606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Tuesday, June 30, 2026

Construction log

Tuesday, June 30, 2026

74 snapshots from the live camera.


AI digest

The site was largely quiet, with no clear change to the ground or equipment between the day’s first and last frames. Observations report intermittent excavator activity and a modest increase in the central debris pile, along with vehicles entering or repositioning in the staging area.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 13 similar no-change frames6:45 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:30 PM PT. No construction activity — the site is quiet.
      9:30 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 9:15 PM PT. No construction activity — the site is quiet.
      9:15 PM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 9:00 PM PT. No construction activity — the site is quiet.
      9:00 PM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 8:45 PM PT. No construction activity — the site is quiet.
      8:45 PM PT

      No construction activity — the site is quiet.

    6. Construction camera frame at 8:30 PM PT. No construction activity — the site is quiet.
      8:30 PM PT

      No construction activity — the site is quiet.

    7. Construction camera frame at 8:15 PM PT. No construction activity — the site is quiet.
      8:15 PM PT

      No construction activity — the site is quiet.

    8. Construction camera frame at 8:00 PM PT. The demolition zone appears static, with no noticeable shifts in equipment placement or rubble accumulation.
      8:00 PM PT

      The demolition zone appears static, with no noticeable shifts in equipment placement or rubble accumulation.

    9. Construction camera frame at 7:45 PM PT. The demolition site remains largely unchanged, with equipment and debris appearing in the same configurations as before.
      7:45 PM PT

      The demolition site remains largely unchanged, with equipment and debris appearing in the same configurations as before.

    10. Construction camera frame at 7:30 PM PT. No construction activity — the site is quiet.
      7:30 PM PT

      No construction activity — the site is quiet.

    11. Construction camera frame at 7:15 PM PT. No construction activity — the site is quiet.
      7:15 PM PT

      No construction activity — the site is quiet.

    12. Construction camera frame at 7:00 PM PT. No construction activity — the site is quiet.
      7:00 PM PT

      No construction activity — the site is quiet.

    13. Construction camera frame at 6:45 PM PT. The scene presents a consistent picture, showing no significant changes in equipment or the debris field over the last quarter hour.
      6:45 PM PT

      The scene presents a consistent picture, showing no significant changes in equipment or the debris field over the last quarter hour.

  3. Construction camera frame at 6:30 PM PT. The site continues in a stable condition, with no readily apparent alterations in the positions of machinery or the quantity of debris.
    6:30 PM PT

    The site continues in a stable condition, with no readily apparent alterations in the positions of machinery or the quantity of debris.

  4. Construction camera frame at 6:15 PM PT. The site looks remarkably similar to its state a few minutes ago, with no clear alterations to equipment placement or debris levels.
    6:15 PM PT

    The site looks remarkably similar to its state a few minutes ago, with no clear alterations to equipment placement or debris levels.

  5. Construction camera frame at 6:00 PM PT. The scene is holding steady, with no obvious changes to the layout of equipment or the size of the debris pile.
    6:00 PM PT

    The scene is holding steady, with no obvious changes to the layout of equipment or the size of the debris pile.

  6. 3 similar no-change frames5:15 PM–5:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 5:45 PM PT. The demolition site appears static, with no noticeable movement of machinery or increase in the debris pile.
      5:45 PM PT

      The demolition site appears static, with no noticeable movement of machinery or increase in the debris pile.

    2. Construction camera frame at 5:30 PM PT. The view remains largely unchanged, with the equipment and debris field holding their positions.
      5:30 PM PT

      The view remains largely unchanged, with the equipment and debris field holding their positions.

    3. Construction camera frame at 5:15 PM PT. The overall scene remains consistent, with no discernible shifts in equipment or debris arrangement.
      5:15 PM PT

      The overall scene remains consistent, with no discernible shifts in equipment or debris arrangement.

  7. Construction camera frame at 5:00 PM PT. The rubble pile has visibly grown, with more debris now accumulated in the center of the demolition zone.
    5:00 PM PT

    The rubble pile has visibly grown, with more debris now accumulated in the center of the demolition zone.

  8. Construction camera frame at 4:45 PM PT. The site shows minimal variation, with equipment remaining in largely the same positions as previously observed.
    4:45 PM PT

    The site shows minimal variation, with equipment remaining in largely the same positions as previously observed.

  9. Construction camera frame at 4:30 PM PT. The site presents a similar view as before, with no immediately apparent adjustments to the debris or the locations of the parked machinery.
    4:30 PM PT

    The site presents a similar view as before, with no immediately apparent adjustments to the debris or the locations of the parked machinery.

  10. 3 similar no-change frames3:45 PM–4:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:15 PM PT. The scene holds steady, with no apparent changes to the equipment or debris layout.
      4:15 PM PT

      The scene holds steady, with no apparent changes to the equipment or debris layout.

    2. Construction camera frame at 4:00 PM PT. The demolition site appears stable, with no noticeable alterations in equipment placement or debris accumulation.
      4:00 PM PT

      The demolition site appears stable, with no noticeable alterations in equipment placement or debris accumulation.

    3. Construction camera frame at 3:45 PM PT. The scene appears largely static, with no significant movement of vehicles or equipment readily visible.
      3:45 PM PT

      The scene appears largely static, with no significant movement of vehicles or equipment readily visible.

  11. Construction camera frame at 3:30 PM PT. The staging area shows a subtle rearrangement of equipment, with a loader now facing a different direction than it was a few minutes ago.
    3:30 PM PT

    The staging area shows a subtle rearrangement of equipment, with a loader now facing a different direction than it was a few minutes ago.

  12. Construction camera frame at 3:15 PM PT. The demolition site remains quiet, with no obvious shifts in the positions of machinery or the size of the debris pile.
    3:15 PM PT

    The demolition site remains quiet, with no obvious shifts in the positions of machinery or the size of the debris pile.

  13. Construction camera frame at 3:00 PM PT. The rubble pile has grown slightly, and a dump truck is now positioned where it wasn't visible before, near the upper-left staging area. The rest of the scene remains consistent.
    3:00 PM PT

    The rubble pile has grown slightly, and a dump truck is now positioned where it wasn't visible before, near the upper-left staging area. The rest of the scene remains consistent.

  14. 4 similar no-change frames2:00 PM–2:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 2:45 PM PT. The demolition site shows minimal variation from the previous view, with equipment remaining in the same positions.
      2:45 PM PT

      The demolition site shows minimal variation from the previous view, with equipment remaining in the same positions.

    2. Construction camera frame at 2:30 PM PT. The site presents a nearly identical view as before, with no discernible movement of equipment or substantial changes to the debris.
      2:30 PM PT

      The site presents a nearly identical view as before, with no discernible movement of equipment or substantial changes to the debris.

    3. Construction camera frame at 2:15 PM PT. The site’s configuration is nearly unchanged, though a small white car is now visible parked near the center of the lot.
      2:15 PM PT

      The site’s configuration is nearly unchanged, though a small white car is now visible parked near the center of the lot.

    4. Construction camera frame at 2:00 PM PT. The scene is holding steady, with no noticeable alterations to the equipment or the growing rubble pile.
      2:00 PM PT

      The scene is holding steady, with no noticeable alterations to the equipment or the growing rubble pile.

  15. Construction camera frame at 1:45 PM PT. The site appears largely as it was, with no obvious shifts in equipment or the debris accumulation.
    1:45 PM PT

    The site appears largely as it was, with no obvious shifts in equipment or the debris accumulation.

  16. Construction camera frame at 1:30 PM PT. A white van has entered the site through the driveway on the left, and is now positioned near the staging area. The overall layout of the demolition zone appears otherwise consistent.
    1:30 PM PT

    A white van has entered the site through the driveway on the left, and is now positioned near the staging area. The overall layout of the demolition zone appears otherwise consistent.

  17. Construction camera frame at 1:15 PM PT. The scene remains remarkably static, with no apparent movement of machinery or significant changes to the debris field.
    1:15 PM PT

    The scene remains remarkably static, with no apparent movement of machinery or significant changes to the debris field.

  18. Construction camera frame at 1:00 PM PT. The demolition site shows minimal difference from the last check, with all major equipment remaining in place.
    1:00 PM PT

    The demolition site shows minimal difference from the last check, with all major equipment remaining in place.

  19. 2 similar no-change frames12:30 PM–12:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 12:45 PM PT. The demolition site is quiet, with no discernible changes in equipment placement or the size of the debris pile.
      12:45 PM PT

      The demolition site is quiet, with no discernible changes in equipment placement or the size of the debris pile.

    2. Construction camera frame at 12:30 PM PT. The site presents a largely unchanged view, with equipment and the debris pile holding their previous positions.
      12:30 PM PT

      The site presents a largely unchanged view, with equipment and the debris pile holding their previous positions.

  20. Construction camera frame at 12:15 PM PT. The rubble pile has grown slightly, with the excavator continuing to feed it debris from the remaining structure.
    12:15 PM PT

    The rubble pile has grown slightly, with the excavator continuing to feed it debris from the remaining structure.

  21. Construction camera frame at 12:00 PM PT. The staging area on the upper-left shows a repositioned loader, now closer to the driveway entrance. Otherwise, the site remains consistent with the prior view.
    12:00 PM PT

    The staging area on the upper-left shows a repositioned loader, now closer to the driveway entrance. Otherwise, the site remains consistent with the prior view.

  22. 6 similar no-change frames10:30 AM–11:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 11:45 AM PT. Everything on site appears to be in the same location as before, with no observable shifts in activity or debris.
      11:45 AM PT

      Everything on site appears to be in the same location as before, with no observable shifts in activity or debris.

    2. Construction camera frame at 11:30 AM PT. The scene is holding steady, with no apparent movement of machinery or changes to the debris field.
      11:30 AM PT

      The scene is holding steady, with no apparent movement of machinery or changes to the debris field.

    3. Construction camera frame at 11:15 AM PT. The site shows minimal alteration from the previous view, with all equipment and the rubble pile remaining in the same positions.
      11:15 AM PT

      The site shows minimal alteration from the previous view, with all equipment and the rubble pile remaining in the same positions.

    4. Construction camera frame at 11:00 AM PT. The demolition site appears largely as it was, with no significant alterations to equipment placement or rubble accumulation visible.
      11:00 AM PT

      The demolition site appears largely as it was, with no significant alterations to equipment placement or rubble accumulation visible.

    5. Construction camera frame at 10:45 AM PT. A small white vehicle is now visible parked along the service road on the right side of the frame. The excavator continues to work at the rubble pile, and the rest of the site appears unchanged.
      10:45 AM PT

      A small white vehicle is now visible parked along the service road on the right side of the frame. The excavator continues to work at the rubble pile, and the rest of the site appears unchanged.

    6. Construction camera frame at 10:30 AM PT. The site presents a static view, with no noticeable changes in equipment or the demolition's progress over the last quarter hour.
      10:30 AM PT

      The site presents a static view, with no noticeable changes in equipment or the demolition's progress over the last quarter hour.

  23. Construction camera frame at 10:15 AM PT. The scene remains remarkably still, with equipment and the rubble pile maintaining their positions.
    10:15 AM PT

    The scene remains remarkably still, with equipment and the rubble pile maintaining their positions.

  24. Construction camera frame at 10:00 AM PT. A white van has entered the site through the driveway on the left and is now parked in the upper-left staging area. The rest of the scene appears consistent, with the excavator continuing work on the central rubble pile.
    10:00 AM PT

    A white van has entered the site through the driveway on the left and is now parked in the upper-left staging area. The rest of the scene appears consistent, with the excavator continuing work on the central rubble pile.

  25. Construction camera frame at 9:45 AM PT. The scene holds steady, with no apparent shifts in equipment positions or demolition progress.
    9:45 AM PT

    The scene holds steady, with no apparent shifts in equipment positions or demolition progress.

  26. Construction camera frame at 9:30 AM PT. The excavator is actively feeding material onto the growing rubble pile in the center of the site. Otherwise, the staging area and surrounding vehicles appear to be in the same positions as before.
    9:30 AM PT

    The excavator is actively feeding material onto the growing rubble pile in the center of the site. Otherwise, the staging area and surrounding vehicles appear to be in the same positions as before.

  27. Construction camera frame at 9:15 AM PT. The rubble pile has visibly grown as the excavator continues to work at the center of the site. Beyond that, the scene remains stable, with equipment and parked vehicles holding their positions.
    9:15 AM PT

    The rubble pile has visibly grown as the excavator continues to work at the center of the site. Beyond that, the scene remains stable, with equipment and parked vehicles holding their positions.

  28. Construction camera frame at 9:00 AM PT. The demolition site appears largely unchanged, though the standing water seems to have receded slightly.
    9:00 AM PT

    The demolition site appears largely unchanged, though the standing water seems to have receded slightly.

  29. Construction camera frame at 8:45 AM PT. Workers are now visible near the excavator in the center of the site. The overall layout of the demolition zone and staging area remains consistent.
    8:45 AM PT

    Workers are now visible near the excavator in the center of the site. The overall layout of the demolition zone and staging area remains consistent.

  30. Construction camera frame at 8:30 AM PT. A second white car now joins the first in the upper-left staging area, having entered through the driveway on the left.
    8:30 AM PT

    A second white car now joins the first in the upper-left staging area, having entered through the driveway on the left.

  31. Construction camera frame at 8:15 AM PT. A white car has entered the site via the driveway on the left and is now parked in the upper-left staging area.
    8:15 AM PT

    A white car has entered the site via the driveway on the left and is now parked in the upper-left staging area.

  32. 2 similar no-change frames7:45 AM–8:00 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:00 AM PT. Equipment and the debris field maintain their positions, showing no observable shift in the last fifteen minutes.
      8:00 AM PT

      Equipment and the debris field maintain their positions, showing no observable shift in the last fifteen minutes.

    2. Construction camera frame at 7:45 AM PT. The view is consistent, with no discernible shift in the arrangement of equipment or the amount of debris.
      7:45 AM PT

      The view is consistent, with no discernible shift in the arrangement of equipment or the amount of debris.

  33. Construction camera frame at 7:30 AM PT. The scene is remarkably still, with all machinery and debris appearing in the same locations as before.
    7:30 AM PT

    The scene is remarkably still, with all machinery and debris appearing in the same locations as before.

  34. 4 similar no-change frames6:30 AM–7:15 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 7:15 AM PT. The site appears largely unchanged, with equipment remaining in the same positions and no visible progress on the demolition.
      7:15 AM PT

      The site appears largely unchanged, with equipment remaining in the same positions and no visible progress on the demolition.

    2. Construction camera frame at 7:00 AM PT. The site holds steady, showing no significant changes in equipment or the debris accumulation.
      7:00 AM PT

      The site holds steady, showing no significant changes in equipment or the debris accumulation.

    3. Construction camera frame at 6:45 AM PT. The site presents a consistent picture, with no apparent alterations in equipment placement or the size of the rubble pile.
      6:45 AM PT

      The site presents a consistent picture, with no apparent alterations in equipment placement or the size of the rubble pile.

    4. Construction camera frame at 6:30 AM PT. The scene remains stable, with no observable alterations to the positioning of equipment or the extent of the rubble.
      6:30 AM PT

      The scene remains stable, with no observable alterations to the positioning of equipment or the extent of the rubble.

  35. Construction camera frame at 6:15 AM PT. The demolition zone shows very little alteration from the previous view, with the machinery and debris remaining in similar positions.
    6:15 AM PT

    The demolition zone shows very little alteration from the previous view, with the machinery and debris remaining in similar positions.

  36. Construction camera frame at 6:00 AM PT. The staging area on the upper-left shows a white van has entered and is now parked near the equipment. Apart from that, the demolition site maintains a consistent appearance.
    6:00 AM PT

    The staging area on the upper-left shows a white van has entered and is now parked near the equipment. Apart from that, the demolition site maintains a consistent appearance.

  37. 3 similar no-change frames5:15 AM–5:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 5:45 AM PT. The demolition site appears quiet, with no apparent movement of equipment or significant changes to the debris field.
      5:45 AM PT

      The demolition site appears quiet, with no apparent movement of equipment or significant changes to the debris field.

    2. Construction camera frame at 5:30 AM PT. The scene appears remarkably static, with no noticeable shifts in equipment or debris since the last view.
      5:30 AM PT

      The scene appears remarkably static, with no noticeable shifts in equipment or debris since the last view.

    3. Construction camera frame at 5:15 AM PT. The excavator in the center of the rubble pile appears to have shifted slightly, now facing a different direction. Otherwise, the scene remains largely unchanged, with equipment positioned as before.
      5:15 AM PT

      The excavator in the center of the rubble pile appears to have shifted slightly, now facing a different direction. Otherwise, the scene remains largely unchanged, with equipment positioned as before.

  38. Construction camera frame at 5:00 AM PT. The site is now bathed in brighter light, revealing more detail in the rubble pile and staging area. A lone vehicle is visible on the street to the left, having entered the frame since the last check.
    5:00 AM PT

    The site is now bathed in brighter light, revealing more detail in the rubble pile and staging area. A lone vehicle is visible on the street to the left, having entered the frame since the last check.

  39. 5 similar no-change frames12:00 AM–4:00 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.

← Jun 29All daysJul 1 →