Find a fact
Search the project record.
Search the same sourced reference material used across the site, including published news.
Results for “Completion”
When will Onni 606 be finished? →
No exact completion date has been publicly announced in the records reviewed through October 14, 2026. Onni has described a construction program of close to five years. The 2022 design-review schedule had the three towers topping out in roughly October 2027, February 2029 and April 2030; those…
/faqProject update (Aug 1, 2026) — Completed July report: early earthwork, with deep excavation still gated →
Aug 1, 2026: The human-reviewed completed-month record uses July 13 as its earliest verified comparison visual and July 21 as its latest, without presenting either as a calendar endpoint. Bellevue records through the July 31 cutoff document soil export, a Tower 2 structural revision request and…
/news/2026-07-onni-606-construction-progress-reportOnni Group completed project — Two Gilmore Place →
Two Gilmore Place (Burnaby, BC, Condo, completed 2024): 64 storeys · 708 ft · tallest tower in BC. The signature tower of Onni's Gilmore Place master-plan at Brentwood — the tallest building in British Columbia and the tallest residential tower in Western Canada.
/developerOnni Group completed project — 1335 Howe →
1335 Howe (Vancouver, BC, Condo + Level hotel, completed 2022): 40 storeys · 120 homes. A condo-and-extended-stay tower in Vancouver's Beach District, pairing 120 residences with an Onni-run Level hotel and ground-floor retail.
/developerOnni Group completed project — Westlake Encore →
Westlake Encore (Etobicoke, Toronto, ON, Condo, completed 2018): 46 storeys · 481 ft · 523 units. The final phase of Onni's Westlake Village master-planned community on the Humber Bay waterfront.
/developerOnni Group completed project — 820 Olive →
820 Olive (Los Angeles, CA, Rental, completed 2019): 49 floors · 563 ft · 516 units. A downtown LA rental high-rise on the Broadway/Olive corridor — briefly the tallest residential tower in California on completion.
/developerOnni Group completed project — Old Town Park →
Old Town Park (Chicago, IL, Rental, completed 2018): 32 storeys · 405 units · first of three towers. The first delivered tower of Onni's three-building Old Town Park master-plan in Chicago's Old Town.
/developerHas Onni 606 started shoring or the deep garage excavation? →
Bellevue recorded eight pile inspections under issued shoring permit 21-134212-BV from September 28 through October 14, 2026, all marked Ongoing without notes. These follow a September 18 preconstruction entry allowing shoring to start, with later city approval required at the specified east-side…
/faqCurrent construction phase — what's happening on site now →
As of October 14, 2026, the current phase is: Earthwork — ongoing shoring pile inspections. Bellevue lists eight ongoing pile inspections under the shoring permit from September 28 through October 14. The September 18 condition still calls for later city approval at the specified east-side…
/liveProject timeline →
2019 — Site acquired: Onni Group purchases the ~4-acre Barnes & Noble block for roughly $116M. 2021 — Cleanup track opens: Ecology's December 15 opinion says that, if the proposed independent cleanup is completed as described, further remedial action will likely not be needed. It is prospective—not…
/timelineProject update (Oct 14, 2026) — Eight ongoing pile inspections under the shoring permit →
Oct 14, 2026: Bellevue recorded eight pile inspections from September 28 through October 14 under 21-134212-BV, all marked Ongoing without notes. They extend the shoring field record but do not confirm completion, resolution of the east-side soil-nail condition or a permanent garage start. The…
/news/2026-10-14-shoring-pile-inspectionsProject update (Oct 14, 2026) — September cleanup report now in the public file →
Oct 14, 2026: TRC's September 10 Quarterly Progress Report No. 20 confirms summer soil characterization and retains tentative excavation and reporting targets. It does not establish an actual remedial-excavation start or cleanup completion. The next report is due December 10.
/news/2026-10-14-ecology-quarterly-report-20Project update (Sep 23, 2026) — Shoring cleared to start as the central cut expands →
Sep 23, 2026: Bellevue's September 18 preconstruction inspection under shoring permit 21-134212-BV says work may start, with a later city approval required for east-side soil nails at the elevation noted by the inspector. September 12–22 camera frames show a broader central cut and a tall-mast rig;…
/news/2026-09-23-shoring-preconstruction-central-cutProject update (Jul 23, 2026) — Tower 2 structural review requests another revision →
Jul 23, 2026: Bellevue completed the Revision 2 structural review of Tower 2 building permit 25-105109-BB on July 23 with a revision request. The reviewer said the Revision 2 submittal was the same as Revision 1 and directed the applicant back to structural comments posted June 24. The permit…
/news/2026-07-23-tower-2-structural-review-requests-another-revisionProject update (Jul 17, 2026) — Early excavation begins under issued grading permit →
Jul 17, 2026: Camera frames show excavators working exposed soil across a broad shallow cut and dump trucks moving through the site. Bellevue permit 21-133872-GD was issued for early clear-and-grade work for mass excavation, completed its second preconstruction conference June 17 and received an…
/news/2026-07-17-early-excavation-under-issued-grading-permitProject update (Jun 2026) — Cleanup report No. 19 — fieldwork slated for end of June →
Jun 2026: TRC's Quarterly Progress Report No. 19 to the Department of Ecology (dated June 4, posted June 11) is the first to point at imminent field work: it lists 'preparation for site redevelopment and site characterization activities planned for the end of June 2026' — the next on-site step…
/timelineConstruction phase guide — Demolition and block clearance →
01; status Complete; records 25-126179-BE · issued Jan 12, 2026. Visible evidence: The former John Danz Theatre and Belle Lanes/Barnes & Noble structures disappear, followed by slab breaking, sorting and removal. What that evidence supports: An issued demolition permit plus field removal…
/timelineConstruction phase guide — Perimeter shoring →
03; status Ongoing pile inspections; completion unconfirmed; records 21-134212-BV · issued Sep 3 · pile inspections Sep 28–Oct 14. Visible evidence: Once authorized and mobilized, a continuous earth-retention operation around the excavation edge would be the durable field signal—not simply a drill…
/timelineConstruction phase guide — Tower structure and topping out →
07; status Future / pending permits; records 25-105181-BB · 25-105109-BB · 25-105295-BB. Visible evidence: Independent cores and floor plates repeat upward from the shared base; topping out means a tower's primary structure has reached its planned roof level. What that evidence supports: An issued…
/timelineConstruction phase guide — Enclosure, interiors and public realm →
08; status Future; records Later trade, tenant and occupancy approvals. Visible evidence: Facade installation trails structure while interior systems, testing, streetscape, plaza and through-block connections proceed on overlapping tracks. What that evidence supports: Final inspections and…
/timeline