Results for “Shoring”
Who is the excavation or shoring contractor? →
Bellevue's issued early-works clear-and-grade permit (21-133872-GD) names Gary Merlino Construction Co. as contractor, under Washington license GARYMCC150MW. The separately issued mass-excavation and shoring record (21-134212-BV) now lists ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis…
/faqHas Onni 606 started shoring or the deep garage excavation? →
Bellevue recorded eight pile inspections under issued shoring permit 21-134212-BV from September 28 through October 14, 2026, all marked Ongoing without notes. These follow a September 18 preconstruction entry allowing shoring to start, with later city approval required at the specified east-side…
/faqProject update (Oct 14, 2026) — Eight ongoing pile inspections under the shoring permit →
Oct 14, 2026: Bellevue recorded eight pile inspections from September 28 through October 14 under 21-134212-BV, all marked Ongoing without notes. They extend the shoring field record but do not confirm completion, resolution of the east-side soil-nail condition or a permanent garage start. The…
/news/2026-10-14-shoring-pile-inspectionsProject update (Sep 23, 2026) — Shoring cleared to start as the central cut expands →
Sep 23, 2026: Bellevue's September 18 preconstruction inspection under shoring permit 21-134212-BV says work may start, with a later city approval required for east-side soil nails at the elevation noted by the inspector. September 12–22 camera frames show a broader central cut and a tall-mast rig;…
/news/2026-09-23-shoring-preconstruction-central-cutProject update (Sep 3, 2026) — Mass-excavation and shoring permit issued →
Sep 3, 2026: Bellevue issued mass-excavation and shoring permit 21-134212-BV on September 3. A PSE gas-main street-use permit on the parcel was issued the same day; its public scope does not establish that the work is an Onni critical-path requirement. Permit issuance is a legal milestone, not…
/timelineConstruction phase guide — Perimeter shoring →
03; status Ongoing pile inspections; completion unconfirmed; records 21-134212-BV · issued Sep 3 · pile inspections Sep 28–Oct 14. Visible evidence: Once authorized and mobilized, a continuous earth-retention operation around the excavation edge would be the durable field signal—not simply a drill…
/timelineGlossary: Shoring →
Shoring: Temporary walls and bracing that hold back soil and protect neighbors while a deep hole is excavated.
/glossaryPermit 21-134212-BV — Mass excavation & shoring →
Status Issued; Issued Sep 3 · pile inspections Sep 28–Oct 14, 2026. Bellevue issued mass-excavation and shoring permit 21-134212-BV September 3. Its September 18 building preconstruction inspection is marked Partial with Corrections, but the inspector expressly wrote that shoring may start. The…
/permitsPermit critical path — Shoring issued; full-site grading remains pending →
As of October 14, 2026. Records: 24-104334-GD, 21-134212-BV. Status: Mixed — issued / pending. Bellevue issued the shoring permit September 3. A September 18 preconstruction inspection says shoring may start, with later city approval required on the east side at the soil-nail elevation where no…
/permitsConstruction impacts — Shoring pile inspections are ongoing; full grading remains pending. →
As of October 14, 2026, Comparing dated September 12 and 22 camera frames shows a broader central cut and a tall-mast rig near the north side. The view does not establish that the rig is installing shoring, show a completed support wall, or measure excavation depth. The October 14 parcel record…
/construction-impactsNews (2026-10-14): Eight ongoing pile inspections extend Onni 606's shoring record →
News article published 2026-10-14 — Eight ongoing pile inspections extend Onni 606's shoring record. Bellevue logged pile inspections from September 28 through October 14 under the issued shoring permit; the permanent garage's inspection list remains empty. Bellevue's inspection ledger now records…
/news/2026-10-14-shoring-pile-inspectionsNews (2026-09-23): Bellevue clears shoring start as Onni 606's central cut expands →
News article published 2026-09-23 — Bellevue clears shoring start as Onni 606's central cut expands. A September 18 inspection says shoring may start, with an east-side soil-nail condition; camera frames show a larger cut and new tall-mast equipment. The City of Bellevue has given Onni 606's…
/news/2026-09-23-shoring-preconstruction-central-cutNews (2026-09-03): Onni 606 Mass Excavation and Shoring Permit Issued by City of Bellevue →
News article published 2026-09-03 — Onni 606 Mass Excavation and Shoring Permit Issued by City of Bellevue. The City of Bellevue has issued the mass excavation and shoring permit for the Onni 606 development, a significant step for the three-tower project. The independent tracker onni606.com…
/news/2026-09-03-onni-606-mass-excavation-and-shoring-permit-issued-by-city-of-bellevuNews (2026-08-29): Onni 606 Mass Excavation and Shoring Permit Moves to 'Ready to Issue' Status →
News article published 2026-08-29 — Onni 606 Mass Excavation and Shoring Permit Moves to 'Ready to Issue' Status. The permit for mass excavation and shoring at the Onni 606 development site in Downtown Bellevue has advanced to 'Ready to Issue' status, as indicated by city records. The Onni 606…
/news/2026-08-28-onni-606-mass-excavation-and-shoring-permit-moves-to-ready-to-issue-sNews (2026-08-22): Long steel-beam haul and gas relocation surface as Onni 606 shoring review advances →
News article published 2026-08-22 — Long steel-beam haul and gas relocation surface as Onni 606 shoring review advances. Two August 13 street-use filings cover 64- to 96-foot beam deliveries and a 425-foot PSE gas-main relocation; meanwhile, Bellevue is reviewing Revision 15 of the still-pending…
/news/2026-08-22-steel-beam-haul-gas-relocation-shoring-reviewWho is building Onni 606 — is there a general contractor? →
No third-party general contractor has been publicly named for the overall Onni 606 build. The issued shoring and below-grade permit records now list ONNI 106TH AVE BELLEVUE LLC / Rossano Alessandro De Cotiis as contractor-of-record under registration ONNI11A780MN, while the pending podium permit…
/faqWill Onni 606 actually get built on schedule? →
Onni targeted a July 2026 excavation start and a roughly five-year build. As of October 14, 2026, Bellevue lists eight ongoing pile inspections under the shoring permit from September 28 through October 14. The September 18 condition still calls for later city approval at the specified east-side…
/faqWhen will structural concrete work start at Onni 606? →
No start date for the permanent garage or tower concrete has been announced. Bellevue issued the P2-through-P5 below-grade building permit on September 9, 2026, but its inspection record had no posted inspection at the October 14 check; the separate podium and tower building permits remained…
/faqWhat kind of foundation will support the Onni 606 towers? →
The public-facing record establishes a shared five-level below-grade garage and a separate shoring system for the excavation. It does not clearly establish the final tower foundation design—such as whether the tower bases use a mat, individual footings or deep piles—so a visible drilling rig should…
/faqCan the construction camera identify a rig, pile, or stack of materials? →
The wide camera view can show a machine's general shape, its position and visible change between dated frames. A tall mast is consistent with a drill rig, but it cannot tell whether that rig is doing soil investigation, anchors, piles or shoring. Likewise, orange stacks, drums, bags and wheeled…