Find a fact

Search the project record.

Search the same sourced reference material used across the site, including published news.


Results for “Completion”

  1. When will Onni 606 be finished?

    No exact completion date has been publicly announced in the records reviewed through September 7, 2026. Onni has described a construction program of close to five years. The 2022 design-review schedule had the three towers topping out in roughly October 2027, February 2029 and April 2030; those…

    /faq
  2. Project update (Aug 1, 2026) — Completed July report: early earthwork, with deep excavation still gated

    Aug 1, 2026: The human-reviewed completed-month record uses July 13 as its earliest verified comparison visual and July 21 as its latest, without presenting either as a calendar endpoint. Bellevue records through the July 31 cutoff document soil export, a Tower 2 structural revision request and…

    /news/2026-07-onni-606-construction-progress-report
  3. Onni Group completed project — Two Gilmore Place

    Two Gilmore Place (Burnaby, BC, Condo, completed 2024): 64 storeys · 708 ft · tallest tower in BC. The signature tower of Onni's Gilmore Place master-plan at Brentwood — the tallest building in British Columbia and the tallest residential tower in Western Canada.

    /developer
  4. Onni Group completed project — 1335 Howe

    1335 Howe (Vancouver, BC, Condo + Level hotel, completed 2022): 40 storeys · 120 homes. A condo-and-extended-stay tower in Vancouver's Beach District, pairing 120 residences with an Onni-run Level hotel and ground-floor retail.

    /developer
  5. Onni Group completed project — Westlake Encore

    Westlake Encore (Etobicoke, Toronto, ON, Condo, completed 2018): 46 storeys · 481 ft · 523 units. The final phase of Onni's Westlake Village master-planned community on the Humber Bay waterfront.

    /developer
  6. Onni Group completed project — 820 Olive

    820 Olive (Los Angeles, CA, Rental, completed 2019): 49 floors · 563 ft · 516 units. A downtown LA rental high-rise on the Broadway/Olive corridor — briefly the tallest residential tower in California on completion.

    /developer
  7. Onni Group completed project — Old Town Park

    Old Town Park (Chicago, IL, Rental, completed 2018): 32 storeys · 405 units · first of three towers. The first delivered tower of Onni's three-building Old Town Park master-plan in Chicago's Old Town.

    /developer
  8. Project timeline

    2019 — Site acquired: Onni Group purchases the ~4-acre Barnes & Noble block for roughly $116M. 2021 — Cleanup track opens: Ecology's December 15 opinion says that, if the proposed independent cleanup is completed as described, further remedial action will likely not be needed. It is prospective—not…

    /timeline
  9. Project update (Jul 23, 2026) — Tower 2 structural review requests another revision

    Jul 23, 2026: Bellevue completed the Revision 2 structural review of Tower 2 building permit 25-105109-BB on July 23 with a revision request. The reviewer said the Revision 2 submittal was the same as Revision 1 and directed the applicant back to structural comments posted June 24. The permit…

    /news/2026-07-23-tower-2-structural-review-requests-another-revision
  10. Project update (Jul 17, 2026) — Early excavation begins under issued grading permit

    Jul 17, 2026: Camera frames show excavators working exposed soil across a broad shallow cut and dump trucks moving through the site. Bellevue permit 21-133872-GD was issued for early clear-and-grade work for mass excavation, completed its second preconstruction conference June 17 and received an…

    /news/2026-07-17-early-excavation-under-issued-grading-permit
  11. Project update (Jun 2026) — Cleanup report No. 19 — fieldwork slated for end of June

    Jun 2026: TRC's Quarterly Progress Report No. 19 to the Department of Ecology (dated June 4, posted June 11) is the first to point at imminent field work: it lists 'preparation for site redevelopment and site characterization activities planned for the end of June 2026' — the next on-site step…

    /timeline
  12. Construction phase guide — Demolition and block clearance

    01; status Complete; records 25-126179-BE · issued Jan 12, 2026. Visible evidence: The former John Danz Theatre and Belle Lanes/Barnes & Noble structures disappear, followed by slab breaking, sorting and removal. What that evidence supports: An issued demolition permit plus field removal…

    /timeline
  13. Construction phase guide — Perimeter shoring

    03; status Permit issued; field start unconfirmed; records 21-134212-BV · Issued in September 7 record. Visible evidence: Once authorized and mobilized, a continuous earth-retention operation around the excavation edge would be the durable field signal—not simply a drill rig elsewhere on the block.…

    /timeline
  14. Construction phase guide — Tower structure and topping out

    07; status Future / pending permits; records 25-105181-BB · 25-105109-BB · 25-105295-BB. Visible evidence: Independent cores and floor plates repeat upward from the shared base; topping out means a tower's primary structure has reached its planned roof level. What that evidence supports: An issued…

    /timeline
  15. Construction phase guide — Enclosure, interiors and public realm

    08; status Future; records Later trade, tenant and occupancy approvals. Visible evidence: Facade installation trails structure while interior systems, testing, streetscape, plaza and through-block connections proceed on overlapping tracks. What that evidence supports: Final inspections and…

    /timeline
  16. Economic & civic impact

    ≈4,000 Workers supported (office, hotel & retail (SEPA)); $116M Land cost (≈4 acres, acquired 2019); ≈5 yrs Construction (April 2026 reported program; no current completion date); 15,000 sf Public plaza (open space for the city).

    /
  17. Glossary: Topping out

    Topping out: The milestone when a building's highest structural element is placed — i.e. it reaches full height, before the facade and interiors are finished.

    /glossary
  18. Glossary: SEPA

    SEPA: Washington's State Environmental Policy Act — the environmental review a major project must complete.

    /glossary
  19. Glossary: No Further Action Likely opinion

    No Further Action Likely opinion: A prospective Ecology opinion that, if a proposed independent cleanup is completed as described, further remedial action will likely not be needed. The December 2021 Onni 606 opinion is conditional; the August 2026 CID did not replace it or declare the cleanup…

    /glossary
  20. Environmental cleanup of the 606 site — overview

    Beneath the permits and the cranes runs a second, quieter story most coverage misses: an independent cleanup, enrolled for Washington Ecology technical review, of a dry-cleaning-solvent plume believed to have migrated from properties across NE 8th Street — and whose schedule is fused to the deep…