Skip to content
606Independent guide, Bellevue
  • Live
  • Progress
  • Project
  • History
  • Search
606

606 (& 620) 106th Ave NE, Bellevue, WA

An independent guide to the Onni 606 development.

For the wider city, visit bellevue.wiki ↗

Project

  • Overview
  • Live cam
  • Latest progress
  • Construction log
  • News
  • Permit ledger
  • Construction impacts
  • The Towers
  • Skyline & height
  • Timeline
  • Gallery

Context

  • History of the block
  • Location
  • Developer

Help

  • Search the site
  • FAQ
  • Glossary
  • Sources & press
  • Contact
  • Updates feed
  • Sitemap

This is an independent, informational fan site. It is not affiliated with, sponsored by, or endorsed by Onni Group. Figures are compiled from public reporting and are approximate and subject to change. Project names and trademarks belong to their respective owners.

© 2026 onni606.com — built by an enthusiast.

  1. Home
  2. /Construction log
  3. /September 2026

Construction log

September 2026

30 days on camera and 1,890 snapshots at 606 106th Ave NE. Each day is summarized below. Open one to see every frame.


Start and end of the month

Onni 606 construction site, first frame, Sep 1, 6:15 AM PT
First Sep 1, 6:15 AM PT
Onni 606 construction site, last frame, Sep 30, 7:00 PM PT
Last Sep 30, 7:00 PM PT

Day by day

  1. Tue, Sep 166 snapshots

    The site was largely quiet, with equipment and vehicles holding position for most of the day; a dump truck entered, an excavator briefly raised its boom, and a small wheeled vehicle shifted to the right side. The frames show no substantial change to the ground or site layout compared with the start of the day.

  2. Wed, Sep 266 snapshots

    The site was largely quiet, with equipment staying in place and no clear change to the graded area. A red truck and a white van were reported entering during the day; the first and last frames show little visible difference.

  3. Thu, Sep 364 snapshots

    A red portable office appeared near the center-left of the site, and a few vehicles entered and exited throughout the day, but otherwise, the site remained largely static with no significant changes in equipment positions or ground appearance.

  4. Fri, Sep 465 snapshots

    The site was largely quiet, with equipment and the graded area mostly holding steady through the day. A crane appeared near the rear-right and later extended its boom toward the street; several vehicles entered, but no substantial ground change is evident.

  5. Sat, Sep 565 snapshots

    The site was largely quiet, with the heavy equipment mostly holding position; a small red vehicle and a white pickup entered from the left and parked near the yellow machinery. Between the first and last frames, no substantial change to the ground or equipment layout is apparent.

  6. Sun, Sep 665 snapshots

    The site remained largely quiet, with most machinery and materials holding position; a few machines shifted slightly, and trucks briefly entered and left via the left driveway. Between the week-old reference and today’s frames, the central graded area appears largely unchanged.

  7. Mon, Sep 765 snapshots

    The site remained quiet, with the equipment layout and graded ground appearing unchanged in the day’s frames. A white pickup and small red vehicle entered the work area, and a light-colored vehicle later moved toward the left driveway; no substantial ground or equipment changes were visible.

  8. Tue, Sep 865 snapshots

    Earth was visibly shifted during the day: a broad dark strip of soil now crosses the central area, with machinery positioned along it and at its left end. A fire truck briefly entered and left; other small vehicles appeared, but no further ground change was noted.

  9. Wed, Sep 965 snapshots

    The site’s ground surface and equipment layout appear largely unchanged from the September 2 reference; no substantial progress is evident across the day. A red truck entered from the left, and a small vehicle and people were briefly visible on site.

  10. Thu, Sep 1065 snapshots

    The site remained broadly unchanged through the day, with small vehicles and trucks moving in and out and equipment shifting around the central area. The final frame uses a different camera angle, so it does not establish a clear change to the ground.

  11. Fri, Sep 1162 snapshots

    The site remained largely quiet, with only small vehicles appearing and a piece of machinery shifting slightly. The final frame shows no clear substantial change to the ground or site layout.

  12. Sat, Sep 1264 snapshots

    The site was largely quiet, with no clear ground or equipment changes visible during the day. A yellow dump truck entered through the left driveway, but no further movement was noted.

  13. Sun, Sep 1363 snapshots

    Visibility is too low to assess construction activity.

  14. Mon, Sep 1464 snapshots

    A yellow machine moved from the center of the site to the lower right corner. Otherwise, no significant changes were visible on site today.

  15. Tue, Sep 1563 snapshots

    A large volume of earth has been moved, creating a new, distinct, and deep depression in the center-right of the site, and a new, large, and high mound of earth in the center-left. Several yellow machines and a dark-colored vehicle moved around the site throughout the day.

  16. Wed, Sep 1664 snapshots

    The site’s central cut appears broader and more clearly defined by day’s end, with a light-colored graded area and a dark patch visible near the middle. Yellow machines shifted around the site, but no other substantial change is apparent.

  17. Thu, Sep 1764 snapshots

    A small utility vehicle moved on site, and two other vehicles, including a red truck, entered the site throughout the day.

  18. Fri, Sep 1863 snapshots

    A yellow excavator moved to the southeast corner of the site, and a red and white truck entered the site. The overall site appearance, including the central mound of dark earth, remained unchanged.

  19. Sat, Sep 1962 snapshots

    The site was quiet, with no visible changes during the day. Compared with the September 12 frame, the central cut is larger; the supplied frames do not show a clear change from the start to the end of September 19.

  20. Sun, Sep 2061 snapshots

    Visibility is too low to assess construction activity.

  21. Mon, Sep 2162 snapshots

    The larger central cut and graded areas visible on September 14 are already present in the day’s first frame, with no substantial ground change apparent by the last. A yellow excavator moved to the lower-right corner during the day; otherwise activity was quiet.

  22. Tue, Sep 2262 snapshots

    The large blue machine near the center of the site extended its boom upward, and a red truck entered the site. Otherwise, a small piece of equipment moved from the lower-left to the center of the site, and the blue machine near the center shifted position slightly.

  23. Wed, Sep 2362 snapshots

    The site remained largely quiet, with no clear change to the ground visible during the day. A small vehicle moved across the central dark area, an excavator shifted slightly on the right, and another vehicle entered from the left driveway.

  24. Thu, Sep 2460 snapshots

    The central cut appears broader and more defined than in the September 17 reference, with a long dark strip of material or ground visible across it; the day’s first and last frames show no clear additional change in its shape. During the day, a small yellow machine and an excavator changed positions, and workers were briefly visible near the center.

  25. Fri, Sep 2561 snapshots

    The site remained largely quiet, with no clear major change in the ground or new structure visible. A yellow machine shifted from the lower-left toward the lower-center; several vehicles and machines were present, but no sustained activity is apparent.

  26. Sat, Sep 2662 snapshots

    The site remained largely unchanged, with no clear ground-shape change during the day. A yellow vehicle shifted from the lower-left toward center-left, while several machines gathered near the lower-left street edge.

  27. Sun, Sep 2758 snapshots

    Visibility is too low to assess construction activity.

  28. Mon, Sep 2862 snapshots

    Standing water is visible in the large central work area, with construction equipment around the site; compared with September 21, the central area appears darker and wetter. No clear change is visible between the day’s first and last frames.

  29. Tue, Sep 2960 snapshots

    The site remained largely quiet, with no clear substantial ground change visible during the day. A small piece of equipment shifted toward the right, and a white vehicle moved to the lower-right; several vehicles were visible along the left edge.

  30. Wed, Sep 3060 snapshots

    The central area remained largely unchanged from last week, with no substantial ground or structural progress visible; a small blue machine shifted position during the day. A few people appeared briefly, and a small amount of water pooled in the central area.