Onni 606 · July 1, 2026

Demolition done: the 606 block is cleared, but excavation still waits on permits

Dickson Demolition has taken both buildings down and graded the four-acre superblock flat. The dig can't start until the mass-excavation, shoring and below-grade permits clear city review.


As of early July 2026, the roughly four-acre block at 606 (and 620) 106th Avenue NE — the site of Onni Group's planned three-tower Onni 606 — has been fully cleared. The two buildings that stood on it are gone; Dickson Demolition took them down after the City of Bellevue issued the demolition permit, and the block has been graded to a flat dirt-and-concrete pad. What remains is a small cluster of staged heavy equipment — an excavator and dozers — sitting on the open ground.

The next phase, excavation, has not begun. Onni's plan calls for five below-grade levels holding 1,712 parking stalls, which means a deep dig on a downtown block. Two permits gate that work, and both were still in city review in mid-2026: the mass-excavation and shoring permit (21-134212-BV) and the below-grade structural permit for parking levels P2 through P5 (24-104362-BB). The below-grade permit has been held pending structural drawings and an ongoing peer review.

The timing gap matters. Onni representatives had pointed to a summer 2026 excavation start — Brendan Lawrence told a Bellevue Downtown Association breakfast the team was shifting from permitting into excavation and construction this summer — but with the enabling permits unissued, that start is uncertain. A cleared pad is not the same as a dig under way.

One piece of early financing had been reported: the Seattle DJC said Wells Fargo agreed to provide a $53.5 million loan to Onni around mid-2025, describing it as help to get the project started while noting that all three towers would require substantially more capital. That supports treating it as early-work or predevelopment financing, not proof that the full construction package is in place. The four superstructure building permits — the shared podium (25-105052-BB) and the three towers (25-105181-BB, 25-105109-BB, 25-105295-BB) — remain pending, as expected, since the podium is built before the towers rise. For now the record shows a project poised at the edge of excavation, waiting on the paperwork that lets the machines start digging.