The construction record

Latest progress.

What changed, what is approved, and what the camera can show.


Published reporting

The latest record

  1. Eight ongoing pile inspections extend Onni 606's shoring record →

    Bellevue logged pile inspections from September 28 through October 14 under the issued shoring permit; the permanent garage's inspection list remains empty.

  2. Latest cleanup report records summer soil characterization →

    TRC's September report confirms June–July characterization and retains a tentative excavation schedule; the next quarterly report is due December 10.

  3. City minutes document Bellgate's removal and required return →

    An April Arts Commission update describes secure storage and periodic inspections during redevelopment, with reinstallation tied to construction completion.

  4. October coverage tracks excavation and a proposed program shift →

    DJC and The Registry report renewed activity; their garage and tower figures need to be read alongside dated city approvals.

  5. Bellevue clears shoring start as Onni 606's central cut expands →

    A September 18 inspection says shoring may start, with an east-side soil-nail condition; camera frames show a larger cut and new tall-mast equipment.

Automated camera observations

From the camera

Browse dated observations →