606

606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Wednesday, July 1, 2026

Construction log

Wednesday, July 1, 2026

74 snapshots from the live camera.


AI digest

The site remained largely quiet, with the excavator shifting around the central debris pile and trucks and vans briefly entering or leaving the staging area. By the final frame, the excavator was visible near the center; no substantial change to the ground or debris layout is apparent.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 3 similar no-change frames9:15 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:30 PM PT. No construction activity — the site is quiet.
      9:30 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 9:15 PM PT. No construction activity — the site is quiet.
      9:15 PM PT

      No construction activity — the site is quiet.

  3. Construction camera frame at 9:00 PM PT. The excavator has shifted slightly to the right, continuing to work on the central rubble pile.
    9:00 PM PT

    The excavator has shifted slightly to the right, continuing to work on the central rubble pile.

  4. 2 similar no-change frames8:30 PM–8:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:45 PM PT. Everything on site appears to be holding its position, with no noticeable alterations to the layout or debris.
      8:45 PM PT

      Everything on site appears to be holding its position, with no noticeable alterations to the layout or debris.

    2. Construction camera frame at 8:30 PM PT. The scene presents a consistent picture, with no apparent shifts in the position of equipment or the size of the debris.
      8:30 PM PT

      The scene presents a consistent picture, with no apparent shifts in the position of equipment or the size of the debris.

  5. Construction camera frame at 8:15 PM PT. The site appears stable, with no obvious movement of machinery or significant alteration to the rubble pile.
    8:15 PM PT

    The site appears stable, with no obvious movement of machinery or significant alteration to the rubble pile.

  6. 6 similar no-change frames6:45 PM–8:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:00 PM PT. No construction activity — the site is quiet.
      8:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 7:45 PM PT. No construction activity — the site is quiet.
      7:45 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 7:30 PM PT. The scene looks largely unchanged, with the excavator continuing its work at the same spot on the debris pile.
      7:30 PM PT

      The scene looks largely unchanged, with the excavator continuing its work at the same spot on the debris pile.

    4. Construction camera frame at 7:15 PM PT. The site remains quiet, with no discernible changes in equipment or the debris field over the last quarter hour.
      7:15 PM PT

      The site remains quiet, with no discernible changes in equipment or the debris field over the last quarter hour.

    5. Construction camera frame at 7:00 PM PT. The demolition site remains steady, with no noticeable alterations to equipment positioning or debris accumulation.
      7:00 PM PT

      The demolition site remains steady, with no noticeable alterations to equipment positioning or debris accumulation.

    6. Construction camera frame at 6:45 PM PT. The scene presents a consistent picture, with no apparent shifts in equipment or the size of the rubble.
      6:45 PM PT

      The scene presents a consistent picture, with no apparent shifts in equipment or the size of the rubble.

  7. Construction camera frame at 6:30 PM PT. The excavator appears to have shifted slightly to the right, continuing to work on the central pile of debris.
    6:30 PM PT

    The excavator appears to have shifted slightly to the right, continuing to work on the central pile of debris.

  8. Construction camera frame at 6:15 PM PT. Everything on site appears to be holding its position, with no new arrivals or visible progress on the demolition.
    6:15 PM PT

    Everything on site appears to be holding its position, with no new arrivals or visible progress on the demolition.

  9. 2 similar no-change frames5:45 PM–6:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:00 PM PT. The demolition site continues at the same pace, showing no significant movement of equipment or increase in the debris pile.
      6:00 PM PT

      The demolition site continues at the same pace, showing no significant movement of equipment or increase in the debris pile.

    2. Construction camera frame at 5:45 PM PT. The scene is largely unchanged, with the excavator continuing work in the center of the demolition zone.
      5:45 PM PT

      The scene is largely unchanged, with the excavator continuing work in the center of the demolition zone.

  10. Construction camera frame at 5:30 PM PT. A white van has entered the site via the driveway on the left, parking near the staging area.
    5:30 PM PT

    A white van has entered the site via the driveway on the left, parking near the staging area.

  11. Construction camera frame at 5:15 PM PT. The site remains remarkably stable, with no obvious changes to the rubble pile or equipment positions.
    5:15 PM PT

    The site remains remarkably stable, with no obvious changes to the rubble pile or equipment positions.

  12. Construction camera frame at 5:00 PM PT. The scene is holding steady, with no noticeable adjustments to machinery or the debris field.
    5:00 PM PT

    The scene is holding steady, with no noticeable adjustments to machinery or the debris field.

  13. 2 similar no-change frames4:30 PM–4:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:45 PM PT. The site appears quiet, with no discernible shifts in equipment placement or debris accumulation over the past quarter hour.
      4:45 PM PT

      The site appears quiet, with no discernible shifts in equipment placement or debris accumulation over the past quarter hour.

    2. Construction camera frame at 4:30 PM PT. The site presents a static view, with no clear alterations to the position of equipment or the amount of debris.
      4:30 PM PT

      The site presents a static view, with no clear alterations to the position of equipment or the amount of debris.

  14. Construction camera frame at 4:15 PM PT. The demolition site shows little visible progression, with equipment remaining in similar positions as before.
    4:15 PM PT

    The demolition site shows little visible progression, with equipment remaining in similar positions as before.

  15. Construction camera frame at 4:00 PM PT. The scene appears largely unchanged, though the excavator’s position within the rubble pile seems slightly different.
    4:00 PM PT

    The scene appears largely unchanged, though the excavator’s position within the rubble pile seems slightly different.

  16. Construction camera frame at 3:45 PM PT. The overall scene remains consistent, with the excavator continuing to work within the central debris pile.
    3:45 PM PT

    The overall scene remains consistent, with the excavator continuing to work within the central debris pile.

  17. 2 similar no-change frames3:15 PM–3:30 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 3:30 PM PT. The site remains remarkably still, showing no apparent movement of machinery or significant changes to the debris.
      3:30 PM PT

      The site remains remarkably still, showing no apparent movement of machinery or significant changes to the debris.

    2. Construction camera frame at 3:15 PM PT. The scene is holding steady, with no noticeable changes to the equipment or the debris field in the last fifteen minutes.
      3:15 PM PT

      The scene is holding steady, with no noticeable changes to the equipment or the debris field in the last fifteen minutes.

  18. Construction camera frame at 3:00 PM PT. Activity on site is minimal, although the excavator appears to have shifted slightly within the rubble pile.
    3:00 PM PT

    Activity on site is minimal, although the excavator appears to have shifted slightly within the rubble pile.

  19. Construction camera frame at 2:45 PM PT. The site presents a largely consistent view, with no discernible alterations to the equipment or debris field over the last fifteen minutes.
    2:45 PM PT

    The site presents a largely consistent view, with no discernible alterations to the equipment or debris field over the last fifteen minutes.

  20. Construction camera frame at 2:30 PM PT. The demolition progresses at a measured pace, though the scene is presently quite similar to the last check-in.
    2:30 PM PT

    The demolition progresses at a measured pace, though the scene is presently quite similar to the last check-in.

  21. 3 similar no-change frames1:45 PM–2:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 2:15 PM PT. The site appears largely unchanged, with the excavator continuing work in the same location within the rubble.
      2:15 PM PT

      The site appears largely unchanged, with the excavator continuing work in the same location within the rubble.

    2. Construction camera frame at 2:00 PM PT. The demolition site remains quite static, with no obvious shifts in equipment positioning or debris accumulation.
      2:00 PM PT

      The demolition site remains quite static, with no obvious shifts in equipment positioning or debris accumulation.

    3. Construction camera frame at 1:45 PM PT. The demolition site maintains a similar appearance, with no significant changes to equipment or debris levels apparent in the last quarter hour.
      1:45 PM PT

      The demolition site maintains a similar appearance, with no significant changes to equipment or debris levels apparent in the last quarter hour.

  22. Construction camera frame at 1:30 PM PT. The overall view of the demolition site is consistent, with the excavator still working within the central rubble area.
    1:30 PM PT

    The overall view of the demolition site is consistent, with the excavator still working within the central rubble area.

  23. 5 similar no-change frames12:15 PM–1:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 1:15 PM PT. The scene is holding a steady state, with no readily observable changes in the location of equipment or the extent of the rubble.
      1:15 PM PT

      The scene is holding a steady state, with no readily observable changes in the location of equipment or the extent of the rubble.

    2. Construction camera frame at 1:00 PM PT. The site shows minimal alteration, with equipment remaining in largely the same positions as before.
      1:00 PM PT

      The site shows minimal alteration, with equipment remaining in largely the same positions as before.

    3. Construction camera frame at 12:45 PM PT. The demolition site presents a consistent view, with no discernible alterations to the equipment or the size of the debris pile over the last fifteen minutes.
      12:45 PM PT

      The demolition site presents a consistent view, with no discernible alterations to the equipment or the size of the debris pile over the last fifteen minutes.

    4. Construction camera frame at 12:30 PM PT. The scene appears largely unchanged, with the excavator continuing its work in the center of the demolition zone.
      12:30 PM PT

      The scene appears largely unchanged, with the excavator continuing its work in the center of the demolition zone.

    5. Construction camera frame at 12:15 PM PT. The site remains remarkably stable, with no visible shifts in equipment placement or debris accumulation.
      12:15 PM PT

      The site remains remarkably stable, with no visible shifts in equipment placement or debris accumulation.

  24. Construction camera frame at 12:00 PM PT. The site continues in a quiet state, with no readily apparent changes to the equipment or debris arrangement.
    12:00 PM PT

    The site continues in a quiet state, with no readily apparent changes to the equipment or debris arrangement.

  25. Construction camera frame at 11:45 AM PT. The overall scene holds steady, with no significant movement of machinery or alteration to the debris field.
    11:45 AM PT

    The overall scene holds steady, with no significant movement of machinery or alteration to the debris field.

  26. Construction camera frame at 11:30 AM PT. The excavator’s position has shifted slightly as it continues to work on the central rubble pile.
    11:30 AM PT

    The excavator’s position has shifted slightly as it continues to work on the central rubble pile.

  27. 3 similar no-change frames10:45 AM–11:15 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 11:15 AM PT. Activity on site is minimal, as the excavator remains in the same location and the debris pile shows no noticeable growth.
      11:15 AM PT

      Activity on site is minimal, as the excavator remains in the same location and the debris pile shows no noticeable growth.

    2. Construction camera frame at 11:00 AM PT. The demolition site presents a familiar view, with equipment and debris remaining in largely the same positions.
      11:00 AM PT

      The demolition site presents a familiar view, with equipment and debris remaining in largely the same positions.

    3. Construction camera frame at 10:45 AM PT. The scene appears largely unchanged, with the excavator maintaining its position near the center of the rubble.
      10:45 AM PT

      The scene appears largely unchanged, with the excavator maintaining its position near the center of the rubble.

  28. Construction camera frame at 10:30 AM PT. The site remains steady, with no obvious shifts in equipment or the size of the debris pile.
    10:30 AM PT

    The site remains steady, with no obvious shifts in equipment or the size of the debris pile.

  29. Construction camera frame at 10:15 AM PT. A white van has entered the site via the driveway on the left, parking near the other vehicles.
    10:15 AM PT

    A white van has entered the site via the driveway on the left, parking near the other vehicles.

  30. Construction camera frame at 10:00 AM PT. The excavator continues to work at the rubble pile, though its position appears very similar to the last check-in.
    10:00 AM PT

    The excavator continues to work at the rubble pile, though its position appears very similar to the last check-in.

  31. Construction camera frame at 9:45 AM PT. The rubble pile appears slightly larger, indicating continued demolition progress in the center of the site.
    9:45 AM PT

    The rubble pile appears slightly larger, indicating continued demolition progress in the center of the site.

  32. Construction camera frame at 9:30 AM PT. A second dump truck has pulled into the staging area on the upper-left, positioning itself near the other heavy equipment.
    9:30 AM PT

    A second dump truck has pulled into the staging area on the upper-left, positioning itself near the other heavy equipment.

  33. Construction camera frame at 9:15 AM PT. The excavator in the center of the site has shifted position, now working at a different section of the rubble pile.
    9:15 AM PT

    The excavator in the center of the site has shifted position, now working at a different section of the rubble pile.

  34. Construction camera frame at 9:00 AM PT. The scene is largely unchanged, with equipment remaining in the same positions as observed previously.
    9:00 AM PT

    The scene is largely unchanged, with equipment remaining in the same positions as observed previously.

  35. Construction camera frame at 8:45 AM PT. The overall layout of the site remains consistent, though a dark-colored sedan has joined the vehicles parked along the left edge of the frame.
    8:45 AM PT

    The overall layout of the site remains consistent, though a dark-colored sedan has joined the vehicles parked along the left edge of the frame.

  36. Construction camera frame at 8:30 AM PT. A dump truck is now exiting the site via the driveway on the left, having been stationary in the upper-left staging area moments ago.
    8:30 AM PT

    A dump truck is now exiting the site via the driveway on the left, having been stationary in the upper-left staging area moments ago.

  37. Construction camera frame at 8:15 AM PT. The staging area now includes a white van parked near the upper-left corner, which was not present in the previous view.
    8:15 AM PT

    The staging area now includes a white van parked near the upper-left corner, which was not present in the previous view.

  38. Construction camera frame at 8:00 AM PT. The demolition site holds a consistent appearance, with no readily visible adjustments to machinery or the debris accumulation.
    8:00 AM PT

    The demolition site holds a consistent appearance, with no readily visible adjustments to machinery or the debris accumulation.

  39. 6 similar no-change frames6:30 AM–7:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 7:45 AM PT. The site continues to present a similar view, with no discernible alterations in the arrangement of equipment or the size of the rubble.
      7:45 AM PT

      The site continues to present a similar view, with no discernible alterations in the arrangement of equipment or the size of the rubble.

    2. Construction camera frame at 7:30 AM PT. The site appears stable, with no observable alterations to equipment or the rubble pile during the last interval.
      7:30 AM PT

      The site appears stable, with no observable alterations to equipment or the rubble pile during the last interval.

    3. Construction camera frame at 7:15 AM PT. The scene remains largely unchanged, with no noticeable shifts in equipment or debris since the last check-in.
      7:15 AM PT

      The scene remains largely unchanged, with no noticeable shifts in equipment or debris since the last check-in.

    4. Construction camera frame at 7:00 AM PT. The site shows no significant changes in equipment placement or debris accumulation over the last quarter hour.
      7:00 AM PT

      The site shows no significant changes in equipment placement or debris accumulation over the last quarter hour.

    5. Construction camera frame at 6:45 AM PT. The site displays a static scene, with all visible equipment and the debris pile remaining in the same locations.
      6:45 AM PT

      The site displays a static scene, with all visible equipment and the debris pile remaining in the same locations.

    6. Construction camera frame at 6:30 AM PT. The site remains quiet, with no apparent movement of machinery or changes to the debris field.
      6:30 AM PT

      The site remains quiet, with no apparent movement of machinery or changes to the debris field.

  40. Construction camera frame at 6:15 AM PT. The demolition site presents a remarkably consistent picture, showing no obvious adjustments in the positioning of equipment or the amount of debris.
    6:15 AM PT

    The demolition site presents a remarkably consistent picture, showing no obvious adjustments in the positioning of equipment or the amount of debris.

  41. 4 similar no-change frames5:15 AM–6:00 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:00 AM PT. The demolition site continues to show little to no discernible alteration from the previous view.
      6:00 AM PT

      The demolition site continues to show little to no discernible alteration from the previous view.

    2. Construction camera frame at 5:45 AM PT. The staging area appears quiet, with equipment remaining in the same positions as before.
      5:45 AM PT

      The staging area appears quiet, with equipment remaining in the same positions as before.

    3. Construction camera frame at 5:30 AM PT. The scene appears stable, with no noticeable shifts in equipment or debris since the last view.
      5:30 AM PT

      The scene appears stable, with no noticeable shifts in equipment or debris since the last view.

    4. Construction camera frame at 5:15 AM PT. A green excavator has shifted position in the upper-left staging area, now facing toward the rubble pile. Otherwise, the scene remains largely unchanged, with the same equipment and debris layout visible.
      5:15 AM PT

      A green excavator has shifted position in the upper-left staging area, now facing toward the rubble pile. Otherwise, the scene remains largely unchanged, with the same equipment and debris layout visible.

  42. Construction camera frame at 5:00 AM PT. The site is now illuminated with bright work lights, revealing more detail in the rubble pile and staging area. Visibility has increased substantially since the last check, though activity remains minimal at this time.
    5:00 AM PT

    The site is now illuminated with bright work lights, revealing more detail in the rubble pile and staging area. Visibility has increased substantially since the last check, though activity remains minimal at this time.

  43. 5 similar no-change frames12:00 AM–4:00 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.

← Jun 30All daysJul 2 →