Downtown Bellevue pipeline

What else is being built in Downtown Bellevue

Onni 606 is one of several large projects moving through Downtown Bellevue at once. This page tracks the others: which are under construction, which hold land-use approvals but have not started, and which are still in review or on hold. Statuses were checked against the City of Bellevue permit portal and dated reporting as of November 4, 2026.


A master development plan (LP) or design review (LD) decision sets what may be built; it does not authorize construction. Building permits (BB) do. Where only reporting supports a status, the entry says so and gives its date. The city's own Downtown Major Projects list was last published for Q1 2025, so it is cited only for older figures.

Status as of November 4, 2026

Under construction or finishing out

Projects with issued building permits, reported groundbreakings, or interior build-out under way.

Status as of November 4, 2026

Approved, not yet under construction

Projects holding a master development plan or design review approval, with no confirmed construction start.

Status as of November 4, 2026

In review or early design

Applications still under city review, or projects in pre-application and design.

Status as of November 4, 2026

On hold or withdrawn

Approved phases with no announced timeline, and applications the city record shows as canceled.

Status as of November 4, 2026

Recently completed

Towers along the 106th and 108th Avenue NE spine finished since 2024.

Often searched

Names that are not development projects

  • Tower 333An existing 20-story office tower at 333 108th Ave NE, completed in 2008 and leased to Amazon. No development activity has been found.
  • Lincoln Square (W Bellevue and 400 Lincoln Square)Kemper Development's towers on Bellevue Way NE were completed in 2017.