permit still holds the line before the deep dig.
- Construction
A day later, slab removal has spread across a much wider part of the Onni 606 site
A July 14 photograph shows a broad field of broken concrete and exposed subgrade where the previous morning's close view showed one bounded removal area.
- Construction
Three excavators strip the remaining slab as Onni 606 enters early earthwork
A close view shows three excavators breaking and clearing concrete across a widening work area — systematic slab removal, not yet the deep shored dig.
Onni 606 Temporary Power Permit Moves to 'Ready to Issue' Status
The permit for temporary construction power at the Onni 606 development site in Downtown Bellevue has advanced to 'Ready to Issue,' indicating progress toward site utility installation.
Demolition done: the 606 block is cleared, but excavation still waits on permits
Dickson Demolition has taken both buildings down and graded the four-acre superblock flat. The dig can't start until the mass-excavation, shoring and below-grade permits clear city review.
June 2026
Site power goes in: the first field-mobilization permits reach the 606 record
A temporary electrical service plus a 2,500- and 4,000-amp construction-power drop — small filings, but the first concrete sign the block is shifting from demolition toward the dig.
Onni proposes reshuffling the towers — moving the hotel from Tower 1 to Tower 3
A pending City of Bellevue application (26-106943-LJ) would comprehensively reconfigure Onni 606, most notably relocating the hotel. It is filed but not yet approved.
Cleanup report No. 19 points to on-site fieldwork by the end of June
TRC's latest quarterly progress report to the Department of Ecology is the first in the series to flag imminent field work on the contaminated 606 site.
April 2026