The construction record
Latest progress.
What changed, what is approved, and what the camera can show.
Published reporting
The latest record
Eight ongoing pile inspections extend Onni 606's shoring record →
Bellevue logged pile inspections from September 28 through October 14 under the issued shoring permit; the permanent garage's inspection list remains empty.
Latest cleanup report records summer soil characterization →
TRC's September report confirms June–July characterization and retains a tentative excavation schedule; the next quarterly report is due December 10.
City minutes document Bellgate's removal and required return →
An April Arts Commission update describes secure storage and periodic inspections during redevelopment, with reinstallation tied to construction completion.
October coverage tracks excavation and a proposed program shift →
DJC and The Registry report renewed activity; their garage and tower figures need to be read alongside dated city approvals.
Bellevue clears shoring start as Onni 606's central cut expands →
A September 18 inspection says shoring may start, with an east-side soil-nail condition; camera frames show a larger cut and new tall-mast equipment.
Automated camera observations