The construction record

Latest progress.

What changed, what is approved, and what the camera can show.


Published updates

The latest record

Recent published updates could not be checked. These dated articles remain available.

  1. Conveyor and podium reviews advance while both Onni 606 permits remain pending

    Bellevue approved the pit conveyors' electrical review and two podium utility reviews August 24; neither action issued a permit or cleared the project's larger excavation gates.

  2. Ecology sets disposal conditions for 21,250 tons of PCE-affected Onni 606 soil

    The August 13 contained-in determination creates a documented disposal pathway through April 2027; it is not a No Further Action decision or approval of the cleanup plan.

  3. Long steel-beam haul and gas relocation surface as Onni 606 shoring review advances

    Two August 13 street-use filings cover 64- to 96-foot beam deliveries and a 425-foot PSE gas-main relocation; meanwhile, Bellevue is reviewing Revision 15 of the still-pending shoring permit.

  4. New Onni 606 permit details twin excavation-pit conveyor systems

    Bellevue filing 26-117887-BG seeks electrical approval for two 600-amp, 480-volt conveyor systems for NW Construction; an August 11 review requested control-panel listing information, while the fuel-cube permit is now Ready to Issue.

  5. July 2026 progress report: Onni 606 moves into early earthwork

    A completed-month review pairs the verified July 13–21 visual sequence with permit, inspection and environmental records checked through July 31.