Skip to content
606Onni 606 · Bellevue
  • Live
  • Progress
  • Project
  • History
  • Search
606

606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Monday, August 10, 2026

Construction log

Monday, August 10, 2026

70 snapshots from the live camera.


AI digest

Activity focused on the lower-center graded area, where a darker patch of disturbed earth expanded and shifted shape, with yellow excavators rotating and repositioning within that area. Several vehicles, including a dump truck, a dark-colored truck, and white pickup trucks, entered and moved around the site throughout the day.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 5 similar no-change frames8:15 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:00 PM PT. No construction activity — the site is quiet.
      9:00 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 8:45 PM PT. The site remains quiet, with the same arrangement of equipment visible in both views.
      8:45 PM PT

      The site remains quiet, with the same arrangement of equipment visible in both views.

    4. Construction camera frame at 8:30 PM PT. The site appears largely unchanged during this interval, though lighting conditions have shifted slightly.
      8:30 PM PT

      The site appears largely unchanged during this interval, though lighting conditions have shifted slightly.

    5. Construction camera frame at 8:15 PM PT. The equipment across the site holds its positions, with no discernible movement in this interval.
      8:15 PM PT

      The equipment across the site holds its positions, with no discernible movement in this interval.

  3. Construction camera frame at 8:00 PM PT. A compact yellow machine has shifted position from the center to the lower-right portion of the site.
    8:00 PM PT

    A compact yellow machine has shifted position from the center to the lower-right portion of the site.

  4. Construction camera frame at 7:45 PM PT. The scene presents a static view, with equipment remaining in essentially the same locations as before.
    7:45 PM PT

    The scene presents a static view, with equipment remaining in essentially the same locations as before.

  5. Construction camera frame at 7:30 PM PT. The arrangement of machinery looks remarkably similar, with only slight changes in shadow patterns across the site.
    7:30 PM PT

    The arrangement of machinery looks remarkably similar, with only slight changes in shadow patterns across the site.

  6. Construction camera frame at 7:15 PM PT. The small red container has moved slightly toward the lower edge of the site since the last view.
    7:15 PM PT

    The small red container has moved slightly toward the lower edge of the site since the last view.

  7. Construction camera frame at 7:00 PM PT. The site remains largely as it was, though the shadows have lengthened a bit across the graded ground.
    7:00 PM PT

    The site remains largely as it was, though the shadows have lengthened a bit across the graded ground.

  8. Construction camera frame at 6:45 PM PT. The layout of equipment across the site appears consistent, with no obvious shifts in position during the interval.
    6:45 PM PT

    The layout of equipment across the site appears consistent, with no obvious shifts in position during the interval.

  9. Construction camera frame at 6:30 PM PT. The position of one of the yellow machines near the center of the site has subtly altered between the frames.
    6:30 PM PT

    The position of one of the yellow machines near the center of the site has subtly altered between the frames.

  10. Construction camera frame at 6:15 PM PT. The equipment arrangement is holding steady, though a piece of machinery has shifted position in the lower right corner of the site.
    6:15 PM PT

    The equipment arrangement is holding steady, though a piece of machinery has shifted position in the lower right corner of the site.

  11. Construction camera frame at 6:00 PM PT. The machinery layout is stable, though a dark-colored vehicle has moved onto the service road on the right.
    6:00 PM PT

    The machinery layout is stable, though a dark-colored vehicle has moved onto the service road on the right.

  12. Construction camera frame at 5:45 PM PT. A small red container now sits near the center of the site, having appeared between the two frames.
    5:45 PM PT

    A small red container now sits near the center of the site, having appeared between the two frames.

  13. Construction camera frame at 5:30 PM PT. The scene is largely unchanged, though the shadows have shifted slightly across the graded area.
    5:30 PM PT

    The scene is largely unchanged, though the shadows have shifted slightly across the graded area.

  14. Construction camera frame at 5:15 PM PT. A small white vehicle is now visible traveling along the service road on the right side of the frame.
    5:15 PM PT

    A small white vehicle is now visible traveling along the service road on the right side of the frame.

  15. Construction camera frame at 5:00 PM PT. The shadows have lengthened across the site, but equipment appears to remain in the same positions.
    5:00 PM PT

    The shadows have lengthened across the site, but equipment appears to remain in the same positions.

  16. Construction camera frame at 4:45 PM PT. The scene remains quite still, with no obvious shifts in equipment positions or material stockpiles.
    4:45 PM PT

    The scene remains quite still, with no obvious shifts in equipment positions or material stockpiles.

  17. Construction camera frame at 4:30 PM PT. The arrangement of machinery on site is holding, though a red piece of equipment has appeared near the driveway on the left.
    4:30 PM PT

    The arrangement of machinery on site is holding, though a red piece of equipment has appeared near the driveway on the left.

  18. Construction camera frame at 4:15 PM PT. The site presents a largely static view, though one of the excavators near the center has shifted its position slightly.
    4:15 PM PT

    The site presents a largely static view, though one of the excavators near the center has shifted its position slightly.

  19. Construction camera frame at 4:00 PM PT. The overall layout of the site remains consistent, but a white vehicle has entered the driveway on the left side of the frame.
    4:00 PM PT

    The overall layout of the site remains consistent, but a white vehicle has entered the driveway on the left side of the frame.

  20. Construction camera frame at 3:45 PM PT. The scene appears remarkably similar, with equipment holding its positions across the site.
    3:45 PM PT

    The scene appears remarkably similar, with equipment holding its positions across the site.

  21. Construction camera frame at 3:30 PM PT. The site's equipment layout is holding steady, with only minor shifts in the arrangement of material near the center.
    3:30 PM PT

    The site's equipment layout is holding steady, with only minor shifts in the arrangement of material near the center.

  22. Construction camera frame at 3:15 PM PT. An orange-and-yellow machine has moved from the upper-right to the lower-right portion of the site. Otherwise, the positions of equipment and the layout of disturbed ground appear largely unchanged between these views.
    3:15 PM PT

    An orange-and-yellow machine has moved from the upper-right to the lower-right portion of the site. Otherwise, the positions of equipment and the layout of disturbed ground appear largely unchanged between these views.

  23. Construction camera frame at 3:00 PM PT. A yellow excavator near the curved lower edge has rotated, now facing a slightly different direction than it was moments ago. The overall arrangement of equipment across the site appears otherwise consistent.
    3:00 PM PT

    A yellow excavator near the curved lower edge has rotated, now facing a slightly different direction than it was moments ago. The overall arrangement of equipment across the site appears otherwise consistent.

  24. Construction camera frame at 2:45 PM PT. The arrangement of machines across the site remains stable, though the disturbed earth along the curved lower edge appears to have advanced a bit further.
    2:45 PM PT

    The arrangement of machines across the site remains stable, though the disturbed earth along the curved lower edge appears to have advanced a bit further.

  25. Construction camera frame at 2:30 PM PT. The equipment across the site appears to be in roughly the same locations, although the pattern of lighter-colored material near the lower-right corner has subtly shifted.
    2:30 PM PT

    The equipment across the site appears to be in roughly the same locations, although the pattern of lighter-colored material near the lower-right corner has subtly shifted.

  26. Construction camera frame at 2:15 PM PT. The area of disturbed earth along the curved lower edge has grown further, and a yellow excavator in that region is now positioned differently than before.
    2:15 PM PT

    The area of disturbed earth along the curved lower edge has grown further, and a yellow excavator in that region is now positioned differently than before.

  27. Construction camera frame at 2:00 PM PT. The darker area of disturbed earth along the curved bottom edge continues to spread, and a yellow excavator near that section is now facing a different direction.
    2:00 PM PT

    The darker area of disturbed earth along the curved bottom edge continues to spread, and a yellow excavator near that section is now facing a different direction.

  28. Construction camera frame at 1:45 PM PT. The pattern of disturbed earth along the curved edge at the bottom of the frame has expanded slightly, and one of the excavators near that area appears to have shifted its orientation.
    1:45 PM PT

    The pattern of disturbed earth along the curved edge at the bottom of the frame has expanded slightly, and one of the excavators near that area appears to have shifted its orientation.

  29. Construction camera frame at 1:30 PM PT. A small, red vehicle has moved from the service road on the right to a position near the center of the site. The arrangement of the larger tracked equipment across the graded area remains largely unchanged.
    1:30 PM PT

    A small, red vehicle has moved from the service road on the right to a position near the center of the site. The arrangement of the larger tracked equipment across the graded area remains largely unchanged.

  30. Construction camera frame at 1:15 PM PT. The machines across the graded area hold their positions, though a darker patch of disturbed earth has grown along the curve at the bottom of the frame.
    1:15 PM PT

    The machines across the graded area hold their positions, though a darker patch of disturbed earth has grown along the curve at the bottom of the frame.

  31. Construction camera frame at 1:00 PM PT. The arrangement of the heavy equipment remains largely static, though one of the excavators closer to the center of the frame has shifted its position slightly.
    1:00 PM PT

    The arrangement of the heavy equipment remains largely static, though one of the excavators closer to the center of the frame has shifted its position slightly.

  32. Construction camera frame at 12:45 PM PT. The site shows minimal shifts, with the positions of the tracked machines remaining largely consistent across the graded area.
    12:45 PM PT

    The site shows minimal shifts, with the positions of the tracked machines remaining largely consistent across the graded area.

  33. Construction camera frame at 12:30 PM PT. A white truck has entered the site through the driveway on the left and is now positioned near the red containers. Otherwise, the arrangement of equipment across the graded area appears to be stable.
    12:30 PM PT

    A white truck has entered the site through the driveway on the left and is now positioned near the red containers. Otherwise, the arrangement of equipment across the graded area appears to be stable.

  34. Construction camera frame at 12:15 PM PT. The site appears much as it did moments ago, with the machines largely holding their positions across the graded area.
    12:15 PM PT

    The site appears much as it did moments ago, with the machines largely holding their positions across the graded area.

  35. Construction camera frame at 12:00 PM PT. One of the excavators near the bottom of the frame has rotated, now facing a different direction than it was previously. The rest of the site and its equipment appear to be in the same arrangement.
    12:00 PM PT

    One of the excavators near the bottom of the frame has rotated, now facing a different direction than it was previously. The rest of the site and its equipment appear to be in the same arrangement.

  36. Construction camera frame at 11:45 AM PT. The equipment arrangement appears consistent, though a small yellow machine has moved further into the central graded area.
    11:45 AM PT

    The equipment arrangement appears consistent, though a small yellow machine has moved further into the central graded area.

  37. Construction camera frame at 11:30 AM PT. The scene presents a largely unchanged view, with the machinery maintaining its previous positions across the site.
    11:30 AM PT

    The scene presents a largely unchanged view, with the machinery maintaining its previous positions across the site.

  38. Construction camera frame at 11:15 AM PT. The overall scene remains very similar, with no substantial repositioning of the heavy machinery or alterations to the graded earth.
    11:15 AM PT

    The overall scene remains very similar, with no substantial repositioning of the heavy machinery or alterations to the graded earth.

  39. Construction camera frame at 11:00 AM PT. The position of one of the yellow machines near the center of the site appears to have shifted slightly to the south. Otherwise, the equipment and the general layout of the graded area are consistent between the views.
    11:00 AM PT

    The position of one of the yellow machines near the center of the site appears to have shifted slightly to the south. Otherwise, the equipment and the general layout of the graded area are consistent between the views.

  40. Construction camera frame at 10:45 AM PT. The arrangement of equipment across the site shows no significant alterations from the previous view.
    10:45 AM PT

    The arrangement of equipment across the site shows no significant alterations from the previous view.

  41. Construction camera frame at 10:30 AM PT. A dark-colored truck is now positioned near the center of the site, having moved from the right side during the interval. The rest of the equipment and the overall scene remain largely as they were.
    10:30 AM PT

    A dark-colored truck is now positioned near the center of the site, having moved from the right side during the interval. The rest of the equipment and the overall scene remain largely as they were.

  42. Construction camera frame at 10:15 AM PT. The scene appears remarkably static, with the machinery and soil conditions holding their positions from the last view.
    10:15 AM PT

    The scene appears remarkably static, with the machinery and soil conditions holding their positions from the last view.

  43. Construction camera frame at 10:00 AM PT. A white pickup truck has entered the site from the driveway on the left, and another vehicle is now visible near the equipment at the far right. The rest of the scene, including the positions of the excavators and the disturbed soil, appears largely the same.
    10:00 AM PT

    A white pickup truck has entered the site from the driveway on the left, and another vehicle is now visible near the equipment at the far right. The rest of the scene, including the positions of the excavators and the disturbed soil, appears largely the same.

  44. 2 similar no-change frames9:30 AM–9:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 9:45 AM PT. The site maintains a consistent appearance, with no noticeable shifts in equipment positions or activity levels.
      9:45 AM PT

      The site maintains a consistent appearance, with no noticeable shifts in equipment positions or activity levels.

    2. Construction camera frame at 9:30 AM PT. A smaller yellow machine has moved from the center of the site toward the lower edge, near the darker disturbed soil. Otherwise, the arrangement of the larger equipment and the overall scene appear unchanged.
      9:30 AM PT

      A smaller yellow machine has moved from the center of the site toward the lower edge, near the darker disturbed soil. Otherwise, the arrangement of the larger equipment and the overall scene appear unchanged.

  45. Construction camera frame at 9:15 AM PT. The scene remains quite still, with the tracked equipment and the layout of the site appearing virtually identical to the previous view.
    9:15 AM PT

    The scene remains quite still, with the tracked equipment and the layout of the site appearing virtually identical to the previous view.

  46. Construction camera frame at 9:00 AM PT. A yellow piece of equipment has shifted position within the central, darker area of the site. The rest of the scene, including the stationary excavators and the overall layout, appears consistent.
    9:00 AM PT

    A yellow piece of equipment has shifted position within the central, darker area of the site. The rest of the scene, including the stationary excavators and the overall layout, appears consistent.

  47. Construction camera frame at 8:45 AM PT. The arrangement of equipment across the site remains stable, with only minor variations in the darker, disturbed soil area.
    8:45 AM PT

    The arrangement of equipment across the site remains stable, with only minor variations in the darker, disturbed soil area.

  48. Construction camera frame at 8:30 AM PT. The darker area in the lower center of the site appears to have slightly shifted its shape, though the overall scene remains very similar.
    8:30 AM PT

    The darker area in the lower center of the site appears to have slightly shifted its shape, though the overall scene remains very similar.

  49. Construction camera frame at 8:15 AM PT. A large dump truck is now traveling along the service road on the right side of the site, having entered from off-frame. The rest of the scene appears to be holding its current configuration.
    8:15 AM PT

    A large dump truck is now traveling along the service road on the right side of the site, having entered from off-frame. The rest of the scene appears to be holding its current configuration.

  50. Construction camera frame at 8:00 AM PT. A small, dark-colored vehicle has entered the site from the driveway on the left, and is now positioned near the center of the graded area. The larger scene remains largely consistent, with the tracked equipment holding its positions.
    8:00 AM PT

    A small, dark-colored vehicle has entered the site from the driveway on the left, and is now positioned near the center of the graded area. The larger scene remains largely consistent, with the tracked equipment holding its positions.

  51. Construction camera frame at 7:45 AM PT. A small yellow machine has moved from the lower-center portion of the site to the far right edge, near the service road. Otherwise, the equipment arrangement and the darker, worked area remain largely unchanged.
    7:45 AM PT

    A small yellow machine has moved from the lower-center portion of the site to the far right edge, near the service road. Otherwise, the equipment arrangement and the darker, worked area remain largely unchanged.

  52. Construction camera frame at 7:30 AM PT. The darker patch in the lower center of the site has expanded slightly, indicating some continued movement of material in that area. The rest of the scene, including the positions of the various pieces of equipment, remains as it was.
    7:30 AM PT

    The darker patch in the lower center of the site has expanded slightly, indicating some continued movement of material in that area. The rest of the scene, including the positions of the various pieces of equipment, remains as it was.

  53. Construction camera frame at 7:15 AM PT. A darker patch now covers a portion of the graded area in the lower center of the frame, suggesting recent activity. The overall arrangement of equipment and vehicles remains consistent with the previous view.
    7:15 AM PT

    A darker patch now covers a portion of the graded area in the lower center of the frame, suggesting recent activity. The overall arrangement of equipment and vehicles remains consistent with the previous view.

  54. Construction camera frame at 7:00 AM PT. The scene presents a stable view, with the equipment and graded surfaces holding their positions.
    7:00 AM PT

    The scene presents a stable view, with the equipment and graded surfaces holding their positions.

  55. 11 similar no-change frames12:00 AM–6:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:45 AM PT. The arrangement of machinery across the site continues to hold steady, with no visible shifts in position over the last fifteen minutes.
      6:45 AM PT

      The arrangement of machinery across the site continues to hold steady, with no visible shifts in position over the last fifteen minutes.

    2. Construction camera frame at 6:30 AM PT. The graded area appears much the same as before, with equipment remaining in largely the same positions.
      6:30 AM PT

      The graded area appears much the same as before, with equipment remaining in largely the same positions.

    3. Construction camera frame at 6:15 AM PT. The scene remains remarkably consistent, with the arrangement of equipment and graded land appearing static.
      6:15 AM PT

      The scene remains remarkably consistent, with the arrangement of equipment and graded land appearing static.

    4. Construction camera frame at 6:00 AM PT. A small piece of heavy equipment has shifted position in the center of the site, moving slightly to the right. Otherwise, the scene appears largely unchanged, with the graded area and parked machinery remaining in place.
      6:00 AM PT

      A small piece of heavy equipment has shifted position in the center of the site, moving slightly to the right. Otherwise, the scene appears largely unchanged, with the graded area and parked machinery remaining in place.

    5. Construction camera frame at 5:45 AM PT. The site is now illuminated, revealing machinery and graded earth where darkness was before. Conditions remain steady with no apparent movement of equipment or vehicles across the block.
      5:45 AM PT

      The site is now illuminated, revealing machinery and graded earth where darkness was before. Conditions remain steady with no apparent movement of equipment or vehicles across the block.

    6. Construction camera frame at 5:00 AM PT. No construction activity — the site is quiet.
      5:00 AM PT

      No construction activity — the site is quiet.

    7. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    8. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    9. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    10. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    11. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.