Downtown Bellevue pipeline
What else is being built in Downtown Bellevue
Onni 606 is one of several large projects moving through Downtown Bellevue at once. This page tracks the others: which are under construction, which hold land-use approvals but have not started, and which are still in review or on hold. Statuses were checked against the City of Bellevue permit portal and dated reporting as of November 4, 2026.
A master development plan (LP) or design review (LD) decision sets what may be built; it does not authorize construction. Building permits (BB) do. Where only reporting supports a status, the entry says so and gives its date. The city's own Downtown Major Projects list was last published for Q1 2025, so it is cited only for older figures.
Status as of November 4, 2026
Under construction or finishing out
Projects with issued building permits, reported groundbreakings, or interior build-out under way.
Bellevue 600 Tower 1
Bellevue 600 Phase 1, B600
About 600 ft
Office and retail · Amazon · 600 108th Ave NE
Topped out in September 2024. Amazon filed permits in January 2026 to restart work, and interior construction resumed in early 2026.
Reported story counts differ (43 or 45). No occupancy date has been announced.
The Artise
25 stories, about 611,000 sf
Office, leased entirely to Amazon · Schnitzer West and Baupost · 788 106th Ave NE
The shell was delivered in January 2024. Filings from September 2025 show Amazon resuming the interior build-out; the Seattle Daily Journal of Commerce reported the building still empty in July 2026.
The Artise is immediately north of the Onni 606 block, across NE 8th Street.
555 Tower
Amazon "Sonic"
About 600 ft, 42 stories
Office · Vulcan Real Estate (leased to Amazon) · 555 108th Ave NE
The lower floors opened at the end of 2023. Build-out of the upper 22 floors restarted in April 2024, reported for completion as early as the first quarter of 2025.
No source found confirming the upper floors are finished.
Filament East and West
Plaza 200
Two 8-story buildings, 293 homes
Apartments and retail · Holland Partner Group · 201 106th Ave NE and 200–224 105th Ave NE
Bellevue issued the garage building permits April 15, 2026. Holland reported a September 2026 start target and estimated completion in December 2028.
Holland bought the site from Vulcan for $36 million in 2025. A construction start has not been confirmed.
- City of Bellevue permit 24-103701-BB — garage building permit (issued Apr. 15, 2026)
- City of Bellevue permit 24-103684-BB — garage building permit (issued Apr. 15, 2026)
- Filament project update — Holland Partner Group, July 13, 2026
- Vulcan sells Bellevue site for $36M — Downtown Bellevue Network, Nov. 27, 2025
Versant Bellevue
351 homes
Apartments · High Street Residential and PGIM · 11040 Main St
Groundbreaking reported in March 2026.
Status as of November 4, 2026
Approved, not yet under construction
Projects holding a master development plan or design review approval, with no confirmed construction start.
Pinnacle Bellevue North
Pinnacle North
Up to 26 stories, about 1,600 homes
Apartments and retail in six towers · Pinnacle International · 10112 NE 10th St
Bellevue issued the master development plan and design review August 28, 2025; both expire August 28, 2027. The three building permits on record are canceled.
Downtown Bellevue Network reported completion anticipated around 2028, but no construction start has been found. Unit counts differ between the city list (1,613) and the permit filing (1,451).
Kanon
Kanon Office Towers
Two 15-story towers, about 642,000 sf
Office with ground-floor retail · Beam Reach Partners · 222 112th Ave NE
Bellevue issued the master development plan and design review March 11, 2026. Reporting said the first tower could open as early as January 2029.
Belle Vista
Tishman Speyer, 112th Ave NE and Main St
About 1.1 million sf
Office in four towers, built in two phases · Tishman Speyer · 100 112th Ave NE (former Sheraton site)
Design review was reissued June 3, 2026 and expires June 2, 2028. The applicant's February 2026 environmental checklist anticipates Phase 1 from demolition to occupancy in 2026–2030.
That timing is the applicant's; no construction start has been found.
Washington Square
Office of 9 to 12 stories; residential of about 27 stories
Office tower, then a residential tower · Skanska · 10620 NE 8th St
Bellevue issued the master development plan September 24, 2025; it expires September 24, 2027. The office phase goes first, and the residential phase's timing was not yet set.
The city list and reporting give different office heights (9 and 12 stories).
Bellevue North
A 28-story tower and three mid-rises, about 900 homes
Apartments · Wallace Properties · 1000–1100 Bellevue Way NE
Bellevue issued the master development plan March 25, 2026.
HoM District
formerly Main Street Place
Up to 16 stories
Office and apartments · Hines · 103 110th Ave NE
Bellevue issued the master development plan October 1, 2025; it expires October 1, 2027. The Bellevue Downtown Association described it in April 2026 as moving through design.
Cloudvue
formerly Elev8
Three towers; a later residential concept described three 600-ft towers
Office, hotel and residential towers · Stanford Hotels Group · 10855 NE 8th St
The city's Q1 2025 list showed the office-led plan entitled. A pre-development record for a residential version closed January 17, 2025, and in September 2025 the owner was seeking interim tenants for the church on the site.
The newest sources are more than a year old, and no construction start has been found.
Status as of November 4, 2026
In review or early design
Applications still under city review, or projects in pre-application and design.
The Arcadian
18 stories, about 450,000 sf
Office · Schnitzer West · 120 106th Ave NE
Design review is still pending with the city. Schnitzer West told the Seattle Daily Journal of Commerce in July 2026 it expects to break ground in the near term.
Main & Bellevue
Three towers of about 26 stories
Residential · Bosa Development · 102 Bellevue Way NE
The master development plan and first-phase design review, applied for August 1, 2024, are still pending.
Bevel
12 stories, about 180 ft
Mass-timber office · Skanska · 106th Ave NE and NE 9th Pl
In design and entitlement; the architects released the design in August 2026.
Bellevue Square expansion
Kemper Development's "The Bellevue"
Three towers of up to 24 stories (2023 proposal)
Retail, residential and hotel · Kemper Development Co. · 401 Bellevue Way NE
The city's Q1 2025 list showed only a pre-application conference. No design review application has been found.
The newest sources are more than a year old.
Status as of November 4, 2026
On hold or withdrawn
Approved phases with no announced timeline, and applications the city record shows as canceled.
Bellevue 600 Tower 2
Bellevue 600 Phase 2
Reported at 27 to 34 stories; sources differ
Office · Amazon · 600 108th Ave NE
On hold. Amazon opened a 1.75-acre public park, The Meadow, on the Tower 2 site in April 2026 and said a timeline for that phase had not been announced.
Some databases still list Phase 2 as under construction; the April 2026 reporting supersedes them.
Pinnacle Bellevue South
Pinnacle South
Up to 26 stories (2024 reporting)
Residential, retail and hotel · Pinnacle International · 10116 NE 8th St
The city record shows both the master development plan and design review applications canceled.
Status as of November 4, 2026
Recently completed
Towers along the 106th and 108th Avenue NE spine finished since 2024.
Four106
21 stories, about 485,000 sf
Office · Patrinely Group and Dune Real Estate Partners · 380 106th Ave NE
Topped out July 2024 and finished in 2025; tenant improvements were under way in April 2026.
West Main
16 to 19 stories
Office and retail in three towers · Vulcan Real Estate (leased to Amazon) · 117 106th Ave NE
Vulcan completed the shells in 2024, and Amazon moved into the first tower. Amazon filed permits for the remaining two towers in January 2026.
Often searched
Names that are not development projects
- Tower 333An existing 20-story office tower at 333 108th Ave NE, completed in 2008 and leased to Amazon. No development activity has been found.
- Lincoln Square (W Bellevue and 400 Lincoln Square)Kemper Development's towers on Bellevue Way NE were completed in 2017.