Skip to content
606Onni 606 · Bellevue
  • Live
  • Progress
  • Project
  • History
  • Search
606

606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Saturday, August 8, 2026

Construction log

Saturday, August 8, 2026

70 snapshots from the live camera.


AI digest

The site was largely quiet, with excavators and other tracked equipment staying in roughly the same positions; a white pickup entered, and several smaller machines shifted slightly during the day. Compared with August 1, the broad central cut and surrounding graded areas look much the same, with no substantial ground change visible.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 7 similar no-change frames7:45 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:00 PM PT. No construction activity — the site is quiet.
      9:00 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 8:45 PM PT. Equipment across the site remains in the same positions, with only subtle shifts in the evening light.
      8:45 PM PT

      Equipment across the site remains in the same positions, with only subtle shifts in the evening light.

    4. Construction camera frame at 8:30 PM PT. The view remains consistent, with no noticeable alterations to the positioning of machinery or stockpiled materials.
      8:30 PM PT

      The view remains consistent, with no noticeable alterations to the positioning of machinery or stockpiled materials.

    5. Construction camera frame at 8:15 PM PT. The scene is holding steady, with no apparent movement of equipment or materials in the last quarter hour.
      8:15 PM PT

      The scene is holding steady, with no apparent movement of equipment or materials in the last quarter hour.

    6. Construction camera frame at 8:00 PM PT. The site appears largely as it did fifteen minutes ago, with no discernible shifts in equipment or material placement.
      8:00 PM PT

      The site appears largely as it did fifteen minutes ago, with no discernible shifts in equipment or material placement.

    7. Construction camera frame at 7:45 PM PT. The scene remains remarkably still, with the positions of equipment and materials appearing unchanged over the last fifteen minutes.
      7:45 PM PT

      The scene remains remarkably still, with the positions of equipment and materials appearing unchanged over the last fifteen minutes.

  3. Construction camera frame at 7:30 PM PT. The arrangement of equipment remains consistent, though the shadows have shifted slightly with the changing light.
    7:30 PM PT

    The arrangement of equipment remains consistent, though the shadows have shifted slightly with the changing light.

  4. 11 similar no-change frames4:45 PM–7:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 7:15 PM PT. The site presents a largely unchanged view, with equipment remaining in consistent locations across the graded area.
      7:15 PM PT

      The site presents a largely unchanged view, with equipment remaining in consistent locations across the graded area.

    2. Construction camera frame at 7:00 PM PT. The equipment layout is largely static, though a small cluster of white material has appeared near the center of the site.
      7:00 PM PT

      The equipment layout is largely static, though a small cluster of white material has appeared near the center of the site.

    3. Construction camera frame at 6:45 PM PT. The scene shows a consistent arrangement of machinery and materials, with no noticeable changes in equipment positioning over the last fifteen minutes.
      6:45 PM PT

      The scene shows a consistent arrangement of machinery and materials, with no noticeable changes in equipment positioning over the last fifteen minutes.

    4. Construction camera frame at 6:30 PM PT. The equipment across the site maintains its positions, with no apparent movement detected in the last quarter hour.
      6:30 PM PT

      The equipment across the site maintains its positions, with no apparent movement detected in the last quarter hour.

    5. Construction camera frame at 6:15 PM PT. The site appears quiet, with equipment remaining in largely the same positions as fifteen minutes ago.
      6:15 PM PT

      The site appears quiet, with equipment remaining in largely the same positions as fifteen minutes ago.

    6. Construction camera frame at 6:00 PM PT. A small yellow machine has moved position within the central graded area of the site. Otherwise, the equipment and materials remain in the same locations as observed previously.
      6:00 PM PT

      A small yellow machine has moved position within the central graded area of the site. Otherwise, the equipment and materials remain in the same locations as observed previously.

    7. Construction camera frame at 5:45 PM PT. The arrangement of equipment on site appears stable, showing no shifts in position during the last fifteen minutes.
      5:45 PM PT

      The arrangement of equipment on site appears stable, showing no shifts in position during the last fifteen minutes.

    8. Construction camera frame at 5:30 PM PT. The scene remains remarkably unchanged, with all visible machinery holding its previous positions.
      5:30 PM PT

      The scene remains remarkably unchanged, with all visible machinery holding its previous positions.

    9. Construction camera frame at 5:15 PM PT. The site presents a largely static view, with the machinery holding its positions from the previous check.
      5:15 PM PT

      The site presents a largely static view, with the machinery holding its positions from the previous check.

    10. Construction camera frame at 5:00 PM PT. The layout of machinery across the site remains consistent, with no discernible changes in placement over the last fifteen minutes.
      5:00 PM PT

      The layout of machinery across the site remains consistent, with no discernible changes in placement over the last fifteen minutes.

    11. Construction camera frame at 4:45 PM PT. Equipment positions across the site appear stable, with no noticeable alterations in the last fifteen minutes.
      4:45 PM PT

      Equipment positions across the site appear stable, with no noticeable alterations in the last fifteen minutes.

  5. Construction camera frame at 4:30 PM PT. The site’s machinery remains in largely the same configuration, with no obvious repositioning of equipment visible in the last quarter hour.
    4:30 PM PT

    The site’s machinery remains in largely the same configuration, with no obvious repositioning of equipment visible in the last quarter hour.

  6. 4 similar no-change frames3:30 PM–4:15 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:15 PM PT. The site’s appearance is nearly identical, with the machinery remaining in the same locations as before.
      4:15 PM PT

      The site’s appearance is nearly identical, with the machinery remaining in the same locations as before.

    2. Construction camera frame at 4:00 PM PT. The arrangement of equipment on site appears consistent between these views, showing no significant shifts in position.
      4:00 PM PT

      The arrangement of equipment on site appears consistent between these views, showing no significant shifts in position.

    3. Construction camera frame at 3:45 PM PT. The scene appears almost unchanged, with equipment maintaining its previous positions across the site.
      3:45 PM PT

      The scene appears almost unchanged, with equipment maintaining its previous positions across the site.

    4. Construction camera frame at 3:30 PM PT. The site remains largely static, with no immediately apparent movement of equipment or materials in the last fifteen minutes.
      3:30 PM PT

      The site remains largely static, with no immediately apparent movement of equipment or materials in the last fifteen minutes.

  7. Construction camera frame at 3:15 PM PT. The overall layout of the site is consistent, though a small loader near the lower-right has turned to face a slightly different direction.
    3:15 PM PT

    The overall layout of the site is consistent, though a small loader near the lower-right has turned to face a slightly different direction.

  8. Construction camera frame at 3:00 PM PT. The site presents a stable picture, with the arrangement of machines showing no appreciable difference in these two views.
    3:00 PM PT

    The site presents a stable picture, with the arrangement of machines showing no appreciable difference in these two views.

  9. 2 similar no-change frames2:30 PM–2:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 2:45 PM PT. The scene is remarkably similar, with the positions of the heavy equipment appearing to be almost unchanged.
      2:45 PM PT

      The scene is remarkably similar, with the positions of the heavy equipment appearing to be almost unchanged.

    2. Construction camera frame at 2:30 PM PT. Equipment locations are largely unchanged, though one of the smaller machines near the site's eastern edge has rotated slightly.
      2:30 PM PT

      Equipment locations are largely unchanged, though one of the smaller machines near the site's eastern edge has rotated slightly.

  10. Construction camera frame at 2:15 PM PT. The site's appearance is nearly identical, though a small piece of equipment near the lower-right corner seems to have shifted position slightly.
    2:15 PM PT

    The site's appearance is nearly identical, though a small piece of equipment near the lower-right corner seems to have shifted position slightly.

  11. Construction camera frame at 2:00 PM PT. The arrangement of machinery across the site holds, with only minor shifts in position that are difficult to pinpoint.
    2:00 PM PT

    The arrangement of machinery across the site holds, with only minor shifts in position that are difficult to pinpoint.

  12. Construction camera frame at 1:45 PM PT. The scene remains stable, with the positions of the earthmoving equipment appearing consistent between these views.
    1:45 PM PT

    The scene remains stable, with the positions of the earthmoving equipment appearing consistent between these views.

  13. Construction camera frame at 1:30 PM PT. The equipment across the site appears to be holding steady, with no significant alterations visible in this latest view.
    1:30 PM PT

    The equipment across the site appears to be holding steady, with no significant alterations visible in this latest view.

  14. Construction camera frame at 1:15 PM PT. The overall scene presents a consistent picture, with equipment largely holding its positions from the earlier view.
    1:15 PM PT

    The overall scene presents a consistent picture, with equipment largely holding its positions from the earlier view.

  15. Construction camera frame at 1:00 PM PT. The equipment layout is remarkably similar to the previous view, with no obvious repositioning of machines or materials.
    1:00 PM PT

    The equipment layout is remarkably similar to the previous view, with no obvious repositioning of machines or materials.

  16. Construction camera frame at 12:45 PM PT. The scene is largely unchanged, though one piece of yellow equipment near the bottom of the frame has rotated slightly.
    12:45 PM PT

    The scene is largely unchanged, though one piece of yellow equipment near the bottom of the frame has rotated slightly.

  17. Construction camera frame at 12:30 PM PT. A cluster of yellow machinery has shifted position in the lower-right quadrant of the site. Otherwise, the broader scene remains largely as it was fifteen minutes ago.
    12:30 PM PT

    A cluster of yellow machinery has shifted position in the lower-right quadrant of the site. Otherwise, the broader scene remains largely as it was fifteen minutes ago.

  18. Construction camera frame at 12:15 PM PT. The arrangement of equipment across the site remains consistent between these views.
    12:15 PM PT

    The arrangement of equipment across the site remains consistent between these views.

  19. 3 similar no-change frames11:30 AM–12:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 12:00 PM PT. The site remains in a stable state, with no noticeable shifts in equipment placement over the last quarter of an hour.
      12:00 PM PT

      The site remains in a stable state, with no noticeable shifts in equipment placement over the last quarter of an hour.

    2. Construction camera frame at 11:45 AM PT. The site appears static, with all visible equipment and materials maintaining the same positions as in the previous view.
      11:45 AM PT

      The site appears static, with all visible equipment and materials maintaining the same positions as in the previous view.

    3. Construction camera frame at 11:30 AM PT. A small dark-colored vehicle has moved from the lower-right portion of the site toward the center. Otherwise, the arrangement of the larger equipment appears unchanged from the previous view.
      11:30 AM PT

      A small dark-colored vehicle has moved from the lower-right portion of the site toward the center. Otherwise, the arrangement of the larger equipment appears unchanged from the previous view.

  20. Construction camera frame at 11:15 AM PT. Activity on the right side of the frame shows a piece of machinery moving along the service road. Otherwise, the arrangement of equipment and materials across the site appears to be holding steady.
    11:15 AM PT

    Activity on the right side of the frame shows a piece of machinery moving along the service road. Otherwise, the arrangement of equipment and materials across the site appears to be holding steady.

  21. Construction camera frame at 11:00 AM PT. The site presents a largely unchanged view, with equipment remaining in the same positions as fifteen minutes ago.
    11:00 AM PT

    The site presents a largely unchanged view, with equipment remaining in the same positions as fifteen minutes ago.

  22. Construction camera frame at 10:45 AM PT. The tracked equipment in the lower right corner has shifted slightly, now facing a different direction than it was previously. Otherwise, the site’s overall appearance is consistent with the last view.
    10:45 AM PT

    The tracked equipment in the lower right corner has shifted slightly, now facing a different direction than it was previously. Otherwise, the site’s overall appearance is consistent with the last view.

  23. Construction camera frame at 10:30 AM PT. The layout of machinery across the site remains consistent, with no visible repositioning of equipment during the last fifteen minutes.
    10:30 AM PT

    The layout of machinery across the site remains consistent, with no visible repositioning of equipment during the last fifteen minutes.

  24. Construction camera frame at 10:15 AM PT. A white pickup truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment and materials on the site maintain their previous positions.
    10:15 AM PT

    A white pickup truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment and materials on the site maintain their previous positions.

  25. Construction camera frame at 10:00 AM PT. The scene remains remarkably static, with no noticeable shifts in equipment locations or activity over the last fifteen minutes.
    10:00 AM PT

    The scene remains remarkably static, with no noticeable shifts in equipment locations or activity over the last fifteen minutes.

  26. Construction camera frame at 9:45 AM PT. The site continues to show minimal alteration, with the positioning of the tracked equipment appearing largely the same as before.
    9:45 AM PT

    The site continues to show minimal alteration, with the positioning of the tracked equipment appearing largely the same as before.

  27. Construction camera frame at 9:30 AM PT. The arrangement of equipment on the site appears stable, showing no significant repositioning in the last quarter hour.
    9:30 AM PT

    The arrangement of equipment on the site appears stable, showing no significant repositioning in the last quarter hour.

  28. 2 similar no-change frames9:00 AM–9:15 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 9:15 AM PT. The scene is largely unchanged, with equipment remaining in the same positions as the previous view.
      9:15 AM PT

      The scene is largely unchanged, with equipment remaining in the same positions as the previous view.

    2. Construction camera frame at 9:00 AM PT. The site presents a nearly identical picture, with no apparent movement of equipment or materials in the last fifteen minutes.
      9:00 AM PT

      The site presents a nearly identical picture, with no apparent movement of equipment or materials in the last fifteen minutes.

  29. Construction camera frame at 8:45 AM PT. The site's layout holds steady, with the arrangement of machinery appearing virtually identical to the previous view.
    8:45 AM PT

    The site's layout holds steady, with the arrangement of machinery appearing virtually identical to the previous view.

  30. Construction camera frame at 8:30 AM PT. Equipment positions throughout the site stay consistent between these views.
    8:30 AM PT

    Equipment positions throughout the site stay consistent between these views.

  31. 4 similar no-change frames7:30 AM–8:15 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:15 AM PT. The scene appears static, with the arrangement of heavy equipment remaining consistent over the last fifteen minutes.
      8:15 AM PT

      The scene appears static, with the arrangement of heavy equipment remaining consistent over the last fifteen minutes.

    2. Construction camera frame at 8:00 AM PT. The overall composition of the site remains constant, with no noticeable shifts in equipment positions.
      8:00 AM PT

      The overall composition of the site remains constant, with no noticeable shifts in equipment positions.

    3. Construction camera frame at 7:45 AM PT. The site remains stable, with no discernible changes in the placement of equipment or materials over the last quarter hour.
      7:45 AM PT

      The site remains stable, with no discernible changes in the placement of equipment or materials over the last quarter hour.

    4. Construction camera frame at 7:30 AM PT. The site’s appearance is largely unchanged, though one of the smaller machines near the bottom-right corner seems to have rotated slightly.
      7:30 AM PT

      The site’s appearance is largely unchanged, though one of the smaller machines near the bottom-right corner seems to have rotated slightly.

  32. Construction camera frame at 7:15 AM PT. The scene presents a largely consistent picture, with equipment maintaining its positions across the site.
    7:15 AM PT

    The scene presents a largely consistent picture, with equipment maintaining its positions across the site.

  33. Construction camera frame at 7:00 AM PT. A small, dark-colored machine has shifted position near the right edge of the frame. Otherwise, the layout of equipment and the overall scene appear remarkably similar to the last update.
    7:00 AM PT

    A small, dark-colored machine has shifted position near the right edge of the frame. Otherwise, the layout of equipment and the overall scene appear remarkably similar to the last update.

  34. Construction camera frame at 6:45 AM PT. The arrangement of machinery across the site holds steady, with no apparent movement or new arrivals in the past fifteen minutes.
    6:45 AM PT

    The arrangement of machinery across the site holds steady, with no apparent movement or new arrivals in the past fifteen minutes.

  35. 10 similar no-change frames12:00 AM–6:30 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:30 AM PT. The scene shows minimal alteration from the previous view, with equipment remaining in the same general locations.
      6:30 AM PT

      The scene shows minimal alteration from the previous view, with equipment remaining in the same general locations.

    2. Construction camera frame at 6:15 AM PT. The site appears quiet, with no noticeable shifts in equipment positions or activity over the last fifteen minutes.
      6:15 AM PT

      The site appears quiet, with no noticeable shifts in equipment positions or activity over the last fifteen minutes.

    3. Construction camera frame at 6:00 AM PT. The equipment arrangement appears mostly unchanged, though the area near the center of the site now looks slightly more disturbed. Otherwise, the view remains consistent with the previous check-in.
      6:00 AM PT

      The equipment arrangement appears mostly unchanged, though the area near the center of the site now looks slightly more disturbed. Otherwise, the view remains consistent with the previous check-in.

    4. Construction camera frame at 5:45 AM PT. Daylight has revealed several pieces of heavy equipment now visible across the site, including excavators and a tracked dozer. The scene remains largely static, with the machines positioned as they were fifteen minutes ago.
      5:45 AM PT

      Daylight has revealed several pieces of heavy equipment now visible across the site, including excavators and a tracked dozer. The scene remains largely static, with the machines positioned as they were fifteen minutes ago.

    5. Construction camera frame at 5:00 AM PT. No construction activity — the site is quiet.
      5:00 AM PT

      No construction activity — the site is quiet.

    6. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    7. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    8. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    9. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    10. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.

← Aug 7All daysAug 9 →