Timeline

From empty block to skyline.

A multi-year journey from land acquisition to topping out — here's where the project stands, what's underway, and what comes next.


Where the project stands

Early excavation and soil characterization — shoring pending

  1. Acquired2019
  2. Approved2022
  3. Demolition2026
  4. ExcavationJul 2026You are here
  5. Topping out≈2029
  6. CompletionDate TBD
Scroll-driven 3D construction sequence: the 1961 low-rise block is demolished, the pit is excavated, the shared podium rises, and the three ~600 ft towers climb floor by floor. Future stages are illustrative; no current completion date has been announced.

Project milestones

  1. 2019

    Site acquired

    Onni Group purchases the ~4-acre Barnes & Noble block for roughly $116M.

  2. 2021

    Cleanup track opens

    Ecology's December 15 opinion says that, if the proposed independent cleanup is completed as described, further remedial action will likely not be needed. It is prospective—not a final No Further Action decision—and does not settle liability. The site is enrolled for expedited Ecology technical review.

  3. 2022

    Approvals secured

    City of Bellevue approves the Master Development Plan and Design Review in June.

  4. 2022

    Anchor tenants move out

    Barnes & Noble relocates to Crossroads Mall and Doxa Church moves to Redmond after seven years in the former John Danz Theatre — but both buildings stay standing.

  5. 2022–2025

    Buildings stay in use

    Rather than sitting empty, the existing structures keep hosting tenants — most recently a furniture store in the former Barnes & Noble and a church in the former theatre — right up until demolition.

  6. H1 2026

    Demolition complete

    Onni's demolition permit is issued in January, and Dickson Demolition takes the two long-standing buildings down through the spring, clearing the four-acre superblock.

  7. Jul 2026In progress

    Early excavation begins

    Crews begin a broad shallow cut under the issued early-works clear-and-grade permit. The dedicated shoring and below-grade structure permits remain pending, so the full five-level garage excavation has not started.

  8. Not announced

    Completion remains undated

    Onni has described construction as close to five years, but no new completion date has been publicly announced. The April 2030 date belonged to a 2022 sequence that predated the delayed start and pending redesign.

Construction field guide · as of August 22, 2026

How to tell one phase from the next.

A megaproject changes legal phase in the permit record and physical phase in the field. The two usually move together, but not on the same day. This guide shows what to look for—and what not to infer—from the Onni 606 camera.

  1. 01

    Demolition and block clearance

    25-126179-BE · issued Jan 12, 2026

    Complete
    What the field can show
    The former John Danz Theatre and Belle Lanes/Barnes & Noble structures disappear, followed by slab breaking, sorting and removal.
    What that proves
    An issued demolition permit plus field removal establishes that the former buildings were cleared.
    What it does not prove
    A clear block does not establish that mass excavation, shoring or the new structures are authorized.
  2. 02

    Early grading and soil characterization

    21-133872-GD · issued Dec 23, 2025

    Current
    What the field can show
    A broad shallow cut, grading, soil stockpiles, drill activity, dump trucks and documented soil export within the early-work boundary.
    What that proves
    The issued clear-and-grade record supports limited early earthwork; inspections confirm soil export and erosion-control oversight.
    What it does not prove
    Excavators, long-beam planning, fuel, temporary power or pit-conveyor applications do not by themselves mark the start of the deep garage dig.
  3. 03

    Perimeter shoring

    21-134212-BV · Revision 15 in review

    Pending
    What the field can show
    Once authorized and mobilized, a continuous earth-retention operation around the excavation edge would be the durable field signal—not simply a drill rig elsewhere on the block.
    What that proves
    An issued BV permit, completed applicable preconstruction steps and a visible perimeter-support system together would support calling this the shoring phase.
    What it does not prove
    The public record reviewed here does not confirm the shoring contractor or a particular wall system, so equipment shape alone cannot identify the method.
  4. 04

    Mass excavation and cleanup

    21-134212-BV · 24-104334-GD · Ecology cleanup track

    Gated
    What the field can show
    The excavation deepens across the block behind perimeter support, with sustained spoil handling coordinated with the applicant's independent cleanup plan under Ecology technical review.
    What that proves
    The relevant issued permits, inspections and a deepening shored cut would distinguish mass excavation from the current shallow early work.
    What it does not prove
    A single deep test pit, truck campaign or cleanup boring does not establish that the full five-level excavation has begun.
  5. 05

    Below-grade structure

    24-104362-BB · P2 through P5

    Pending
    What the field can show
    Structural slabs, walls, columns and ramps begin replacing the open excavation from the bottom upward.
    What that proves
    Issued building authority and repeated permanent-structure work would mark the change from digging the garage to building it.
    What it does not prove
    Approval of one discipline review—such as conceptual smoke control—is not issuance of the overall below-grade permit.
  6. 06

    Shared podium

    25-105052-BB

    Future / pending permit
    What the field can show
    A common above-grade base spreads across the site for lobbies, retail, amenities, food and beverage, gym, daycare, event and office uses.
    What that proves
    The shared base becoming structurally continuous is the physical bridge between the garage and the independent tower runs.
    What it does not prove
    Podium activity does not establish which tower will be first or that any individual tower permit has been issued.
  7. 07

    Tower structure and topping out

    25-105181-BB · 25-105109-BB · 25-105295-BB

    Future / pending permits
    What the field can show
    Independent cores and floor plates repeat upward from the shared base; topping out means a tower's primary structure has reached its planned roof level.
    What that proves
    An issued permit and sustained vertical structure identify a tower run. The first issued and mobilized package—not an earlier concept sequence—will be the best evidence of order.
    What it does not prove
    Topping out is not completion, occupancy or confirmation that the other two towers are on the same schedule.
  8. 08

    Enclosure, interiors and public realm

    Later trade, tenant and occupancy approvals

    Future
    What the field can show
    Facade installation trails structure while interior systems, testing, streetscape, plaza and through-block connections proceed on overlapping tracks.
    What that proves
    Final inspections and occupancy approvals—not a finished-looking facade—establish when space may open for use.
    What it does not prove
    Exterior completion does not mean hotel rooms, residences, offices or the public realm are ready or legally occupied.

Sequence is a field-reading guide, not a contractor schedule. Adjacent phases can overlap, and permit reviews often advance long before their corresponding work appears on camera. See the current record dependencies in the permit critical-path map.

The build

What the multi-year phase sequence looks like.

Early grading remains the only issued excavation phase. Bellevue documented soil export on July 28, while perimeter shoring and the below-grade structure remain unissued. Ecology's August 13 contained-in determination sets handling and reporting conditions for a specific 21,250 tons of PCE-contaminated soil; it does not approve the cleanup plan or identify the earlier export as part of that stream. The next legal phase change requires the applicable shoring, full-grading and below-grade approvals. Beam-haul and pit-conveyor filings are supporting mobilization records, not proof that those gates have cleared. Here's how a project this large comes out of the ground once the dig begins.

The first and slowest act is the hole. Before any tower rises, crews dig a deep excavation across nearly the entire ~4-acre superblock to make room for roughly 1,712 parking stalls, most of them below grade. Shoring the walls, hauling out spoil and pouring the foundation mats for three towers can take the better part of the first year on its own — all of it happening largely out of sight, below street level. (figures approximate)

From there the work goes podium-first: the shared base that knits the three towers together — lobbies, retail, the daycare and amenity levels — is built across the block before the towers climb above it. Only then do the two residential towers and the office tower begin their vertical run toward the ~600-ft Bellevue ceiling, floor by repeated floor.

Expect tower cranes on the skyline for years. Multiple cranes will leapfrog up alongside each tower, becoming the most visible sign of progress from across downtown long before any facade goes on. A topping-out for the tallest tower is the milestone that signals the structure has reached full height.

At street level, the nearest-term impact is along 106th Ave NE: expect periodic lane and sidewalk closures, hauling traffic and pedestrian detours around the site once excavation ramps up. The timing remains contingent on the excavation, shoring and below-grade permits that are still moving through city review.

Dated project updates

Latest updates

Newest first

  • Aug 24, 2026

    Pit-conveyor and podium reviews advance without permit issuance

    Bellevue approved the Revision 1 electrical review for excavation-pit conveyor permit 26-117887-BG and the Revision 3 and Revision 4 utility reviews for podium permit 25-105052-BB. The podium's Revision 3 transportation line closed so review could continue under Revision 4. Both permits remain Pending; these discipline actions do not issue the conveyors, podium, shoring or below-grade structure.

    Source ↗
  • Aug 23, 2026

    Ecology sets disposal conditions for 21,250 tons of PCE-affected soil

    An August 13 contained-in determination establishes a controlled disposal and reporting pathway for a specific 21,250 tons of soil through April 30, 2027. The letter does not name a landfill, cover contaminated water or other excavation areas, approve the cleanup plan, or show that soil exported before the decision belonged to this stream.

    Source ↗
  • Aug 22, 2026

    Long steel-beam haul and gas relocation enter the street-use record

    Two August 13 right-of-way applications cover deliveries of 64- to 96-foot steel beams and a 425-foot PSE gas-main relocation through the Onni parcel to the neighboring 601 108th Avenue NE building. The steel-haul review was approved August 21, but both permits remain Pending. Revision 15 of the shoring permit has cleared or drawn no concern from four disciplines while structural and geotechnical reviews remain in progress.

    Source ↗
  • Aug 12, 2026

    New permit details twin excavation-pit conveyor systems

    Bellevue permit 26-117887-BG, applied August 4, covers two 600-amp, 480-volt, three-phase pit-conveyor systems for NW Construction. The first electrical review requested a revision August 11 over the control panels' listing or field-evaluation requirements, so the permit remains Pending. The heavy-equipment fuel permit has advanced to Ready to Issue, while shoring and below-grade permits remain pending.

    Source ↗
  • Aug 1, 2026

    Completed July report: early earthwork, with deep excavation still gated

    The human-reviewed completed-month record uses July 13 as its earliest verified comparison visual and July 21 as its latest, without presenting either as a calendar endpoint. Bellevue records through the July 31 cutoff document soil export, a Tower 2 structural revision request and narrow fire-review approvals; shoring and below-grade permits remained pending, and the soil's volume, classification and destination were not established.

    Source ↗
  • Jul 29, 2026

    Soil export documented as fuel and utility reviews advance

    A July 28 job-conference note under the issued early-grading permit directs crews to maintain a mechanical street sweeper while exporting soils—the first Bellevue inspection entry to state explicitly that soil is leaving the block. On July 29, fire reviewers approved reviews of the pending fuel-cube and utility-extension permits with preconstruction, grounding, fire-line and hydrant conditions. These are narrow review approvals, not permit issuances; the shoring and below-grade permits remain pending.

    Source ↗
  • Jul 23, 2026

    Tower 2 structural review requests another revision

    Bellevue completed the Revision 2 structural review of Tower 2 building permit 25-105109-BB on July 23 with a revision request. The reviewer said the Revision 2 submittal was the same as Revision 1 and directed the applicant back to structural comments posted June 24. The permit remains Pending; this is a request for another revision, not an issuance or denial.

    Source ↗
  • Jul 21, 2026

    Six excavators spread across the early-works area

    A high-resolution afternoon photograph shows six tracked excavators, a tracked dozer and a water truck across a broader graded area than the July 17 camera frame, which showed four excavators. The northeast slab has been broken into a field of rubble or aggregate and the central/southern grade is smoother and more extensive. Bellevue logged a second erosion-control inspection July 20 as Ongoing under the issued early-grading permit; the shoring and below-grade permits remain pending.

    Source ↗
  • Jul 17, 2026

    Early excavation begins under issued grading permit

    Camera frames show excavators working exposed soil across a broad shallow cut and dump trucks moving through the site. Bellevue permit 21-133872-GD was issued for early clear-and-grade work for mass excavation, completed its second preconstruction conference June 17 and received an initial erosion-control inspection July 14. A city review note limits it to early grading: the dedicated shoring and below-grade structure permits remain pending.

    Source ↗
  • Jul 15, 2026

    Another foreground band of slab disappears

    A late-afternoon photograph shows the broad foreground slab and small raised concrete remnant visible July 14 removed, leaving exposed shallow subgrade and distinct rubble stockpiles. Four excavators, a wheel loader and support vehicles are visible. The fixed visual references show the break-sort-clear operation pushing south, but the work remains surface demolition: the shoring and below-grade permits are still pending and no perimeter shoring or deep block-wide cut is visible.

    Source ↗
  • Jul 14, 2026

    Slab removal spreads across a much wider work area

    Photographs taken about 23 hours apart show rapid visible progress: the bounded removal patch seen July 13 has become a long field of broken concrete and exposed shallow subgrade across much of the visible foreground. At least four excavators and a wheel loader are present in the July 14 view. Different framing prevents a precise area measurement, and the work remains early earthwork and surface demolition — not the deep shored excavation.

    Source ↗
  • Jul 14, 2026

    Fuel, power and utility permits deepen mobilization

    A new fuel-cube filing for heavy equipment (26-116729-FR) joined the ledger July 13; Comcast's permit to relocate a splice case through two vaults (26-114882-TJ) was issued the same day; and the large temporary construction-power permit (26-114797-BG) is now Ready to Issue after electrical approval July 7. The pattern is active jobsite preparation, not authorization for the deep dig: the shoring and below-grade permits remain pending.

    Source ↗
  • Jun 2026

    Site power goes in — first mobilization permits

    Beyond the teardown, the first field-mobilization permits reached the city ledger. A temporary electrical service (26-114355-BF) was applied for and issued the same day — June 17 — then finaled June 25; a larger temporary construction-power permit (26-114797-BG, applied June 26) installs a 2,500-amp and a 4,000-amp 480-volt service drawn from the PSE transformers, with a power skid for site lights, tools and a portable office. A late-May right-of-way permit (26-111760-TJ) cleared a wireless cabinet off a city streetlight pole to make way for the work. Small permits, but the first concrete sign the block is shifting from demolition toward the dig.

    Source ↗
  • Jun 2026

    Reconfiguration proposed

    A City of Bellevue application (26-106943-LJ), filed April 1, 2026 and still pending, proposes a comprehensive reconfiguration of the development — most notably moving the hotel from Tower 1 to Tower 3. It is not yet approved; the current approved plan still places the hotel in Tower 1. A linked predevelopment record (26-108760-DC) requires a new transportation concurrency determination before the reconfiguration can be approved — the procedural reason it has stayed pending.

    Source ↗
  • Jun 2026

    Cleanup report No. 19 — fieldwork slated for end of June

    TRC's Quarterly Progress Report No. 19 to the Department of Ecology (dated June 4, posted June 11) is the first to point at imminent field work: it lists 'preparation for site redevelopment and site characterization activities planned for the end of June 2026' — the next on-site step after January's groundwater sampling. Its tentative milestone schedule has demolition in Q2 2026, contained-in (CID) soil characterization and a contained-in disposal decision in Q2–Q3 2026, remedial excavation in Q3–Q4 2026, an interim remedial action complete by Q4 2026–Q1 2027, and the final Remedial Action Report in Q2–Q3 2027 — all expressly contingent on Bellevue permitting and market conditions. The next report (No. 20) is due September 10.

    Source ↗
  • Jun 2026

    Demolition under way

    With the demolition permit issued, Dickson Demolition has equipment on the block and is taking the two buildings down. Excavation waits on the mass-excavation/shoring and below-grade permits, both still in city review in mid-2026 — the below-grade permit is held pending structural drawings and an ongoing peer review — so Onni's hoped-for July excavation start is uncertain. A $53.5M Wells Fargo loan was recorded the prior year.

    Source ↗
  • Summer 2026

    Permitting → excavation

    Onni's Brendan Lawrence told a Bellevue Downtown Association breakfast the team is shifting from permitting into excavation and construction this summer.

    Source ↗
  • Apr 2026

    Project profile published

    Coverage details the full program — 1,300+ homes, 400+ hotel suites, ~896k sf of office, two pools, a daycare and a 15,000 sf plaza — calling it the largest construction project in Washington State.

    Source ↗
  • Jan 2026

    Cleanup mobilizes — first field work

    After roughly eighteen quarterly reports of 'no work performed at the site,' crews collect groundwater samples for a dewatering assessment — the first field activity on the contaminated-site cleanup since it was re-enrolled in 2021, and an early sign of mobilization ahead of demolition.

    Source ↗
  • Jun 2025

    Cleanup schedule fused to construction

    An environmental consultant's quarterly progress report to the Department of Ecology (Expedited Voluntary Cleanup Program No. XN0011) schedules contaminated-soil work to track the build: demolition and soil characterization in early 2026, remedial excavation in late 2026, and a final remedial action report in 2027.

    Source ↗
  • 2025

    Plan refined

    An approved update (permit 24-113252-LJ) trimmed below-grade parking from 2,479 stalls across seven levels to 1,712 across five, roughly doubled indoor bike storage to ~532, and relocated the central energy plant to Tower 1.

    Source ↗
  • Jun 2022

    Master Plan & Design Review approved

    The City of Bellevue approved the Master Development Plan and Design Review for the three-tower scheme.

    Source ↗
  • 2019

    Site acquired

    Onni Group bought the ~4-acre block from Sterling Realty Organization for about $116 million — recorded February 12, 2019 as a bargain-and-sale deed (King County excise #2973252), conveying title to ONNI 106th Ave Bellevue LLC.

    Source ↗