Timeline
From empty block to skyline.
A multi-year journey from land acquisition to topping out — here's where the project stands, what's underway, and what comes next.
Where the project stands
Early excavation under way — shoring pending
- Acquired2019
- Approved2022
- Demolition2026You are here
- ExcavationJul 2026
- Topping out≈2029
- Completion≈2030
- 2019
Site acquired
Onni Group purchases the ~4-acre Barnes & Noble block for roughly $116M.
- 2021
Cleanup track opens
The Washington Department of Ecology issues a 'No Further Action Likely' opinion for the contaminated 606/620 block (Dec 15); the site is enrolled in the state's Expedited Voluntary Cleanup Program, and a cleanup is later scheduled to run alongside demolition and excavation.
- 2022
Approvals secured
City of Bellevue approves the Master Development Plan and Design Review in June.
- 2022
Anchor tenants move out
Barnes & Noble relocates to Crossroads Mall and Doxa Church moves to Redmond after seven years in the former John Danz Theatre — but both buildings stay standing.
- 2022–2025
Buildings stay in use
Rather than sitting empty, the existing structures keep hosting tenants — most recently a furniture store in the former Barnes & Noble and a church in the former theatre — right up until demolition.
- H1 2026
Demolition complete
Onni's demolition permit is issued in January, and Dickson Demolition takes the two long-standing buildings down through the spring, clearing the four-acre superblock.
- Jul 2026In progress
Early excavation begins
Crews begin a broad shallow cut under the issued early-works clear-and-grade permit. The dedicated shoring and below-grade structure permits remain pending, so the full five-level garage excavation has not started.
- ≈2030
Targeted completion
A roughly five-year construction program delivers all three towers.
The build
What a five-year build looks like.
Six excavators and a dozer are spread across a broad, graded early-works area under an issued clear-and-grade permit. Full shored excavation has not started. Limited early grading continues while full excavation, perimeter shoring and below-grade construction remain dependent on separate city approvals. Here's how a project this large comes out of the ground once the dig begins.
The first and slowest act is the hole. Before any tower rises, crews dig a deep excavation across nearly the entire ~4-acre superblock to make room for roughly 1,712 parking stalls, most of them below grade. Shoring the walls, hauling out spoil and pouring the foundation mats for three towers can take the better part of the first year on its own — all of it happening largely out of sight, below street level. (figures approximate)
From there the work goes podium-first: the shared base that knits the three towers together — lobbies, retail, the daycare and amenity levels — is built across the block before the towers climb above it. Only then do the two residential towers and the office tower begin their vertical run toward the ~600-ft Bellevue ceiling, floor by repeated floor.
Expect tower cranes on the skyline for years. Multiple cranes will leapfrog up alongside each tower, becoming the most visible sign of progress from across downtown long before any facade goes on. A topping-out for the tallest tower is the milestone that signals the structure has reached full height.
At street level, the nearest-term impact is along 106th Ave NE: expect periodic lane and sidewalk closures, hauling traffic and pedestrian detours around the site once excavation ramps up. The timing remains contingent on the excavation, shoring and below-grade permits that are still moving through city review.
Latest updates
Newest first
- Jul 21, 2026
July progress report: the cleared block enters early earthwork
The month-to-date record traces a clear transition: remaining surface slab was broken and removed across the block, exposed subgrade widened from a bounded foreground patch to most of the visible site, and the active fleet grew to six excavators plus a dozer by July 21. The work is authorized under the early clear-and-grade permit; it is not yet the deep, shored five-level garage excavation, whose separate permits remain pending.
Source ↗ - Jul 21, 2026
Six excavators spread across the early-works area
A high-resolution afternoon photograph shows six tracked excavators, a tracked dozer and a water truck across a broader graded area than the July 17 camera frame, which showed four excavators. The northeast slab has been broken into a field of rubble or aggregate and the central/southern grade is smoother and more extensive. Bellevue logged a second erosion-control inspection July 20 as Ongoing under the issued early-grading permit; the shoring and below-grade permits remain pending.
Source ↗ - Jul 17, 2026
Early excavation begins under issued grading permit
Camera frames show excavators working exposed soil across a broad shallow cut and dump trucks moving through the site. Bellevue permit 21-133872-GD was issued for early clear-and-grade work for mass excavation, completed its second preconstruction conference June 17 and received an initial erosion-control inspection July 14. A city review note limits it to early grading: the dedicated shoring and below-grade structure permits remain pending.
Source ↗ - Jul 15, 2026
Another foreground band of slab disappears
A late-afternoon photograph shows the broad foreground slab and small raised concrete remnant visible July 14 removed, leaving exposed shallow subgrade and distinct rubble stockpiles. Four excavators, a wheel loader and support vehicles are visible. The fixed visual references show the break-sort-clear operation pushing south, but the work remains surface demolition: the shoring and below-grade permits are still pending and no perimeter shoring or deep block-wide cut is visible.
Source ↗ - Jul 14, 2026
Slab removal spreads across a much wider work area
Photographs taken about 23 hours apart show rapid visible progress: the bounded removal patch seen July 13 has become a long field of broken concrete and exposed shallow subgrade across much of the visible foreground. At least four excavators and a wheel loader are present in the July 14 view. Different framing prevents a precise area measurement, and the work remains early earthwork and surface demolition — not the deep shored excavation.
Source ↗ - Jul 14, 2026
Fuel, power and utility permits deepen mobilization
A new fuel-cube filing for heavy equipment (26-116729-FR) joined the ledger July 13; Comcast's permit to relocate a splice case through two vaults (26-114882-TJ) was issued the same day; and the large temporary construction-power permit (26-114797-BG) is now Ready to Issue after electrical approval July 7. The pattern is active jobsite preparation, not authorization for the deep dig: the shoring and below-grade permits remain pending.
Source ↗ - Jun 2026
Site power goes in — first mobilization permits
Beyond the teardown, the first field-mobilization permits reached the city ledger. A temporary electrical service (26-114355-BF) was applied for and issued the same day — June 17 — then finaled June 25; a larger temporary construction-power permit (26-114797-BG, applied June 26) installs a 2,500-amp and a 4,000-amp 480-volt service drawn from the PSE transformers, with a power skid for site lights, tools and a portable office. A late-May right-of-way permit (26-111760-TJ) cleared a wireless cabinet off a city streetlight pole to make way for the work. Small permits, but the first concrete sign the block is shifting from demolition toward the dig.
Source ↗ - Jun 2026
Reconfiguration proposed
A City of Bellevue application (26-106943-LJ), filed April 1, 2026 and still pending, proposes a comprehensive reconfiguration of the development — most notably moving the hotel from Tower 1 to Tower 3. It is not yet approved; the current approved plan still places the hotel in Tower 1. A linked predevelopment record (26-108760-DC) requires a new transportation concurrency determination before the reconfiguration can be approved — the procedural reason it has stayed pending.
Source ↗ - Jun 2026
Cleanup report No. 19 — fieldwork slated for end of June
TRC's Quarterly Progress Report No. 19 to the Department of Ecology (dated June 4, posted June 11) is the first to point at imminent field work: it lists 'preparation for site redevelopment and site characterization activities planned for the end of June 2026' — the next on-site step after January's groundwater sampling. Its tentative milestone schedule has demolition in Q2 2026, contained-in (CID) soil characterization and Ecology approval in Q2–Q3 2026, remedial excavation in Q3–Q4 2026, an interim remedial action complete by Q4 2026–Q1 2027, and the final Remedial Action Report in Q2–Q3 2027 — all expressly contingent on Bellevue permitting and market conditions. The next report (No. 20) is due September 10.
Source ↗ - Jun 2026
Demolition under way
With the demolition permit issued, Dickson Demolition has equipment on the block and is taking the two buildings down. Excavation waits on the mass-excavation/shoring and below-grade permits, both still in city review in mid-2026 — the below-grade permit is held pending structural drawings and an ongoing peer review — so Onni's hoped-for July excavation start is uncertain. A $53.5M Wells Fargo loan was recorded the prior year.
Source ↗ - Summer 2026
Permitting → excavation
Onni's Brendan Lawrence told a Bellevue Downtown Association breakfast the team is shifting from permitting into excavation and construction this summer.
Source ↗ - Apr 2026
Project profile published
Coverage details the full program — 1,300+ homes, 400+ hotel suites, ~896k sf of office, two pools, a daycare and a 15,000 sf plaza — calling it the largest construction project in Washington State.
Source ↗ - Jan 2026
Cleanup mobilizes — first field work
After roughly eighteen quarterly reports of 'no work performed at the site,' crews collect groundwater samples for a dewatering assessment — the first field activity on the contaminated-site cleanup since it was re-enrolled in 2021, and an early sign of mobilization ahead of demolition.
Source ↗ - Jun 2025
Cleanup schedule fused to construction
An environmental consultant's quarterly progress report to the Department of Ecology (Expedited Voluntary Cleanup Program No. XN0011) schedules contaminated-soil work to track the build: demolition and soil characterization in early 2026, remedial excavation in late 2026, and a final remedial action report in 2027.
Source ↗ - 2025
Plan refined
An approved update (permit 24-113252-LJ) trimmed below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to ~532, and relocated the central energy plant to Tower 1.
Source ↗ - Jun 2022
Master Plan & Design Review approved
The City of Bellevue approved the Master Development Plan and Design Review for the three-tower scheme.
Source ↗ - 2019
Site acquired
Onni Group bought the ~4-acre block from Sterling Realty Organization for about $116 million — recorded February 12, 2019 as a bargain-and-sale deed (King County excise #2973252), conveying title to ONNI 106th Ave Bellevue LLC.
Source ↗
Keep exploring