606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Monday, June 22, 2026

Construction log

Monday, June 22, 2026

75 snapshots from the live camera.


AI digest

The site was largely quiet, with only brief equipment repositioning and truck movements; the observations report small incremental changes to the debris pile, but little sustained activity. Compared with the week-earlier frame, the lot appears substantially cleared of the large debris piles, with a broad, relatively level surface and a few pieces of equipment remaining.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 12 similar no-change frames7:00 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:30 PM PT. No construction activity — the site is quiet.
      9:30 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 9:15 PM PT. No construction activity — the site is quiet.
      9:15 PM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 9:00 PM PT. No construction activity — the site is quiet.
      9:00 PM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 8:45 PM PT. No construction activity — the site is quiet.
      8:45 PM PT

      No construction activity — the site is quiet.

    6. Construction camera frame at 8:30 PM PT. No construction activity — the site is quiet.
      8:30 PM PT

      No construction activity — the site is quiet.

    7. Construction camera frame at 8:15 PM PT. No construction activity — the site is quiet.
      8:15 PM PT

      No construction activity — the site is quiet.

    8. Construction camera frame at 8:00 PM PT. No construction activity — the site is quiet.
      8:00 PM PT

      No construction activity — the site is quiet.

    9. Construction camera frame at 7:45 PM PT. No construction activity — the site is quiet.
      7:45 PM PT

      No construction activity — the site is quiet.

    10. Construction camera frame at 7:30 PM PT. No construction activity — the site is quiet.
      7:30 PM PT

      No construction activity — the site is quiet.

    11. Construction camera frame at 7:15 PM PT. No construction activity — the site is quiet.
      7:15 PM PT

      No construction activity — the site is quiet.

    12. Construction camera frame at 7:00 PM PT. No construction activity — the site is quiet.
      7:00 PM PT

      No construction activity — the site is quiet.

  3. Construction camera frame at 6:45 PM PT. The overall scene is holding steady, with no obvious changes to the arrangement of equipment or the size of the debris pile.
    6:45 PM PT

    The overall scene is holding steady, with no obvious changes to the arrangement of equipment or the size of the debris pile.

  4. Construction camera frame at 6:30 PM PT. The site maintains a consistent appearance, with no significant shifts in the debris or the positions of the parked machinery.
    6:30 PM PT

    The site maintains a consistent appearance, with no significant shifts in the debris or the positions of the parked machinery.

  5. Construction camera frame at 6:15 PM PT. The demolition site continues to show a nearly identical arrangement of equipment and debris.
    6:15 PM PT

    The demolition site continues to show a nearly identical arrangement of equipment and debris.

  6. 4 similar no-change frames5:15 PM–6:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:00 PM PT. The scene remains largely static, with no noticeable movement of machinery or increase in the rubble pile.
      6:00 PM PT

      The scene remains largely static, with no noticeable movement of machinery or increase in the rubble pile.

    2. Construction camera frame at 5:45 PM PT. The site’s layout is essentially unchanged, with equipment remaining in the same positions.
      5:45 PM PT

      The site’s layout is essentially unchanged, with equipment remaining in the same positions.

    3. Construction camera frame at 5:30 PM PT. The scene appears stable, with no discernible alterations to the equipment or the debris pile in the last quarter hour.
      5:30 PM PT

      The scene appears stable, with no discernible alterations to the equipment or the debris pile in the last quarter hour.

    4. Construction camera frame at 5:15 PM PT. The site’s appearance is remarkably consistent, showing no changes in equipment positioning or debris accumulation.
      5:15 PM PT

      The site’s appearance is remarkably consistent, showing no changes in equipment positioning or debris accumulation.

  7. Construction camera frame at 5:00 PM PT. The demolition site presents a familiar picture, with no readily apparent alterations to the equipment or debris.
    5:00 PM PT

    The demolition site presents a familiar picture, with no readily apparent alterations to the equipment or debris.

  8. Construction camera frame at 4:45 PM PT. The demolition site shows no appreciable differences in the placement of equipment or the size of the debris pile over the last fifteen minutes.
    4:45 PM PT

    The demolition site shows no appreciable differences in the placement of equipment or the size of the debris pile over the last fifteen minutes.

  9. Construction camera frame at 4:30 PM PT. The site continues to look very much the same, with no obvious shifts in the position of equipment or the size of the debris pile.
    4:30 PM PT

    The site continues to look very much the same, with no obvious shifts in the position of equipment or the size of the debris pile.

  10. 6 similar no-change frames3:00 PM–4:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:15 PM PT. The scene remains largely as it was, with no noticeable changes to the equipment or debris arrangement.
      4:15 PM PT

      The scene remains largely as it was, with no noticeable changes to the equipment or debris arrangement.

    2. Construction camera frame at 4:00 PM PT. The site maintains its current configuration, with no apparent movement of machinery or significant changes to the debris field.
      4:00 PM PT

      The site maintains its current configuration, with no apparent movement of machinery or significant changes to the debris field.

    3. Construction camera frame at 3:45 PM PT. The site appears static, with no discernible changes in equipment location or the amount of debris.
      3:45 PM PT

      The site appears static, with no discernible changes in equipment location or the amount of debris.

    4. Construction camera frame at 3:30 PM PT. The view across the demolition site is remarkably consistent, showing no significant shifts in equipment or debris.
      3:30 PM PT

      The view across the demolition site is remarkably consistent, showing no significant shifts in equipment or debris.

    5. Construction camera frame at 3:15 PM PT. The site presents a largely unchanged view, with the machinery and rubble pile remaining in the same positions.
      3:15 PM PT

      The site presents a largely unchanged view, with the machinery and rubble pile remaining in the same positions.

    6. Construction camera frame at 3:00 PM PT. The demolition site shows no alterations in equipment positioning or debris accumulation over the last fifteen minutes.
      3:00 PM PT

      The demolition site shows no alterations in equipment positioning or debris accumulation over the last fifteen minutes.

  11. Construction camera frame at 2:45 PM PT. Everything remains in place across the lot and staging area.
    2:45 PM PT

    Everything remains in place across the lot and staging area.

  12. Construction camera frame at 2:30 PM PT. The scene is holding steady, with no noticeable adjustments to equipment or the size of the rubble pile.
    2:30 PM PT

    The scene is holding steady, with no noticeable adjustments to equipment or the size of the rubble pile.

  13. Construction camera frame at 2:15 PM PT. The overall layout of the demolition site remains constant, with no discernible movement of equipment or significant changes to the debris.
    2:15 PM PT

    The overall layout of the demolition site remains constant, with no discernible movement of equipment or significant changes to the debris.

  14. Construction camera frame at 2:00 PM PT. The site appears stable, with equipment and the debris pile maintaining their prior positions.
    2:00 PM PT

    The site appears stable, with equipment and the debris pile maintaining their prior positions.

  15. Construction camera frame at 1:45 PM PT. A dump truck has exited the site via the driveway on the left, and another appears to be taking its place.
    1:45 PM PT

    A dump truck has exited the site via the driveway on the left, and another appears to be taking its place.

  16. 2 similar no-change frames1:15 PM–1:30 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 1:30 PM PT. No visible activity or movement has occurred across the site.
      1:30 PM PT

      No visible activity or movement has occurred across the site.

    2. Construction camera frame at 1:15 PM PT. The site maintains a largely unchanged appearance, with no obvious shifts in equipment placement or debris levels.
      1:15 PM PT

      The site maintains a largely unchanged appearance, with no obvious shifts in equipment placement or debris levels.

  17. Construction camera frame at 1:00 PM PT. The scene shows minimal alteration from the previous view, with all equipment appearing to stay in place.
    1:00 PM PT

    The scene shows minimal alteration from the previous view, with all equipment appearing to stay in place.

  18. Construction camera frame at 12:45 PM PT. The site’s appearance is remarkably consistent, with machinery and debris remaining in the same positions.
    12:45 PM PT

    The site’s appearance is remarkably consistent, with machinery and debris remaining in the same positions.

  19. Construction camera frame at 12:30 PM PT. The central rubble pile appears slightly larger, with the excavator continuing to work within it.
    12:30 PM PT

    The central rubble pile appears slightly larger, with the excavator continuing to work within it.

  20. Construction camera frame at 12:15 PM PT. The site remains relatively static, with equipment positioned as it was moments ago.
    12:15 PM PT

    The site remains relatively static, with equipment positioned as it was moments ago.

  21. Construction camera frame at 12:00 PM PT. The demolition site presents a similar view as before, with no readily apparent adjustments to the equipment or debris.
    12:00 PM PT

    The demolition site presents a similar view as before, with no readily apparent adjustments to the equipment or debris.

  22. Construction camera frame at 11:45 AM PT. No significant activity or movement is visible across the site.
    11:45 AM PT

    No significant activity or movement is visible across the site.

  23. Construction camera frame at 11:30 AM PT. A flatbed truck is exiting the site via the service road on the right.
    11:30 AM PT

    A flatbed truck is exiting the site via the service road on the right.

  24. Construction camera frame at 11:15 AM PT. The scene appears largely unchanged, though a new orange traffic cone has appeared near the service road on the right.
    11:15 AM PT

    The scene appears largely unchanged, though a new orange traffic cone has appeared near the service road on the right.

  25. Construction camera frame at 11:00 AM PT. The excavator is now working alongside a second, smaller piece of machinery in the center of the demolition zone.
    11:00 AM PT

    The excavator is now working alongside a second, smaller piece of machinery in the center of the demolition zone.

  26. Construction camera frame at 10:45 AM PT. A white van has entered the site through the driveway on the left, parking near the staging area.
    10:45 AM PT

    A white van has entered the site through the driveway on the left, parking near the staging area.

  27. Construction camera frame at 10:30 AM PT. The site remains fairly static, with no obvious shifts in equipment positioning or debris removal.
    10:30 AM PT

    The site remains fairly static, with no obvious shifts in equipment positioning or debris removal.

  28. Construction camera frame at 10:15 AM PT. The excavator appears to have repositioned itself further into the center of the demolition zone.
    10:15 AM PT

    The excavator appears to have repositioned itself further into the center of the demolition zone.

  29. Construction camera frame at 10:00 AM PT. No new activity is visible across the site.
    10:00 AM PT

    No new activity is visible across the site.

  30. Construction camera frame at 9:45 AM PT. The staging area on the upper-left appears busier, as a crane is now actively swinging a load toward the rubble pile.
    9:45 AM PT

    The staging area on the upper-left appears busier, as a crane is now actively swinging a load toward the rubble pile.

  31. Construction camera frame at 9:30 AM PT. The rubble pile has grown incrementally, with the excavator continuing to feed debris into it.
    9:30 AM PT

    The rubble pile has grown incrementally, with the excavator continuing to feed debris into it.

  32. Construction camera frame at 9:15 AM PT. The excavator in the center of the lot has shifted slightly, now angled a bit more to the right.
    9:15 AM PT

    The excavator in the center of the lot has shifted slightly, now angled a bit more to the right.

  33. Construction camera frame at 9:00 AM PT. The scene appears largely unchanged, with equipment remaining in similar positions throughout the site.
    9:00 AM PT

    The scene appears largely unchanged, with equipment remaining in similar positions throughout the site.

  34. Construction camera frame at 8:45 AM PT. A noticeable rearrangement of equipment is taking place in the upper-left staging area, with a yellow loader now positioned closer to the street.
    8:45 AM PT

    A noticeable rearrangement of equipment is taking place in the upper-left staging area, with a yellow loader now positioned closer to the street.

  35. Construction camera frame at 8:30 AM PT. A small dump truck has entered the site via the service road on the right, positioning itself near the central rubble pile.
    8:30 AM PT

    A small dump truck has entered the site via the service road on the right, positioning itself near the central rubble pile.

  36. Construction camera frame at 8:15 AM PT. The scene is remarkably consistent, showing little to no alteration in equipment positions or debris levels.
    8:15 AM PT

    The scene is remarkably consistent, showing little to no alteration in equipment positions or debris levels.

  37. Construction camera frame at 8:00 AM PT. The staging area shows a subtle shift, with a dump truck now positioned where an excavator was previously parked.
    8:00 AM PT

    The staging area shows a subtle shift, with a dump truck now positioned where an excavator was previously parked.

  38. Construction camera frame at 7:45 AM PT. The rubble pile has grown slightly, with fresh debris visible along its eastern edge.
    7:45 AM PT

    The rubble pile has grown slightly, with fresh debris visible along its eastern edge.

  39. Construction camera frame at 7:30 AM PT. Everything remains in place across the lot and staging area.
    7:30 AM PT

    Everything remains in place across the lot and staging area.

  40. Construction camera frame at 7:15 AM PT. Activity in the upper-left staging area has increased, as a loader is now actively moving debris into a waiting dump truck.
    7:15 AM PT

    Activity in the upper-left staging area has increased, as a loader is now actively moving debris into a waiting dump truck.

  41. Construction camera frame at 7:00 AM PT. The site appears stable, with no clear movement of machinery or noticeable increase in the rubble pile over the last quarter hour.
    7:00 AM PT

    The site appears stable, with no clear movement of machinery or noticeable increase in the rubble pile over the last quarter hour.

  42. 2 similar no-change frames6:30 AM–6:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:45 AM PT. The site is largely unchanged, though the shadows have shifted slightly with the sun’s movement.
      6:45 AM PT

      The site is largely unchanged, though the shadows have shifted slightly with the sun’s movement.

    2. Construction camera frame at 6:30 AM PT. The scene remains consistent, with no significant changes to the equipment arrangement or debris accumulation apparent.
      6:30 AM PT

      The scene remains consistent, with no significant changes to the equipment arrangement or debris accumulation apparent.

  43. Construction camera frame at 6:15 AM PT. A small orange excavator has moved from the central rubble pile toward the service road on the right side of the frame.
    6:15 AM PT

    A small orange excavator has moved from the central rubble pile toward the service road on the right side of the frame.

  44. Construction camera frame at 6:00 AM PT. The site continues in a quiet state, with no readily apparent adjustments to the positioning of equipment or the height of the rubble.
    6:00 AM PT

    The site continues in a quiet state, with no readily apparent adjustments to the positioning of equipment or the height of the rubble.

  45. 3 similar no-change frames5:15 AM–5:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 5:45 AM PT. The scene is holding steady, with no noticeable alterations to the layout of equipment or the size of the debris pile.
      5:45 AM PT

      The scene is holding steady, with no noticeable alterations to the layout of equipment or the size of the debris pile.

    2. Construction camera frame at 5:30 AM PT. The demolition site presents a static view, with all equipment remaining in the same positions as before.
      5:30 AM PT

      The demolition site presents a static view, with all equipment remaining in the same positions as before.

    3. Construction camera frame at 5:15 AM PT. The site appears much the same as before, with no discernible movement of equipment or increase in the rubble pile.
      5:15 AM PT

      The site appears much the same as before, with no discernible movement of equipment or increase in the rubble pile.

  46. Construction camera frame at 5:00 AM PT. The site remains largely as it was, with no obvious shifts in machinery or the debris field.
    5:00 AM PT

    The site remains largely as it was, with no obvious shifts in machinery or the debris field.

  47. 6 similar no-change frames12:00 AM–4:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:45 AM PT. Visibility has improved, revealing a quiet site with no apparent changes in equipment or debris levels.
      4:45 AM PT

      Visibility has improved, revealing a quiet site with no apparent changes in equipment or debris levels.

    2. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    6. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.