Project update (Jul 14, 2026) — Slab removal spreads across a much wider work area →
Jul 14, 2026: Photographs taken about 23 hours apart show rapid visible progress: the bounded removal patch seen July 13 has become a long field of broken concrete and exposed shallow subgrade across much of the visible foreground. At least four excavators and a wheel loader are present in the July…
/news/2026-07-14-slab-removal-expands-across-siteWhat hours can construction run at Onni 606? →
The project's SEPA filing commits it to Bellevue's Noise Controls (Bellevue City Code Ch. 9.18). The city's current standard window allows construction noise on non-holiday weekdays from 7 a.m. to 8 p.m. and Saturdays from 8 a.m. to 6 p.m., with construction-site noise prohibited on Sundays and…
/faqWho is doing the concrete work? →
No concrete subcontractor is named in the public permit record yet. The shared-podium building permit (25-105052-BB) lists the contractor only as "OWNER," while Onni says it manages construction in-house and works with specialized subcontractors. Gary Merlino Construction is named for the current…
/faqProject update (Aug 1, 2026) — Completed July report: early earthwork, with deep excavation still gated →
Aug 1, 2026: The human-reviewed completed-month record uses July 13 as its earliest verified comparison visual and July 21 as its latest, without presenting either as a calendar endpoint. Bellevue records through the July 31 cutoff document soil export, a Tower 2 structural revision request and…
/news/2026-07-onni-606-construction-progress-reportProject update (Jul 21, 2026) — Six excavators spread across the early-works area →
Jul 21, 2026: A high-resolution afternoon photograph shows six tracked excavators, a tracked dozer and a water truck across a broader graded area than the July 17 camera frame, which showed four excavators. The northeast slab has been broken into a field of rubble or aggregate and the…
/news/2026-07-21-six-excavators-early-earthwork-expandsProject update (Jun 2026) — Cleanup report No. 19 — fieldwork slated for end of June →
Jun 2026: TRC's Quarterly Progress Report No. 19 to the Department of Ecology (dated June 4, posted June 11) is the first to point at imminent field work: it lists 'preparation for site redevelopment and site characterization activities planned for the end of June 2026' — the next on-site step…
/timelineProject update (Jan 2026) — Cleanup mobilizes — first field work →
Jan 2026: After roughly eighteen quarterly reports of 'no work performed at the site,' crews collect groundwater samples for a dewatering assessment — the first field activity on the contaminated-site cleanup since it was re-enrolled in 2021, and an early sign of mobilization ahead of demolition.
/timelineEnvironmental — Eighteen quarters of “no work performed.” →
The cleanup has a long paper trail and, for years, very little action. Onni first enrolled the block in Ecology's Voluntary Cleanup Program in August 2019, but the state terminated that enrollment in September 2020 after Onni indicated no cleanup was scheduled “in the foreseeable future.” Onni…
/environmentalPermit 21-133872-GD · 22-104918-UE — Early-works package →
Status Issued Dec 23, 2025; Issued Dec 2025 · soil-export conference Jul 28, 2026. The authority now supporting visible earth removal is early-works clear-and-grade permit 21-133872-GD, issued December 23, 2025 with the city description "Early works clear and grade permit for mass excavation." Its…
/permitsConstruction impacts — hours, noise, trucks and access →
A practical guide to the rules around Onni 606's multi-year build — when construction noise is normally allowed, how the excavation may move through Downtown Bellevue, and where to check a closure or report a problem. Standard facts: Weekday noise hours: 7am–8pm (unless a city permit expands them);…
/construction-impactsConstruction impacts — The early work is already under inspection. →
The environmental record commits the project to Puget Sound Clean Air Agency dust rules, sprinklering during demolition, reduced equipment idling and a Temporary Erosion and Sedimentation Control plan. Contaminated soil is handled through an independent cleanup enrolled in Ecology's Expedited…
/construction-impactsConstruction image (July 13, 2026 · 10:18 a.m. PDT) — Slab breaking opens a bounded work area →
Provenance: High-resolution site photograph provided to onni606.com; original retained on the CDN. What it proves: Three excavators were positioned around a sharply bounded slab opening, with fractured material and a water truck visible. Limit: A still image records equipment present, not whether…
/galleryConstruction image (July 21, 2026 · 2:28 p.m. PDT) — Early earthwork spans most of the visible block →
Provenance: High-resolution site photograph provided to onni606.com; original retained on the CDN. What it proves: Six excavators, a dozer and a water truck were visible across a much broader graded and exposed work area. Limit: Different framing and resolution prevent a reliable area or volume…
/galleryNews (2026-08-01): July 2026 progress report: Onni 606 moves into early earthwork →
News article published 2026-08-01 — July 2026 progress report: Onni 606 moves into early earthwork. A completed-month review pairs the verified July 13–21 visual sequence with permit, inspection and environmental records checked through July 31. This human-reviewed report closes the July record at…
/news/2026-07-onni-606-construction-progress-reportNews (2026-07-21): Six excavators spread across Onni 606 as early earthwork expands →
News article published 2026-07-21 — Six excavators spread across Onni 606 as early earthwork expands. A July 21 photograph shows more equipment, a broader graded work area and the northeast slab broken up; Bellevue logged the early-grading permit's second erosion-control inspection a day earlier. A…
/news/2026-07-21-six-excavators-early-earthwork-expandsNews (2026-07-14): Fuel storage, construction power and utility work deepen 606 mobilization →
News article published 2026-07-14 — Fuel storage, construction power and utility work deepen 606 mobilization. Three small Bellevue records point to a more fully equipped jobsite, while the shoring permit still holds the line before the deep dig. The newest filing on the Onni 606 parcel is a narrow…
/news/2026-07-14-fuel-power-utility-permits-mobilizationNews (2026-07-13): Three excavators strip the remaining slab as Onni 606 enters early earthwork →
News article published 2026-07-13 — Three excavators strip the remaining slab as Onni 606 enters early earthwork. A close view shows three excavators breaking and clearing concrete across a widening work area — systematic slab removal, not yet the deep shored dig. A coordinated slab-removal…
/news/2026-07-13-slab-breaking-begins-on-cleared-blockNews (2026-06-11): Cleanup report No. 19 points to on-site fieldwork by the end of June →
News article published 2026-06-11 — Cleanup report No. 19 points to on-site fieldwork by the end of June. TRC's latest quarterly progress report to the Department of Ecology is the first in the series to flag imminent field work on the contaminated 606 site. TRC's Quarterly Progress Report No. 19…
/news/2026-06-cleanup-report-19-fieldwork-end-of-junePublic realm and access — North plaza and midblock connector →
public: A north pedestrian plaza and required east–west connector lead toward the neighboring Symetra public-space network and public-facing food and retail uses. The approval requires an access agreement; its text also refers to posted operating hours, so the recorded agreement will control the…
/designConstruction impacts — The standard window — and the exception process. →
Bellevue's current construction-noise rules allow construction sound from 7 a.m. to 8 p.m. Monday through Friday and from 8 a.m. to 6 p.m. on Saturdays that are not legal holidays. Construction-site noise is not allowed on Sundays or legal holidays under the standard exemption. Those are noise…
/construction-impacts