Construction log
31 days on camera and 1,792 snapshots at 606 106th Ave NE. Each day is summarized below. Open one to see every frame.
Standing water appeared in the central area during the day; otherwise, the site and equipment showed no notable change. Compared with September 24, the central area is visibly wetter, with no clear new structural work.
Visibility improved enough to show vehicles and equipment across the site, but no substantial ground change is apparent over the day. A small orange vehicle shifted to the lower-right, and a red vehicle moved into the central area; otherwise activity was quiet.
The site appears largely unchanged from the September 26 reference, with the central cut and surrounding earthwork area still visible. The day’s observations report no visible changes, and the first frame is obscured, so no further progress can be confirmed.
Visibility is too low to assess construction activity.
The site was obscured by haze for much of the day, then became visible; the final view shows the existing cut and equipment, with no clear substantial change to the ground. A yellow excavator and other small vehicles shifted around the site, and a blue machine was visible beside the steel beams; activity otherwise appeared quiet.
The central cut and surrounding graded areas look broadly unchanged from the week-earlier frame. A small red vehicle moved across the site, and light-colored vehicles appeared during the day; no substantial ground change is evident.
A tall, slender rig was set up near the center of the site during the day, and a blue truck moved into the central area. Otherwise, the frames show no clear change to the ground or site layout; activity appears quiet.
Fog and haze obscured the site early, but the clearer final view shows no substantial change to the ground or equipment during the day. A small red container appeared near the center of the cut; the rest of the activity was quiet.
The site remained largely unchanged through the day. A blue machine moved into view near the left edge, and a truck entered via the left driveway; no substantial change to the ground or site layout is apparent.
The site was largely quiet, with no clear change to the ground or materials visible over the day. The central tall-mast rig’s boom shifted slightly down and then up; no other substantial activity is apparent.
Visibility is too low to assess construction activity.
The site’s graded surface and equipment layout appear largely unchanged from the week-earlier frame, with no clear substantial ground change over the day. Several machines and vehicles were visible; a blue-and-white utility vehicle and a red truck entered through the left driveway, and another red truck appeared on the right-side service road.
The site remained largely unchanged through the day, with a few small vehicles and a white van and pickup moving onto the block. Compared with October 6, the central cut appears larger, but there was no clear substantial ground change between today’s first and last frames.
Several vehicles repositioned across the site during the day: a red truck entered from the left driveway, and a yellow machine moved in from the right side toward the center. The ground layout appears broadly unchanged from the earlier reference frame.
The blue crane shifted position and extended its boom across the site; a cable later stretched toward the lower-right, with intermittent dust rising near the red piping. A truck entered through the left driveway, but the ground and overall site layout show no clear substantial change.
The site remained largely unchanged through the day, with several machines visible and no substantial ground or material movement apparent. A small yellow machine shifted toward the lower right, and a white car entered from the left driveway.
The site remained largely unchanged through the day, with no clear ground or material movement visible. Several machines and vehicles were on site, but the frames show no substantial progress.
Visibility is too low to assess construction activity.
Several machines shifted around the site during the day, and trucks entered from the left-side driveway; no substantial change to the ground or site layout is apparent. Compared with October 12, the block remains broadly similar, with equipment and materials in different positions.
Several cranes and other equipment were visible across the site by day’s end, with a small yellow vehicle and a dark truck shifting position during the day. The frames show no clear substantial change to the graded ground or site layout compared with the earlier reference.
The site remained largely unchanged from the prior week, with several machines and vehicles on the graded ground; a red truck and white pickup entered, and a yellow machine shifted position during the day. A small pool of water appeared near the center, while the crane was raised slightly.
The site remained largely quiet, with heavy machinery and vehicles parked across the block; one yellow machine shifted slightly along the right side during the day. Compared with October 15, the ground layout and equipment positions appear broadly similar, with no clear substantial change visible.
The site remained largely unchanged through the day, with heavy equipment shifting position and trucks moving in and out. By the last frame, a small red container was visible near the center; no substantial change to the ground is apparent.
The site was quiet, with no visible changes during the day. Compared with the week-earlier frame, the muddy water area and equipment layout appear broadly unchanged.
Visibility is too low to assess construction activity.
Quiet day on the Onni 606 site: machinery shifted around the central water pool and a tall blue crane appeared near it, but no substantial change in ground shape or new structure is visible across the first and last frames.
Machinery shuffled around the site throughout the day, with the blue crane near top center swinging upright beside the mast rig and several excavators repositioning, but no vehicles were clearly entering or leaving the driveway or service road. Comparing the first and last frames, the ground and built-up area look essentially unchanged, with no substantial new earth movement or structure visible.
Machines were active across the block throughout the day, with excavators and dump trucks repositioning and a fresh spoil pile at the upper right being worked and then partly cleared. Comparing the first and last frames against the week-earlier baseline, the ground surface looks broadly similar and no new structure or large change in site shape is clearly visible, and no vehicles are clearly entering or leaving through the driveway or service road
Earthwork continued quietly on the Onni 606 site on October 29, with the central rig and lower-center excavator in place and only repositioning of trucks and yellow excavators along the edges, plus a blue crawler crane that was swung and moved across the site during the day. Frames from the start and end of the day show the same broad ground layout, so no large new volume of earth moved or new structure is visible, and light fading into
Quiet day on the Onni 606 site: machines were repositioned around the block and a cement mixer and a few workers came and went, but the ground itself shows no clear new earthwork. Comparing the first and last frames against the October 23 baseline, the central pile-rig area and the surrounding dirt look essentially unchanged, and no new structure is taking shape. Lighting shifted from dusk blue to da
Over the day, the most visible change was fresh spoil being spread and built up along the left edge near the street, with a pale mound widening there, while a small excavator on the left slope and a few parked vehicles shifted position. Elsewhere the mid-block drill rig, trucks, and tall blue crane stayed in place, and the upper-right yellow machines were partly rearranged, though much of the surface difference reflects