Results for “Hotel”
Is there a hotel? →
Yes. The June 2022 approval places 257 hotel rooms in Tower 1 alongside residences. The 2019 SEPA checklist modeled 317 suites, and April 2026 reporting described over 400; those different evidence versions should not be blended. Pending land-use application 26-106943-LJ would move the hotel into…
/faqWhat is the Level hotel? →
Level is Onni's own brand of furnished suites — apartment-style rooms with full kitchens and in-suite laundry, for both nightly and extended (30-plus-night) stays. It's an aparthotel hybrid rather than a conventional hotel flag, which is why the 606 hotel component is described as 'suites' and…
/faqTower 1 — Hotel + Residential →
Tower 1 is the hotel + residential tower: 53 stories, about 600 ft tall, a tapered slab. Hotel rooms: 257 approved; Residences: 425 approved; Stories: 53. Vertical program: Residences — 425 homes in the 2022 approval; Hotel — 257 rooms in the 2022 approval; Podium — Lobby, retail & amenity base.
/towersNews (2026-06-20): Onni proposes reshuffling the towers — moving the hotel from Tower 1 to Tower 3 →
News article published 2026-06-20 — Onni proposes reshuffling the towers — moving the hotel from Tower 1 to Tower 3. A pending City of Bellevue application (26-106943-LJ) would comprehensively reconfigure Onni 606, most notably relocating the hotel. It is filed but not yet approved. A City of…
/news/2026-06-reconfiguration-hotel-tower-1-to-tower-3What is Onni 606? →
Onni 606 is a three-tower, mixed-use development under construction at 606 106th Ave NE in Downtown Bellevue, Washington. The approved program combines apartments, a hotel and offices on a shared podium and has been billed by local reporting as the largest construction project in Washington State.
/faqIs it spelled "Onni" or "Omni" Bellevue? →
"Onni" — after Onni Group, the project's developer. "Omni Bellevue" is a common misspelling (likely confused with the unrelated Omni Hotels brand); the development itself has no connection to Omni Hotels.
/faqHow much office space is there? →
The June 2022 approval places 871,818 square feet of office and a 9,532-square-foot daycare in Tower 3. The 2019 SEPA checklist and April 2026 reporting use about 896,000 square feet, while the pending reconfiguration would reduce the office program to make room for the relocated hotel. No amended…
/faqHow do I rent, book, or lease at Onni 606 — and what will it be called? →
You can't yet, and there is no public marketing name. At the August 24, 2026 review, the project was in earthwork and the apartments and hotel rooms were not leasing, booking or pre-leasing. No sales or reservation channel has been announced. There's also no separate brand name: public coverage…
/faqAre the three towers staggered, or all the same height? →
They are essentially the same height, not staggered. All three rise to roughly 600 feet — the maximum Downtown Bellevue allows — so the roofline is even rather than stepped. What differs is the footprint and story count: about 53 stories for the hotel-and-residential tower (a tapered slab), 54 for…
/faqWhich tower will be built first? →
The last published sequence is podium first, then Tower 2, Tower 1 and Tower 3. Onni stated that order in the 2022 design-review record, and the current permit posture still makes Tower 2 the least blocked: Tower 1 and Tower 3 are held pending the 2026 proposal that moves the hotel between them,…
/faqWhat is the total construction cost of Onni 606? →
An Onni project lead has published one historical estimate: in a July 2022 project entry, senior development manager Brendan Lawrence listed a $1.47 billion cost and $2.1 billion projected value at stabilization. That snapshot described an earlier 1,043-residence, 269-hotel-suite and nearly…
/faqOnni 606 — by the numbers →
3 Towers (on a shared podium); ≈600 ft Max height (each tower); 1,059 Residences (2022 approved baseline); 257 Hotel rooms (2022 approved: Tower 1); 871,818 sf Office (2022 approved: Tower 3); 1,712 Parking stalls (across five below-grade levels).
/Approved tower program vs. pending 2026 redesign →
As of August 22, 2026, land-use permit 26-106943-LJ is Pending — not approved. Approved plan — Tower 1: 257 hotel rooms + 425 residences; Tower 2: 634 residences; Tower 3: 871,818 sf office + 9,532 sf daycare. Proposed plan — Tower 1: Residential program; hotel removed; Tower 2: All-residential…
/towersTower levels and story counts — Tower 1 →
As of August 22, 2026. Published program: The 2022 design-approval record reports 53 stories, 425 residences and 257 hotel rooms. A separate 2019 SEPA checklist uses 317 suites, while April 2026 reporting describes more than 400; neither replaces the approved count without an amended schedule.…
/towersTower levels and story counts — Tower 2 →
As of August 22, 2026. Published program: The 2022 design-approval record reports 54 stories and 634 residences. A separate 2019 environmental worksheet models 1,289 residences project-wide, but the public text reviewed here does not assign that total between the towers. Permit scope: 25-105109-BB…
/towersTower levels and story counts — Tower 3 →
As of August 22, 2026. Published program: The 2022 design-approval record reports 45 stories and 871,818 square feet of office. The 2019 environmental worksheet uses 894,500 square feet; current project coverage rounds the office program to about 896,000 square feet plus a 9,532-square-foot…
/towersTower program record — Design approval →
June 23, 2022; 19-104024-LP · 19-104023-LD; status Approved. The design-review-era schedule reports 53 / 54 / 45 stories; 1,059 residences split 425 + 634; 257 hotel suites in Tower 1; and 871,818 sf of office in Tower 3. Those figures do not match every input in the 2019 environmental model.
/towersTower program record — Current coverage + proposed reconfiguration →
April–August 2026; Project profile · 26-106943-LJ; status Proposal pending. Current coverage describes more than 1,300 residences, more than 400 hotel suites and about 896,000 sf of office. The pending application would move the hotel to Tower 3 and shrink the office program; neither the coverage…
/towersProject update (Jun 2026) — Reconfiguration proposed →
Jun 2026: A City of Bellevue application (26-106943-LJ), filed April 1, 2026 and still pending, proposes a comprehensive reconfiguration of the development — most notably moving the hotel from Tower 1 to Tower 3. It is not yet approved; the current approved plan still places the hotel in Tower 1. A…
/timelineProject update (Apr 2026) — Project profile published →
Apr 2026: Coverage details the full program — 1,300+ homes, 400+ hotel suites, ~896k sf of office, two pools, a daycare and a 15,000 sf plaza — calling it the largest construction project in Washington State.
/timeline