Independent updates on construction, permits, environmental records and dated visual progress, with links to the evidence.


Verified project status

Earthwork — ongoing shoring pile inspections

On the ground
Comparing dated September 12 and 22 camera frames shows a broader central cut and a tall-mast rig near the north side. The view does not establish that the rig is installing shoring, show a completed support wall, or measure excavation depth.
In the record
The October 14 parcel record lists the shoring and P2-through-P5 below-grade permits as Issued. Eight pile inspections under shoring are marked Ongoing, without notes confirming completion or satisfaction of the east-side condition. Below-grade has no posted inspection. Full-site grading, utility extension, the podium, all three towers and the 2026 redesign remain Pending.
Next verified gate
Watch for further shoring inspections and any east-side city approval required at the soil-nail elevation, plus issuance of full-site grading. Pile inspections under shoring do not establish a tower foundation system or a permanent garage-structure start.