Skip to content
606Onni 606 · Bellevue
  • Live
  • Progress
  • Project
  • History
  • Search
606

606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /Sunday, September 6, 2026

Construction log

Sunday, September 6, 2026

65 snapshots from the live camera.


AI digest

The site remained largely quiet, with most machinery and materials holding position; a few machines shifted slightly, and trucks briefly entered and left via the left driveway. Between the week-old reference and today’s frames, the central graded area appears largely unchanged.

▶ Play this day as a timelapse
  1. Construction camera frame at 11:00 PM PT. No construction activity — the site is quiet.
    11:00 PM PT

    No construction activity — the site is quiet.

  2. 6 similar no-change frames7:15 PM–10:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 10:00 PM PT. No construction activity — the site is quiet.
      10:00 PM PT

      No construction activity — the site is quiet.

    2. Construction camera frame at 9:00 PM PT. No construction activity — the site is quiet.
      9:00 PM PT

      No construction activity — the site is quiet.

    3. Construction camera frame at 8:00 PM PT. No construction activity — the site is quiet.
      8:00 PM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 7:45 PM PT. Equipment positions across the site are holding steady, with no visible movement in the last quarter hour.
      7:45 PM PT

      Equipment positions across the site are holding steady, with no visible movement in the last quarter hour.

    5. Construction camera frame at 7:30 PM PT. The site maintains a consistent appearance, with the positioning of machinery and materials showing no noticeable alterations in the last fifteen minutes.
      7:30 PM PT

      The site maintains a consistent appearance, with the positioning of machinery and materials showing no noticeable alterations in the last fifteen minutes.

    6. Construction camera frame at 7:15 PM PT. The scene is quiet, with no apparent changes to the location of equipment or materials since the last check-in.
      7:15 PM PT

      The scene is quiet, with no apparent changes to the location of equipment or materials since the last check-in.

  3. Construction camera frame at 7:00 PM PT. A small, dark-colored machine has moved from the right side of the central graded area toward the lower-center of the frame. Otherwise, the equipment and materials on site hold their positions.
    7:00 PM PT

    A small, dark-colored machine has moved from the right side of the central graded area toward the lower-center of the frame. Otherwise, the equipment and materials on site hold their positions.

  4. Construction camera frame at 6:45 PM PT. The arrangement of equipment across the site remains much the same as it was fifteen minutes ago.
    6:45 PM PT

    The arrangement of equipment across the site remains much the same as it was fifteen minutes ago.

  5. Construction camera frame at 6:30 PM PT. The site appears remarkably stable, with no discernible shifts in equipment or material placement over the last fifteen minutes.
    6:30 PM PT

    The site appears remarkably stable, with no discernible shifts in equipment or material placement over the last fifteen minutes.

  6. Construction camera frame at 6:15 PM PT. The scene appears largely still, with equipment maintaining its previous arrangement across the site.
    6:15 PM PT

    The scene appears largely still, with equipment maintaining its previous arrangement across the site.

  7. 2 similar no-change frames5:45 PM–6:00 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:00 PM PT. A white pickup truck has entered the site via the driveway on the left side of the frame. Otherwise, the arrangement of equipment and materials appears unchanged from fifteen minutes ago.
      6:00 PM PT

      A white pickup truck has entered the site via the driveway on the left side of the frame. Otherwise, the arrangement of equipment and materials appears unchanged from fifteen minutes ago.

    2. Construction camera frame at 5:45 PM PT. The site's overall layout remains consistent, showing no significant movement of equipment or materials in the intervening time.
      5:45 PM PT

      The site's overall layout remains consistent, showing no significant movement of equipment or materials in the intervening time.

  8. Construction camera frame at 5:30 PM PT. Shadows have lengthened across the site, but the positioning of the machines and materials appears static.
    5:30 PM PT

    Shadows have lengthened across the site, but the positioning of the machines and materials appears static.

  9. Construction camera frame at 5:15 PM PT. The equipment on the right side of the frame has shifted slightly, with one machine now positioned further forward. Otherwise, the site maintains a similar appearance to the previous view.
    5:15 PM PT

    The equipment on the right side of the frame has shifted slightly, with one machine now positioned further forward. Otherwise, the site maintains a similar appearance to the previous view.

  10. Construction camera frame at 5:00 PM PT. The red vehicle previously visible near the left edge of the frame is no longer present. Otherwise, the machinery and materials maintain their positions across the site.
    5:00 PM PT

    The red vehicle previously visible near the left edge of the frame is no longer present. Otherwise, the machinery and materials maintain their positions across the site.

  11. 4 similar no-change frames4:00 PM–4:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 4:45 PM PT. The site holds a consistent appearance, with no noticeable alterations to the placement of machinery or materials over the last fifteen minutes.
      4:45 PM PT

      The site holds a consistent appearance, with no noticeable alterations to the placement of machinery or materials over the last fifteen minutes.

    2. Construction camera frame at 4:30 PM PT. The site appears quiet, with no shifts in the positions of the equipment or materials visible in the last quarter of an hour.
      4:30 PM PT

      The site appears quiet, with no shifts in the positions of the equipment or materials visible in the last quarter of an hour.

    3. Construction camera frame at 4:15 PM PT. The scene is largely unchanged, with the same machinery visible in the same locations as the previous view.
      4:15 PM PT

      The scene is largely unchanged, with the same machinery visible in the same locations as the previous view.

    4. Construction camera frame at 4:00 PM PT. The arrangement of equipment across the site remains consistent, showing no movement in the last fifteen minutes.
      4:00 PM PT

      The arrangement of equipment across the site remains consistent, showing no movement in the last fifteen minutes.

  12. Construction camera frame at 3:45 PM PT. A red truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment arrangement appears stable, with no other noticeable changes in position.
    3:45 PM PT

    A red truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment arrangement appears stable, with no other noticeable changes in position.

  13. 2 similar no-change frames3:15 PM–3:30 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 3:30 PM PT. The overall scene remains remarkably steady, with no discernible shifts in the positions of equipment or materials.
      3:30 PM PT

      The overall scene remains remarkably steady, with no discernible shifts in the positions of equipment or materials.

    2. Construction camera frame at 3:15 PM PT. The site presents a static view, with no apparent shifts in equipment locations or ongoing work.
      3:15 PM PT

      The site presents a static view, with no apparent shifts in equipment locations or ongoing work.

  14. Construction camera frame at 3:00 PM PT. Activity on site is minimal, as the arrangement of machinery and materials remains consistent between views.
    3:00 PM PT

    Activity on site is minimal, as the arrangement of machinery and materials remains consistent between views.

  15. 3 similar no-change frames2:15 PM–2:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 2:45 PM PT. The site appears unchanged, with all visible equipment holding its position from the previous view.
      2:45 PM PT

      The site appears unchanged, with all visible equipment holding its position from the previous view.

    2. Construction camera frame at 2:30 PM PT. The scene shows no notable differences, with all equipment remaining in the same positions as fifteen minutes ago.
      2:30 PM PT

      The scene shows no notable differences, with all equipment remaining in the same positions as fifteen minutes ago.

    3. Construction camera frame at 2:15 PM PT. The site maintains a consistent appearance, with no visible movement of machinery or materials in the last fifteen minutes.
      2:15 PM PT

      The site maintains a consistent appearance, with no visible movement of machinery or materials in the last fifteen minutes.

  16. Construction camera frame at 2:00 PM PT. Shadows have subtly lengthened across the site, but the positions of equipment and materials appear to be the same.
    2:00 PM PT

    Shadows have subtly lengthened across the site, but the positions of equipment and materials appear to be the same.

  17. 2 similar no-change frames1:30 PM–1:45 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 1:45 PM PT. The scene is holding steady, with no discernible changes to the arrangement of equipment or activity on the site.
      1:45 PM PT

      The scene is holding steady, with no discernible changes to the arrangement of equipment or activity on the site.

    2. Construction camera frame at 1:30 PM PT. The overall scene remains stable, with no apparent shifts in the locations of machines or materials.
      1:30 PM PT

      The overall scene remains stable, with no apparent shifts in the locations of machines or materials.

  18. Construction camera frame at 1:15 PM PT. Equipment positions remain consistent across the site, with only subtle shifts in shadow patterns occurring during this period.
    1:15 PM PT

    Equipment positions remain consistent across the site, with only subtle shifts in shadow patterns occurring during this period.

  19. Construction camera frame at 1:00 PM PT. The site appears unchanged from the previous view, with equipment remaining in the same locations and shadows continuing to shift.
    1:00 PM PT

    The site appears unchanged from the previous view, with equipment remaining in the same locations and shadows continuing to shift.

  20. Construction camera frame at 12:45 PM PT. The arrangement of machines and materials across the site appears consistent between these frames, though shadows have continued to lengthen.
    12:45 PM PT

    The arrangement of machines and materials across the site appears consistent between these frames, though shadows have continued to lengthen.

  21. 4 similar no-change frames11:45 AM–12:30 PM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 12:30 PM PT. The site maintains its current appearance, with no visible alterations to the equipment or materials within the frame.
      12:30 PM PT

      The site maintains its current appearance, with no visible alterations to the equipment or materials within the frame.

    2. Construction camera frame at 12:15 PM PT. The scene presents a consistent view, with no observable movement of equipment or vehicles during this interval.
      12:15 PM PT

      The scene presents a consistent view, with no observable movement of equipment or vehicles during this interval.

    3. Construction camera frame at 12:00 PM PT. A white vehicle is now entering the site via the driveway on the left side of the frame. Beyond that, the arrangement of equipment and materials appears unchanged.
      12:00 PM PT

      A white vehicle is now entering the site via the driveway on the left side of the frame. Beyond that, the arrangement of equipment and materials appears unchanged.

    4. Construction camera frame at 11:45 AM PT. The scene remains largely static, with the equipment and materials holding their previous positions under the lengthening shadows.
      11:45 AM PT

      The scene remains largely static, with the equipment and materials holding their previous positions under the lengthening shadows.

  22. Construction camera frame at 11:30 AM PT. A yellow machine has shifted position slightly within the central area of the site. Otherwise, the equipment and materials appear to remain in place, and shadows continue to lengthen.
    11:30 AM PT

    A yellow machine has shifted position slightly within the central area of the site. Otherwise, the equipment and materials appear to remain in place, and shadows continue to lengthen.

  23. Construction camera frame at 11:15 AM PT. The shadows have shifted slightly across the graded area, but the equipment and materials remain in the same positions.
    11:15 AM PT

    The shadows have shifted slightly across the graded area, but the equipment and materials remain in the same positions.

  24. Construction camera frame at 11:00 AM PT. The scene appears remarkably still, with no discernible shifts in equipment or material placement across the site.
    11:00 AM PT

    The scene appears remarkably still, with no discernible shifts in equipment or material placement across the site.

  25. Construction camera frame at 10:45 AM PT. A small, light-blue machine is now visible among the other equipment near the center of the site; it wasn't present in the earlier view. The rest of the scene, including the red structure and the arrangement of materials, appears constant.
    10:45 AM PT

    A small, light-blue machine is now visible among the other equipment near the center of the site; it wasn't present in the earlier view. The rest of the scene, including the red structure and the arrangement of materials, appears constant.

  26. Construction camera frame at 10:30 AM PT. The arrangement of equipment appears largely the same, though a small, light-colored object is now visible near the center of the graded area.
    10:30 AM PT

    The arrangement of equipment appears largely the same, though a small, light-colored object is now visible near the center of the graded area.

  27. Construction camera frame at 10:15 AM PT. A small red structure has appeared near the center of the site, adjacent to the large pile of earth-toned material. The rest of the scene remains unchanged, with equipment and vehicles holding their prior positions.
    10:15 AM PT

    A small red structure has appeared near the center of the site, adjacent to the large pile of earth-toned material. The rest of the scene remains unchanged, with equipment and vehicles holding their prior positions.

  28. Construction camera frame at 10:00 AM PT. The site holds steady, with all visible machines and materials maintaining their previous arrangement.
    10:00 AM PT

    The site holds steady, with all visible machines and materials maintaining their previous arrangement.

  29. Construction camera frame at 9:45 AM PT. A blue truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment and materials within the block appear to be in the same locations.
    9:45 AM PT

    A blue truck has entered the site via the driveway on the left side of the frame. Otherwise, the equipment and materials within the block appear to be in the same locations.

  30. Construction camera frame at 9:30 AM PT. The scene remains stable, with equipment and materials appearing in the same positions as before.
    9:30 AM PT

    The scene remains stable, with equipment and materials appearing in the same positions as before.

  31. Construction camera frame at 9:15 AM PT. The arrangement of machinery in the center of the site has subtly altered, with one yellow piece of equipment appearing to have rotated. Otherwise, the scene presents a familiar picture, with no other notable shifts in equipment or vehicle positions.
    9:15 AM PT

    The arrangement of machinery in the center of the site has subtly altered, with one yellow piece of equipment appearing to have rotated. Otherwise, the scene presents a familiar picture, with no other notable shifts in equipment or vehicle positions.

  32. Construction camera frame at 9:00 AM PT. A yellow machine has shifted position within the central area of the site. Otherwise, the scene remains consistent, with no other visible changes to equipment or vehicle locations.
    9:00 AM PT

    A yellow machine has shifted position within the central area of the site. Otherwise, the scene remains consistent, with no other visible changes to equipment or vehicle locations.

  33. 2 similar no-change frames8:30 AM–8:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:45 AM PT. The site continues in a stable condition, with no discernible movement of equipment or vehicles between these views.
      8:45 AM PT

      The site continues in a stable condition, with no discernible movement of equipment or vehicles between these views.

    2. Construction camera frame at 8:30 AM PT. The site appears largely unchanged, with all visible machinery and materials holding their previous positions.
      8:30 AM PT

      The site appears largely unchanged, with all visible machinery and materials holding their previous positions.

  34. Construction camera frame at 8:15 AM PT. The site maintains its quiet state, with no equipment shifts or new activity apparent in this comparison.
    8:15 AM PT

    The site maintains its quiet state, with no equipment shifts or new activity apparent in this comparison.

  35. 4 similar no-change frames7:15 AM–8:00 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 8:00 AM PT. Everything on site appears to be holding its position, with no noticeable changes in the layout of equipment or materials.
      8:00 AM PT

      Everything on site appears to be holding its position, with no noticeable changes in the layout of equipment or materials.

    2. Construction camera frame at 7:45 AM PT. The site holds a consistent appearance, with no apparent alterations to the machinery or materials in either view.
      7:45 AM PT

      The site holds a consistent appearance, with no apparent alterations to the machinery or materials in either view.

    3. Construction camera frame at 7:30 AM PT. The view across the site remains remarkably steady, with no visible shifts in the placement of equipment or vehicles.
      7:30 AM PT

      The view across the site remains remarkably steady, with no visible shifts in the placement of equipment or vehicles.

    4. Construction camera frame at 7:15 AM PT. The scene presents a familiar view, with all equipment remaining in the same positions as fifteen minutes ago.
      7:15 AM PT

      The scene presents a familiar view, with all equipment remaining in the same positions as fifteen minutes ago.

  36. Construction camera frame at 7:00 AM PT. The arrangement of equipment on the site remains consistent between these views, showing no movement or new arrivals.
    7:00 AM PT

    The arrangement of equipment on the site remains consistent between these views, showing no movement or new arrivals.

  37. 9 similar no-change frames12:00 AM–6:45 AM PT

    No visible change was reported between sampled frames; continuous inactivity cannot be inferred.

    1. Construction camera frame at 6:45 AM PT. The scene appears static, with no discernible changes in equipment positions or activity over the last fifteen minutes.
      6:45 AM PT

      The scene appears static, with no discernible changes in equipment positions or activity over the last fifteen minutes.

    2. Construction camera frame at 6:30 AM PT. The site is now visible in daylight, revealing several pieces of machinery positioned across the graded area. The scene remains largely unchanged from 15 minutes ago, with the same equipment visible in the same locations.
      6:30 AM PT

      The site is now visible in daylight, revealing several pieces of machinery positioned across the graded area. The scene remains largely unchanged from 15 minutes ago, with the same equipment visible in the same locations.

    3. Construction camera frame at 6:00 AM PT. No construction activity — the site is quiet.
      6:00 AM PT

      No construction activity — the site is quiet.

    4. Construction camera frame at 5:00 AM PT. No construction activity — the site is quiet.
      5:00 AM PT

      No construction activity — the site is quiet.

    5. Construction camera frame at 4:00 AM PT. No construction activity — the site is quiet.
      4:00 AM PT

      No construction activity — the site is quiet.

    6. Construction camera frame at 3:00 AM PT. No construction activity — the site is quiet.
      3:00 AM PT

      No construction activity — the site is quiet.

    7. Construction camera frame at 2:00 AM PT. No construction activity — the site is quiet.
      2:00 AM PT

      No construction activity — the site is quiet.

    8. Construction camera frame at 1:00 AM PT. No construction activity — the site is quiet.
      1:00 AM PT

      No construction activity — the site is quiet.

    9. Construction camera frame at 12:00 AM PT. No construction activity — the site is quiet.
      12:00 AM PT

      No construction activity — the site is quiet.

← Sep 5All daysSep 7 →